US5882366A - Alternating wash/dry water scrubber entry - Google Patents
Alternating wash/dry water scrubber entry Download PDFInfo
- Publication number
- US5882366A US5882366A US08/870,705 US87070597A US5882366A US 5882366 A US5882366 A US 5882366A US 87070597 A US87070597 A US 87070597A US 5882366 A US5882366 A US 5882366A
- Authority
- US
- United States
- Prior art keywords
- line
- gas
- stream
- valve
- lines
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- C—CHEMISTRY; METALLURGY
- C30—CRYSTAL GROWTH
- C30B—SINGLE-CRYSTAL GROWTH; UNIDIRECTIONAL SOLIDIFICATION OF EUTECTIC MATERIAL OR UNIDIRECTIONAL DEMIXING OF EUTECTOID MATERIAL; REFINING BY ZONE-MELTING OF MATERIAL; PRODUCTION OF A HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; SINGLE CRYSTALS OR HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; AFTER-TREATMENT OF SINGLE CRYSTALS OR A HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; APPARATUS THEREFOR
- C30B25/00—Single-crystal growth by chemical reaction of reactive gases, e.g. chemical vapour-deposition growth
- C30B25/02—Epitaxial-layer growth
- C30B25/14—Feed and outlet means for the gases; Modifying the flow of the reactive gases
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01D—SEPARATION
- B01D45/00—Separating dispersed particles from gases or vapours by gravity, inertia, or centrifugal forces
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01D—SEPARATION
- B01D53/00—Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
- B01D53/14—Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by absorption
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J19/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J19/0006—Controlling or regulating processes
- B01J19/002—Avoiding undesirable reactions or side-effects, e.g. avoiding explosions, or improving the yield by suppressing side-reactions
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J19/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J19/26—Nozzle-type reactors, i.e. the distribution of the initial reactants within the reactor is effected by their introduction or injection through nozzles
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J8/00—Chemical or physical processes in general, conducted in the presence of fluids and solid particles; Apparatus for such processes
- B01J8/0015—Feeding of the particles in the reactor; Evacuation of the particles out of the reactor
- B01J8/003—Feeding of the particles in the reactor; Evacuation of the particles out of the reactor in a downward flow
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J8/00—Chemical or physical processes in general, conducted in the presence of fluids and solid particles; Apparatus for such processes
- B01J8/18—Chemical or physical processes in general, conducted in the presence of fluids and solid particles; Apparatus for such processes with fluidised particles
- B01J8/20—Chemical or physical processes in general, conducted in the presence of fluids and solid particles; Apparatus for such processes with fluidised particles with liquid as a fluidising medium
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J8/00—Chemical or physical processes in general, conducted in the presence of fluids and solid particles; Apparatus for such processes
- B01J8/18—Chemical or physical processes in general, conducted in the presence of fluids and solid particles; Apparatus for such processes with fluidised particles
- B01J8/20—Chemical or physical processes in general, conducted in the presence of fluids and solid particles; Apparatus for such processes with fluidised particles with liquid as a fluidising medium
- B01J8/22—Chemical or physical processes in general, conducted in the presence of fluids and solid particles; Apparatus for such processes with fluidised particles with liquid as a fluidising medium gas being introduced into the liquid
-
- C—CHEMISTRY; METALLURGY
- C23—COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
- C23C—COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
- C23C16/00—Chemical coating by decomposition of gaseous compounds, without leaving reaction products of surface material in the coating, i.e. chemical vapour deposition [CVD] processes
- C23C16/44—Chemical coating by decomposition of gaseous compounds, without leaving reaction products of surface material in the coating, i.e. chemical vapour deposition [CVD] processes characterised by the method of coating
- C23C16/4412—Details relating to the exhausts, e.g. pumps, filters, scrubbers, particle traps
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J2219/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J2219/00049—Controlling or regulating processes
- B01J2219/00051—Controlling the temperature
- B01J2219/00074—Controlling the temperature by indirect heating or cooling employing heat exchange fluids
- B01J2219/00076—Controlling the temperature by indirect heating or cooling employing heat exchange fluids with heat exchange elements inside the reactor
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J2219/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J2219/00049—Controlling or regulating processes
- B01J2219/00051—Controlling the temperature
- B01J2219/00074—Controlling the temperature by indirect heating or cooling employing heat exchange fluids
- B01J2219/00087—Controlling the temperature by indirect heating or cooling employing heat exchange fluids with heat exchange elements outside the reactor
- B01J2219/00094—Jackets
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J2219/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J2219/00049—Controlling or regulating processes
- B01J2219/00051—Controlling the temperature
- B01J2219/00132—Controlling the temperature using electric heating or cooling elements
- B01J2219/00135—Electric resistance heaters
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J2219/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J2219/00049—Controlling or regulating processes
- B01J2219/00051—Controlling the temperature
- B01J2219/0015—Controlling the temperature by thermal insulation means
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J2219/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J2219/00049—Controlling or regulating processes
- B01J2219/00164—Controlling or regulating processes controlling the flow
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J2219/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J2219/00049—Controlling or regulating processes
- B01J2219/00245—Avoiding undesirable reactions or side-effects
- B01J2219/00252—Formation of deposits other than coke
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01J—CHEMICAL OR PHYSICAL PROCESSES, e.g. CATALYSIS OR COLLOID CHEMISTRY; THEIR RELEVANT APPARATUS
- B01J2219/00—Chemical, physical or physico-chemical processes in general; Their relevant apparatus
- B01J2219/00049—Controlling or regulating processes
- B01J2219/00245—Avoiding undesirable reactions or side-effects
- B01J2219/00268—Detecting faulty operations
Definitions
- the present invention generally relates to the field of gas stream scrubbing technology. More particularly, the present invention relates to a method and an apparatus for maintaining inlet duct lines of scrubber units free from clogging due to accumulation of particulates and the like.
