US20110056147A1 - Load-bearing construction pod and hybrid method of construction using pods - Google Patents

Load-bearing construction pod and hybrid method of construction using pods Download PDF

Info

Publication number
US20110056147A1
US20110056147A1 US12/584,582 US58458209A US2011056147A1 US 20110056147 A1 US20110056147 A1 US 20110056147A1 US 58458209 A US58458209 A US 58458209A US 2011056147 A1 US2011056147 A1 US 2011056147A1
Authority
US
United States
Prior art keywords
pod
pods
connection
construction
connection holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US12/584,582
Inventor
Patrice Beaudet
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US12/584,582 priority Critical patent/US20110056147A1/en
Publication of US20110056147A1 publication Critical patent/US20110056147A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/005Modulation co-ordination
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34815Elements not integrated in a skeleton
    • E04B1/3483Elements not integrated in a skeleton the supporting structure consisting of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34869Elements for special technical purposes, e.g. with a sanitary equipment

Definitions

  • the present invention relates generally to building construction.
  • the present invention relates to a construction method combining conventional methods of construction and prefabricated, mass-manufactured load-bearing pods (modules).
  • U.S. Pat. Nos. 5,447,000 and 4,891,919 disclose a containerized prefabricated building kits, the shipping container module becomes part of the building, the rest of the building being made of panels that fit inside the container for transportation purposes. These two patents relate to small buildings (single or double family buildings) where the square footage of a building is slightly larger than the combine size of the container that has to be transported.
  • WO 2009/005449 discloses a building system where bathroom modules are integrated into a shaft on top of one another, the rest of the building being erected using factory pre-fitted panels and pillars.
  • the present invention substantially reduces the cost of construction, drastically improves quality and considerably reduces construction time by having the most repetitive and labor intensive parts of the building being incorporated into factory-made standardized pods (modules); thus having specialized construction site work replaced by more productive factory work while making construction simpler for both the conception and erection of the building.
  • the pods of the present invention are fully finished inside and easy to inspect and connect from the outside.
  • Pods can include the bathrooms, the kitchens, the utility rooms, most of the plumbing system, the electric panels and most of the wiring and electrical receptacle outlets. Many of the smaller rooms can be integrated into a pod while larger rooms are being located outside pods.
  • Transportation costs are reasonable because the pods can easily be the