- cleaning apparatus downstream (relative to the direction of waste flow) of a processing system.
- the function of the cleaning apparatus is to receive and process effluents produced in upstream process operations.
- Scrubbers like the ones employed above, generally include elongated columns that accommodate effluents and subject them to a counter-current contacting with liquid solvents, reactant solutions, or slurries.
- the result of the counter-current contacting is an intimate mixing which assists the absorption process to effect removal of impurities from the effluents.
- Integrated cleaning systems may be built into the manufacturing system to be an integral part of the manufacturing system.
- stand-alone systems are maintained in a housing structure independent from the process or manufacturing system. Although such stand-alone units may be integrated to the process of the upstream equipment, stand-alone units enjoy a greater degree of mobility than their integrated cleaning system counterparts.
- scrubber technology is not limited to integrated cleaning systems but may also be incorporated in stand-alone operation systems. Examples include: a) unheated chemically reacting packed bed dry scrubbers, b) unheated chemisorptive packed bed dry scrubbers, c) heated chemically reacting packed bed dry scrubbers, d) heated catalytically reacting packed bed dry scrubbers, e) wet scrubbers, and f) flame-based thermal treatment units. Each of the aforementioned units is applicable to selected usages depending on the nature of the gas stream undergoing treatment.
- Clogging can be caused by the reaction of silicon bearing in-coming species reacting with water, or water vapor, and depositing droplets of silicon-containing water in the inlet of a scrubber.
- This clog-formation mechanism is present for processes applied to semiconductor tools used for epitaxial growth on wafers and which tend to use trichloro silane and dichloro silane.
- Clogging can also be caused by the condensation deposition of condensable species in the inlet section to a water scrubber.
- Clogging may also be caused by the back-migration of water vapor from a water scrubber into the incoming process line. This back-migrating water vapor can then react with incoming species and form materials with low volatility and result in their depositing in the inlet to a water scrubber.
- This last mechanism is, for example, characteristic of scrubber abatement of tools for the metal etch process.
- an off-gas such as BCl 3 (boron trichloride) may be produced.
- BCl 3 reacts with water vapor to form a non-volatile particulate boric acid which condenses, accumulates, and at least partially clogs inlet ports or inlet lines.
- Another method utilizes the introduction of a mechanical plunger mechanism or other solid removal means to keep the inlet and lines free of solids accumulations.
- mechanical solutions are costly, labor-intensive, require significant maintenance and are susceptible to mechanical breakdown.
- It is another object of the present invention provide such an apparatus and method which prevents the back-migration of process water.
- the present invention relates to an apparatus and method for cleaning inlet lines of a manifold, which conveys a process gas stream to a downstream treatment unit, e.g., a scrubber unit in the case of semiconductor manufacturing effluent gas streams.
- a downstream treatment unit e.g., a scrubber unit in the case of semiconductor manufacturing effluent gas streams.
- the apparatus includes a manifold receiving gas from an upstream source, e.g., a semiconductor manufacturing process system or tool.
- the manifold includes first and second inlet lines, which are alternatingly employed to flow gas to a downstream process. These lines at their first (upstream) ends are joined to a manifold conduit, and each of the first and second inlet lines at their second (downstream) ends are joined in flow communication with the downstream process unit, which may for example comprise a scrubber unit.
- Each of the first and second inlet lines includes a valve therein, e.g., a pneumatic valve, which is selectively openable or closeable to establish or discontinue flow of gas therethrough, respectively.
- a valve therein e.g., a pneumatic valve
- the manifold is arranged to receive gas from the upstream source and to flow the gas through the manifold and either the first or second inlet line, so that one of such lines is actively flowing gas from the upstream source to the downstream process, while the other is blocked by closure of the respective valve therein to flow of the gas therethrough.
- a pressurized water source is coupled with the manifold, by water flow lines to each of the first and second inlet lines.
- Each of the water flow lines contains a valve, e.g., a pneumatic valve.
- Each of the valves is selectively openable or closeable to establish or discontinue flow of pressurized water therethrough, respectively.
- a heat source may be thermally coupled to each of the first and second inlet lines, e.g., by a thermal jacket placed about each of the first and second inlet lines, to selectively elevate the temperature within at least one of the two inlet lines.
- gas from the upstream process flows into the manifold.
- the valve in one of the first and second inlet lines is open, while the valve in the other of the first and second inlet lines is closed, so that the gas entering the manifold is flowed through the specific one of the inlet lines containing the opened valve.
- the gas flows through the specific one of the inlet lines containing the open valve, and passes to the downstream process.
- the inlet line containing the open valve is sometimes hereinafter for ease of reference referred to as the "open inlet line,” while the other inlet line of the manifold is referred to as the "off-stream line.” In the off-stream line, the valve is closed to prevent flow of gas therethrough.
- valves of the inlet lines may be operationally coordinated and controlled by suitable cycle timer means and controls of a common and conventional type, as adapted to the apparatus of the present invention.
- the off-stream line while not flowing gas therethrough, is cleaned to regenerate same for further processing.
- the valves in the respective inlet lines are controlled so that one of such valves is open at any given time, while the other is closed for off-stream cleaning of the line and renewal of the line for subsequent on-stream operation.
- the off-stream line is cleaned by admission of pressurized water from the pressurized water source to the off-stream line by opening of the valve in the water flow line communicating the pressurized water source with the off-stream line.
- the water flow line valve is closed, to prevent the flow of the pressurized water from the water source to the on-stream line.
- a pressurized drying gas source is coupled with the manifold, by drying gas flow lines to each of the first and second inlet lines.
- Each of the drying gas flow lines contains a valve, e.g., a pneumatic valve.
- Each of the valves is selectively openable or closeable to establish or discontinue flow of pressurized drying gas therethrough, respectively.
- the off-stream line may be dried to ready it for subsequent renewed flow of gas from the upstream source to the downstream process. This is effected by closure of the valve in the pressurized water flow line, to discontinue the pressurized water flushing/scrubbing action of the water on the internal surfaces of the off-stream line. Concurrently, the valve in the drying gas flow line communicating with the off-stream line is opened to admit pressurized drying gas into the off stream line for flow therethrough, to dry the interior surfaces of the off-stream line, so that the flushing water is completely removed from the off-stream line of the manifold.
- the off-stream line may be completely dried to avoid hydrolysis reactions in the subsequent operation of the overall system, when process gas flow through the cleaned and dried line is resumed, viz., when the off-stream line again becomes the on-stream line, and the former on-stream line is taken off-line.
- the changeover operation for such sequence involves first opening the valve in the off-stream line to accommodate the subsequent flow of process gas therethrough. Once the valve in the off-stream line is verified open, the valve in the drying gas line is closed. This procedure prevents any occurrence of both valves being simultaneously closed and creating a deadhead condition in the upstream process flow.
- the manifolded gas processing system is operated so that gas is flowed from the upstream source through an inlet line to the downstream process, with the gas flow being alternatingly, and sequentially directed through each of the inlet lines, so that during the off-stream period of a given inlet line, it is being flushed with pressurized water, and optionally, and preferably, dried by flow therethrough of pressurized drying gas, to renew the inlet line for subsequent flow of gas therethrough.
- the water from the pressurized water flush and the pressurized gas drying steps may be flowed through the off-stream inlet line and may be discharged into the water scrubber, or alternatively may be vented from the off-stream line through valved discharge lines dedicated for such purpose.
- the first and second inlet lines may also be provided with associated heating means, such as an electrical resistance heater, stream tracing lines, or heating jackets, by which the drying process may be carried out more rapidly, and/or to provide process heat to otherwise facilitate the cleaning of the inlet lines of the manifold.
- heating means such as an electrical resistance heater, stream tracing lines, or heating jackets, by which the drying process may be carried out more rapidly, and/or to provide process heat to otherwise facilitate the cleaning of the inlet lines of the manifold.
- the present invention relates to a method of flowing a gas from an upstream source to a downstream process through a manifold including two inlet lines through which gas may flow, by the steps of:
- steps (a)-(h) so that during flow of gas from the upstream source to the downstream process, one of the inlet lines has the gas from the upstream source flowed therethrough, and the other of the inlet lines is off-stream, and undergoes high-pressure water flushing and, optionally, drying.
- the process may also optionally be carried out with heating of the inlet lines.
- FIG. 1 is a schematic representation of a system including (1) an upstream semiconductor manufacturing system; (2) a manifold assembly; and (3) a downstream scrubber unit.
- FIG. 2 is a schematic representation of an illustrative embodiment of the invention.
- FIG. 3 is a block diagram of the steps of a cleaning cycle as may be carried out in the illustrative embodiment of FIG. 2.
- FIG. 1 is a schematic representation of system 10 including an upstream system 12 producing an effluent gas, an exit line 14, a manifold duct line 16, first and second inlet lines 18 and 20; and a downstream scrubber unit 50.
- the upstream system which may for example comprise a semiconductor manufacturing facility or semiconductor process tool, is in closed gas flow communication with the scrubber unit via the manifold and inlet lines.
- the exit line, manifold line and inlet lines may have any suitable diameter, e.g., a diameter ranging from 1.5 to 3 inches.
- FIG. 2 is a schematic representation of an illustrative embodiment of the present invention.
- the upstream system 12, e.g. semiconductor manufacturing tool, is connected to an exit line 14.
- Exit line 14 has walls defining an elongated tubular shape with an internal flow passage and a first end upstream from a second end.
- the internal flow passage of exit line 14 is connected at its first end to the upstream system 12 to receive effluent gas from the upstream system.
- the second end of exit line 14 is connected at an approximate midpoint of intake manifold line 16.
- Intake manifold line 16 has walls defining an elongated body with an internal flow passage, and first and second ends. The first and second ends of intake manifold line 16 are downstream from the approximate midpoint connection with exit line 14.
- the connection of exit line 14 and manifold 16 facilitates the effective passage of effluent gas from the interior flow passage of line 14 to the interior flow passage of manifold line 16.
- First and second intake lines 18 and 20 have walls defining internal passages, and first and second ends.
- the respective first ends of intake lines 18 and 20 are connected to the first and second ends of manifold line 16 thereby facilitating passage of the effluent gas from the internal flow passage of manifold line 16 to the internal flow passages of intake lines 18 and 20.
- the second ends of intake lines are downstream from the first ends.
- the respective second ends of the intake lines 18 and 20 are connected to scrubber unit 50.
- Scrubber 50 is connected as shown to a scrubber water line 52.
- the connection facilitates passage of water, from scrubber water line 52 into scrubber 50.
- the scrubber 50 is also connected to a vent gas discharge line 54, to provide for passage of gas from scrubber 50 through line 54 to a discharge location.
- the scrubber 50 is also connected to a fluid waste line 56, to provide uninterrupted passage of liquid waste from scrubber 50 to a liquid waste discharge location.
- the scrubber water line 52, vent gas discharge line 54, fluid waste line 56, exit line 14, manifold intake line 16 and first and second intake lines 18 and 20, may be of any suitable diameter, appropriate to the specific gas flow rates and processing unit operations involved in the facility.
- connection between the manifold intake line and the first and second intake lines is angled between 45 and 90 degrees so that the internal passage of the manifold line serves as a water baffle retarding back migration of water from within the internal passages of the first and second intake lines.
- first and second intake valves 22 and 24 Connected proximate to the upstream ends of the first and second intake ducts are first and second intake valves 22 and 24.
- the intake valves are two-way valves, each having an open and closed position. When in a closed position, the intake valve prevents the flow of effluent gas from the manifold line 16 into the intake lines.
- first and second heating means 46 and 48 Positioned proximate to the second, downstream ends of the intake lines are first and second heating means 46 and 48.
- the heating means may comprise any heating systems known to the skilled artisan for transferring thermal energy to the internal passages of the first and second inlet lines.
- the heating means will be referred to as heating coils.
- the gas delivery system of the present invention includes a gas source 26, first and second gas delivery lines 28 and 32 having internal passages, first and second ends, and first and second gas flow control valves 30 and 34 therein.
- gas delivery system described herein may include more than one gas source. Multiple gas sources would be connected in gas flow communication to a gas source manifold.
- the gas source manifold may include an gas source isolation valve for each gas source and a gas source flow control valve for each gas source. The gas source manifold would then be connected in gas flow communication to the gas delivery system.
- Gas source 26 is positioned proximate to the first and second intake lines.
- Gas source 26 furnishes gas, such as nitrogen, for delivery at rate of 2 to 100 standard cubic feet per hour, into the internal passages of the first and second intake lines 18 and 20. Effective gas delivery into the intake lines is facilitated by the connection (by any suitable connection means, such as couplings, connectors, etc.) of the first and second gas delivery lines to the first and second intake lines.
- Gas source 26 is connected to the first gas delivery line 28 at the first end of line 28.
- the first end of a second gas delivery line 32 is connected at an approximate midpoint along the length of first gas delivery line 28.
- the connection between said first gas line 28 and second gas line 32 is such that gas contained in line 28 passes without obstruction or leakage into the interior passage of line 32.
- Second gas delivery line 32 is connected to line 28 at a point along the length of line 28 downstream from the connection between line 28 and gas source 26.
- a downstream end of first gas delivery line 28 is connected to a length of second intake line 20 downstream from second valve 24.
- the connection between gas line 28 and intake line 20 provides an unobstructed passageway for gas contained in the internal passage of gas line 28 to pass freely and without leakage into the interior passage of intake line 20.
- a second end of second gas delivery line 32, downstream from the first end of line 32 is connected to first intake line 18.
- the connection between gas line 32 and intake line 18 provides an unobstructed passageway for gas in line 32 to pass freely and without leakage into the interior of intake line 18.
- first gas valve 30 Positioned along first gas delivery line 28, upstream from the connection with second intake line 20 and downstream from the connection with second gas delivery line 32, is first gas valve 30.
- First gas valve 30 is a two way valve equivalent to the first and second intake valves discussed above.
- First gas valve 30 regulates the passage of gas along the interior of first gas delivery line 28 into second intake line 20.
- second gas valve 34 Positioned on the second gas delivery line, upstream from the connection with the first gas line, is second gas valve 34.
- Second gas valve 34 facilitates the passage of gas therethrough from the second gas line into the first intake line.
- the water delivery system includes a water source 36, first and second water lines 38 and 42 having first and second ends and internal passages, and first and second water valves 40 and 44.
- pressurized water source 36 Positioned proximate to the first and second intake lines is pressurized water source 36. Pressurized water source 36 produces a stream of water at a pressure ranging from 0.5 to 5 gallons per minute. Water source 36 is connected to the internal passage of the first water line 38 at the first end of line 38. The connection facilitates the effective passage of pressurized water from the source into the internal passage of line 38. The second end of first water line 38, downstream from said first end, is connected to second intake line 20 for the delivery of the pressurized water from the internal passage of first water line 38 into the internal passage of second intake line 20. Positioned on first water line 38, upstream from the connection with second intake line 20, is a first water valve 40 for facilitating the selective passage of pressurized water therethrough and into intake line 20. First water valve 40 is a two way valve.
- a first end of second water delivery line 42 is connected to first water delivery line 38 at a location upstream from first water valve 40 and downstream from water source 36.
- the second end of second water delivery line 42 downstream from the first end, is connected to first intake line 18 for the delivery of pressurized water from the internal passage of line 38 into the internal passage of intake line 18.
- second water valve 44 Positioned on the second water line, upstream from the connection to the first intake line 18, is second water valve 44 for selectively controlling the passage of pressurized water therethrough.
- Second water valve 44 is a two way valve.
- a first thermal jacket 58 accommodates a length of first intake line 18, first intake valve 22, the connection between line 18 and second gas delivery line 34, the connection between line 18 and second water delivery line 42, and first heating means 48.
- the first thermal jacket provides insulating properties to the elements accommodated therein and cooperates with the heating means to raise an internal thermal temperature of first intake duct line 18.
- Thermal jacket 58 raises side wall temperature while N 2 is flowing to evaporate water deposited on the side wall, and thermal jacket 58 raises the side wall temperature to prevent condensable process gases from condensing in the line.
- BCl 3 from the process will form boric acid upon hydrolysis reaction at the entry to the scrubber, yet, the process line must be heated to prevent AlCl 3 from condensing along the line as well.
- the line may, then, be heated from the process source as is the case for metal etch or WCVD.
- a second thermal jacket 60 accommodates a length of second intake line 20, second intake valve 24, the connection between line 20 and first gas line 28, the connection between line 20 and first water line 38, and second heating means 46.
- the second thermal jacket provides insulating properties to the elements accommodated therein and cooperates with the heating means to raise an internal thermal temperature of second intake line 20.
- valves mentioned above are two way valves each having an open position and a closed position.
- the valves are pneumatic valves with an air open and spring close mode of operation (the valves may, though be air to close, spring to open depending upon the system requirements, performance, and objectives).
- pneumatic valves may include KF-50 connections, electro-pneumatic with integral air solenoid valve, and proof of closure and proof of open switches leads.
- Such valves are available from HPS Division of MKS Instruments as model 190. Electrical connections between the above mentioned and below cited valves are maintained to a control panel (not shown).
- the control panel includes a programmable logic controller (PLC) in electrical connection with the system valves.
- PLC programmable logic controller
- the PLC maintains electrical connections with the valves to monitor valve position and actuate valve position (open or close).
- a timer is associated with the PLC to facilitate PLC timing of valve positions.
- the valves may be electrical, mechanical, electromechanical, magnetic, or other type valves, of any of various commercially available types.
- the valves may, in particular, include limit switches electrically coupled to the cycle timer control means or an alternate control means. The limit switches would provide valve position verification and control interlock to ensure the process gas flow is not deadheaded and to assist in preventing water from being introduced into an on-line (on-stream) gas flow line.
- a first step (block 1 in the FIG. 3 flowchart) in the operation of the present invention is to close all valves: 22, 24, 30, 34, 40, and 44.
- the programmable logic controller (PLC) controls the opening and closing of the valves by regulating the flow of pneumatic air thereto (not shown).
- the cessation of pneumatic air to a valve causes a spring to move a valve baffle to an obstructing position, thereby preventing the flow of gas stream material from a position upstream of the valve to a position downstream of the valve.
- the first step prevents the flow of any effluent gas, pressurized water, or other gas, through any of the duct lines set out above.
- This initial step is a safety precaution prior to use of the apparatus of the present invention, to ensure that an operator is always aware of which intake duct lines are being occupied by a stream of effluent gas from the upstream system 12.
- the initial step ensures that the flow of effluent gas (along with pressurized water and gas from gas source 36) has not yet begun.
- a second step (block 2 in the FIG. 3 flowchart) in the operation of the present invention involves querying whether all the valves are shut. This query is executed by the PLC housed in the control panel. As set out above, the PLC is in electrical communication with electrical position indicator means housed within the aforementioned valves. This query is carried out by the PLC detecting signals from the positioned indicator means and associating same with predetermined valves indicative of a closed position. When it is determined that the aforementioned valves are in the closed position, the third step is initiated. When it is determined that the aforementioned valves are in an open position, an alarm is sounded and the prior step is repeated.
- a third step (block 3 in the FIG. 3 flowchart) entails opening second intake valve 24.
- the opening of valve 24 may be accomplished by allowing the flow of pneumatic air into the valve, thereby causing an internal spring to adjust the position of a valve baffle into one which allows the passage of effluent gas from manifold 16, through second intake valve 24 and into second intake line 20.
- the opening of second intake valve 24 is activated by the PLC.
- First intake valve 22 is held in a closed position thereby sealing off the first intake line from the flow of effluent and off gas causing same to flow exclusively through the second intake line 20.
- a fourth step (block 4 in the FIG. 3 flowchart) entails querying whether the second intake valve 24 has been opened.
- the query into the valve position is carried out by the PLC in the same manner as the valve position query set out in step two. If the PLC determines that the second intake valve is closed, an alarm is sounded and the prior step is repeated. If the PLC detects the intake valve to be open, the next step in the operating procedure is implemented.
- a fifth step (block 5 in the FIG. 3 flowchart) entails opening second water valve 44.
- the opening of valve 44 is performed by the PLC in a similar manner as described above.
- the opening of valve 44 creates an outlet for the flow of pressurized water from water source 36, through first water delivery line 38 and second water delivery line 42, into first intake line 18.
- First water valve 40 is maintained in a closed position to ensure that no water from water source 36 passes therethrough and into second intake line 20.
- Valve 44 is held open by the PLC for a first duration of time set and monitored by a timer associated with the PLC.
- Second water valve 44 is held open for a time in the range of one to ten minutes.
- the flow of pressurized water into first intake line 18 flushes out and scours the internal passage of line 18, as well as dissolving soluble particulate, thereby causing particulates and the like to exit through the first intake line second end into scrubber unit 50.
- a sixth step entails closing water valve 44 after the first duration of time has passed.
- second gas valve 34 is opened (block 6B in the FIG. 3 flowchart) and, if not already activated, the first heating means is activated (block 6C in the FIG. 3 flowchart).
- the closing and opening of the valves is carried out by the PLC in a manner as described above.
- the first heating element is activated by generating a current flow therethrough, controlled by the PLC.
- the current flow encounters the natural resistance of the heating means and generates heat due to the ensuing electrical resistance.
- Second gas valve 34 is kept open for a second duration of time as set and monitored by the timer associated with the PLC.
- a preferred range of time for leaving second gas valve open and activation of the heating means is from thirty minutes to eight hours.
- First gas valve is maintained in a closed position so that the flow of gas from gas source 26 is directed along first gas delivery line 28 to second gas delivery line 32 and first intake line 18.
- the gas in cooperation with heat delivered by first heating means 48, dries the interior walls of the first inlet line.
- a seventh step (block 7 in the FIG. 3 flowchart) entails disengaging the first heating means and opening first intake valve 22.
- the opening of the valve 22 is carried out by a similar manner as described above.
- the heating means is disengaged by the cessation of current thereto as controlled by the PLC.
- An eighth step (block 8 in the FIG. 3 flowchart) entails querying whether first intake valve 22 is open. The query is carried out by the PLC in a similar querying manner as set out above. If the PLC determines that the first intake valve is not open, an alarm is activated and step seven is repeated. Only when the PLC confirms the newly cleaned inlet is open will the PLC close the other inlet for cleaning; otherwise the flow of process gas could be blocked. If the PLC determines that the first intake valve is open, the next step in the operating procedure is implemented.
- a ninth step (block 9 in the FIG. 3 flowchart) entails closing second intake valve 24.
- First intake valve 22 is maintained in an open position.
- the closing of the second intake valve 24 causes the flow of effluent to become diverted from a now closed off second inlet line to a now open first inlet line.
- a tenth step (block 10 in the FIG. 3 flowchart) entails querying whether second intake valve 24 is closed. The query is carried out by the PLC in electrical connection with the second intake valve as set out above. If the PLC determines that the second intake valve is not closed, an alarm is activated and the ninth step is repeated. If the second intake valve is determined to be closed the next step in the operating procedure is implemented.
- An eleventh step (block 11 in the FIG. 3 flowchart) entails opening first water valve 40.
- the second water valve 44 is maintained in a closed position.
- the opening of the first water valve (and the closed second water valve 44) opens a passage for pressurized water to flow from the water source 36 through first water delivery line 38 and first water valve 40 and into second intake line 20.
- Second water valve 44 is maintained in a closed position to ensure that no water passes therethrough and into first inlet line 18.
- the pressurized water flows through second intake line 20 performing scouring and cleaning actions as set out above with regard to the first intake line.
- the pressurized water exits the second intake line through a second end connected to scrubber 50.
- the pressurized water is allowed to flush out the second intake line for a preselected time ranging from one to ten minutes.
- An adjustable timer in electrical connection with the PLC, cooperates with same to time the discharge of the pressurized water.
- a twelfth step (block 12 in the FIG. 3 flowchart) entails closing first water valve 40, a thirteenth step entails opening first gas valve 30 (block 13 in the FIG. 3 flowchart), and a fourteenth step (block 14 in the FIG. 3 flowchart) entails activating second heating means 46.
- the opening and closing of the valves is carried out by the PLC in a similar manner as described above.
- the second gas valve 34 is maintained in a closed position to ensure that no gas passes therethrough and into first inlet duct line 18.
- the opening of first gas valve 30 opens a passage for gas to flow from gas source 26, through first gas delivery line 28 and first gas valve 30, and into second inlet line 20.
- the activation of the second heating means causes, in cooperation with the second thermal jacket 60, the internal temperature of the second inlet line to rise.
- the gas and heat generated from the second heating means dries the interior passage of the second inlet line 20.
- the gas flows through the second inlet line and into the scrubber 50 via the line's second end.
- the first gas valve is held open and the second heating means is activated for a time duration ranging from thirty minutes to height hours. The time duration is monitored by a timer associated with the PLC as described above.
- a fifteenth step (block 15 in the FIG. 3 flowchart) entails closing first gas valve 30 and disengaging second heating means 46 after the time duration has been reached.
- the PLC queries the first intake valve 22 to ensure the valve remains in an open condition. The operation of the valves is performed in a manner as set out above.
- a seventeenth step (block 17 in the FIG. 3 flowchart) entails opening second intake valve 24 and querying (block 18 in the FIG. 3 flowchart) by the PLC as to whether the second intake valve 24 is open. If it is determined that the second intake valve is not open, an alarm is activated and the previous step is repeated.
- the PLC performs the querying process in a manner as set out above.
- a nineteenth step (block 19 in the FIG. 3 flowchart) entails closing first intake valve 22 and querying (block 20 in the FIG. 3 flowchart) to ensure first intake valve is closed. If valve 22 is not closed, an alarm is sounded and the previous step is repeated. If first intake valve 22 is closed, the operational procedure queries the operator as below.
Landscapes
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Organic Chemistry (AREA)
- Engineering & Computer Science (AREA)
- General Chemical & Material Sciences (AREA)
- Materials Engineering (AREA)
- Combustion & Propulsion (AREA)
- Metallurgy (AREA)
- Mechanical Engineering (AREA)
- Crystallography & Structural Chemistry (AREA)
- Analytical Chemistry (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Treating Waste Gases (AREA)
Abstract
Description
Claims (23)
Priority Applications (6)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US08/870,705 US5882366A (en) | 1997-06-06 | 1997-06-06 | Alternating wash/dry water scrubber entry |
PCT/US1997/023741 WO1998029181A1 (en) | 1996-12-31 | 1997-12-31 | Effluent gas stream treatment system for oxidation treatment of semiconductor manufacturing effluent gases |
KR1019997005992A KR100326623B1 (en) | 1996-12-31 | 1997-12-31 | Inlet structures for introducing a particulate solids containing and/or solids forming gas stream to a gas processing system |
EP97952695A EP0954366A4 (en) | 1996-12-31 | 1997-12-31 | Inlet structures for introducing a particulate solids-containing and/or solids-forming gas stream to a gas processing system |
PCT/US1997/024275 WO1998029178A1 (en) | 1996-12-31 | 1997-12-31 | Inlet structures for introducing a particulate solids-containing and/or solids-forming gas stream to a gas processing system |
JP53015998A JP3648539B2 (en) | 1996-12-31 | 1997-12-31 | Exhaust flow treatment system for oxidation treatment of semiconductor manufacturing exhaust |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US08/870,705 US5882366A (en) | 1997-06-06 | 1997-06-06 | Alternating wash/dry water scrubber entry |
Publications (1)
Publication Number | Publication Date |
---|---|
US5882366A true US5882366A (en) | 1999-03-16 |
Family
ID=25355941
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US08/870,705 Expired - Lifetime US5882366A (en) | 1996-12-31 | 1997-06-06 | Alternating wash/dry water scrubber entry |
Country Status (1)
Country | Link |
---|---|
US (1) | US5882366A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6338312B2 (en) * | 1998-04-15 | 2002-01-15 | Advanced Technology Materials, Inc. | Integrated ion implant scrubber system |
US20030175176A1 (en) * | 2000-08-08 | 2003-09-18 | Hiroshi Ikeda | Method and device for preventing solid products from adhering to inner surface of exhaust gas pipe and exhaust gas treatment device with the device |
US20040226585A1 (en) * | 2003-05-16 | 2004-11-18 | Macronix International Co., Ltd. | Cleaning systems with monitoring functions |
US20070166205A1 (en) * | 1996-12-31 | 2007-07-19 | Mark Holst | Effluent gas stream treatment system having utility for oxidation treatment of semiconductor manufacturing effluent gases |
US20080134887A1 (en) * | 2003-04-15 | 2008-06-12 | Applied Materials, Inc. | Low pressure drop canister for fixed bed scrubber applications and method of using same |
US20090205495A1 (en) * | 2004-02-03 | 2009-08-20 | Mark Johnsgard | Apparatus and Method for Providing Heated Effluent Gases to a Scrubber |
US7854792B2 (en) | 2008-09-17 | 2010-12-21 | Airgard, Inc. | Reactive gas control |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2857979A (en) * | 1954-06-30 | 1958-10-28 | Shell Dev | Gas-liquid separator with porous wall |
US3097936A (en) * | 1960-09-30 | 1963-07-16 | Fuller Co | Dust collector control system |
US3888955A (en) * | 1973-04-04 | 1975-06-10 | Saburo Maruko | Connection device |
US4986838A (en) * | 1989-06-14 | 1991-01-22 | Airgard, Inc. | Inlet system for gas scrubber |
US5113789A (en) * | 1990-04-24 | 1992-05-19 | Watkins Johnson Company | Self cleaning flow control orifice |
US5118286A (en) * | 1991-01-17 | 1992-06-02 | Amtech Systems | Closed loop method and apparatus for preventing exhausted reactant gas from mixing with ambient air and enhancing repeatability of reaction gas results on wafers |
US5575636A (en) * | 1994-06-21 | 1996-11-19 | Praxair Technology, Inc. | Porous non-fouling nozzle |
US5704990A (en) * | 1993-11-15 | 1998-01-06 | Zeppelin Schuettguttechnik Gmbh | Method of blowing conveying conduits free of material after conveyance |
-
1997
- 1997-06-06 US US08/870,705 patent/US5882366A/en not_active Expired - Lifetime
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2857979A (en) * | 1954-06-30 | 1958-10-28 | Shell Dev | Gas-liquid separator with porous wall |
US3097936A (en) * | 1960-09-30 | 1963-07-16 | Fuller Co | Dust collector control system |
US3888955A (en) * | 1973-04-04 | 1975-06-10 | Saburo Maruko | Connection device |
US4986838A (en) * | 1989-06-14 | 1991-01-22 | Airgard, Inc. | Inlet system for gas scrubber |
US5113789A (en) * | 1990-04-24 | 1992-05-19 | Watkins Johnson Company | Self cleaning flow control orifice |
US5118286A (en) * | 1991-01-17 | 1992-06-02 | Amtech Systems | Closed loop method and apparatus for preventing exhausted reactant gas from mixing with ambient air and enhancing repeatability of reaction gas results on wafers |
US5704990A (en) * | 1993-11-15 | 1998-01-06 | Zeppelin Schuettguttechnik Gmbh | Method of blowing conveying conduits free of material after conveyance |
US5575636A (en) * | 1994-06-21 | 1996-11-19 | Praxair Technology, Inc. | Porous non-fouling nozzle |
Non-Patent Citations (2)
Title |
---|
Abrea, et al., Causes of anomalous solid formation in the exhaust system of low pressure chemical vapor deposition plasma enhanced chemical vapor deposition semiconductor processes, J. Vac. Sci. Technol B 12(4) Jul./Aug. 1994, pp. 2763 2767. * |
Abrea, et al., Causes of anomalous solid formation in the exhaust system of low-pressure chemical vapor deposition plasma enhanced chemical vapor deposition semiconductor processes, J. Vac. Sci. Technol B 12(4) Jul./Aug. 1994, pp. 2763-2767. |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7695700B2 (en) | 1996-12-31 | 2010-04-13 | Applied Materials, Inc. | Effluent gas stream treatment system having utility for oxidation treatment of semiconductor manufacturing effluent gases |
US20070166205A1 (en) * | 1996-12-31 | 2007-07-19 | Mark Holst | Effluent gas stream treatment system having utility for oxidation treatment of semiconductor manufacturing effluent gases |
US20070212288A1 (en) * | 1996-12-31 | 2007-09-13 | Mark Holst | Effluent gas stream treatment system having utility for oxidation treatment of semiconductor manufacturing effluent gases |
US20090010814A1 (en) * | 1996-12-31 | 2009-01-08 | Mark Holst | Effluent gas stream treatment system having utility for oxidation treatment of semiconductor manufacturing effluent gases |
US6540814B2 (en) | 1997-01-17 | 2003-04-01 | Advanced Technology Materials, Inc | Integrated ion implant scrubber system |
US6338312B2 (en) * | 1998-04-15 | 2002-01-15 | Advanced Technology Materials, Inc. | Integrated ion implant scrubber system |
US20030175176A1 (en) * | 2000-08-08 | 2003-09-18 | Hiroshi Ikeda | Method and device for preventing solid products from adhering to inner surface of exhaust gas pipe and exhaust gas treatment device with the device |
US7736440B2 (en) | 2000-08-08 | 2010-06-15 | Ebara Corporation | Method and apparatus for preventing adherence of solid products in gas exhaust pipe and exhaust gas abatement device with same apparatus |
US20080134887A1 (en) * | 2003-04-15 | 2008-06-12 | Applied Materials, Inc. | Low pressure drop canister for fixed bed scrubber applications and method of using same |
US20040226585A1 (en) * | 2003-05-16 | 2004-11-18 | Macronix International Co., Ltd. | Cleaning systems with monitoring functions |
US20090205495A1 (en) * | 2004-02-03 | 2009-08-20 | Mark Johnsgard | Apparatus and Method for Providing Heated Effluent Gases to a Scrubber |
US7942951B2 (en) * | 2004-02-03 | 2011-05-17 | Airgard, Inc. | Apparatus and method for providing heated effluent gases to a scrubber |
US7854792B2 (en) | 2008-09-17 | 2010-12-21 | Airgard, Inc. | Reactive gas control |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7494628B2 (en) | Apparatus for abatement of by-products generated from deposition processes and cleaning of deposition chambers | |
JPH08150317A (en) | Waste gas treating device | |
US5882366A (en) | Alternating wash/dry water scrubber entry | |
JP2001502604A (en) | Exhaust flow treatment system for oxidation of semiconductor manufacturing exhaust | |
KR102135068B1 (en) | Device for Processing by Separating Waste Gas | |
EP2361668B1 (en) | Apparatus for purifying industrial exhaust gas | |
KR100834519B1 (en) | Method and apparatus for preventing solid product adhesion in exhaust gas piping, and apparatus for treating exhaust gas | |
JP3215081B2 (en) | Apparatus and method for removing exhaust gas from semiconductor manufacturing | |
WO2005066387A1 (en) | Method for cleaning film-forming apparatuses | |
JP3277987B2 (en) | Ozone flow control device | |
JP3815815B2 (en) | Semiconductor device manufacturing method and exhaust gas treatment apparatus | |
US5873388A (en) | System for stabilization of pressure perturbations from oxidation systems for treatment of process gases from semiconductor manufacturing operations | |
WO1998029178A1 (en) | Inlet structures for introducing a particulate solids-containing and/or solids-forming gas stream to a gas processing system | |
WO1999037919A1 (en) | Trap device and trap system | |
JP3242875B2 (en) | Exhaust gas abatement apparatus and exhaust gas abatement method | |
JP4491696B2 (en) | Exhaust gas treatment equipment | |
JPH04290525A (en) | Method and device for treating waste gas | |
US5738699A (en) | Apparatus for treating particles | |
JPH0779949B2 (en) | Exhaust gas treatment device | |
JP3708322B2 (en) | Trap system | |
JPH03146670A (en) | Vapor growth device | |
JPH11137951A (en) | Industrial pretreatment facility of waste gas of semiconductor production and industrial pretreatment method therefor | |
JPH1161412A (en) | Industrial pretreatment apparatus | |
KR100539454B1 (en) | Scrubber for semiconductor device manufacturing equipment | |
JPH10202045A (en) | Waste gas treatment facility |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: ADVANCED TECHNOLOGY MATERIALS, INC., CONNECTICUT Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:HOLST, MARK;REEL/FRAME:009636/0422 Effective date: 19980831 |
|
AS | Assignment |
Owner name: HEWLETT-PACKARD COMPANY, CALIFORNIA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:BALLIEW, PATRICK J.;REEL/FRAME:009667/0151 Effective date: 19981210 |
|
STCF | Information on status: patent grant |
Free format text: PATENTED CASE |
|
CC | Certificate of correction | ||
FEPP | Fee payment procedure |
Free format text: PAT HOLDER NO LONGER CLAIMS SMALL ENTITY STATUS, ENTITY STATUS SET TO UNDISCOUNTED (ORIGINAL EVENT CODE: STOL); ENTITY STATUS OF PATENT OWNER: LARGE ENTITY |
|
AS | Assignment |
Owner name: AGILENT TECHNOLOGIES, INC., COLORADO Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:ATMI, INC.;HEWLETT-PACKARD COMPANY;REEL/FRAME:013089/0674;SIGNING DATES FROM 20020603 TO 20020606 |
|
FPAY | Fee payment |
Year of fee payment: 4 |
|
AS | Assignment |
Owner name: APPLIED MATERIALS, INC., CALIFORNIA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:ADVANCED TECHNOLOGY MATERIALS, INC.;REEL/FRAME:016937/0211 Effective date: 20041216 |
|
AS | Assignment |
Owner name: AVAGO TECHNOLOGIES GENERAL IP PTE. LTD., SINGAPORE Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:AGILENT TECHNOLOGIES, INC.;REEL/FRAME:017207/0020 Effective date: 20051201 |
|
FPAY | Fee payment |
Year of fee payment: 8 |
|
FPAY | Fee payment |
Year of fee payment: 12 |
|
AS | Assignment |
Owner name: AVAGO TECHNOLOGIES GENERAL IP (SINGAPORE) PTE. LTD Free format text: CORRECTIVE ASSIGNMENT TO CORRECT THE NAME OF THE ASSIGNEE PREVIOUSLY RECORDED ON REEL 017207 FRAME 0020. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT;ASSIGNOR:AGILENT TECHNOLOGIES, INC.;REEL/FRAME:038633/0001 Effective date: 20051201 |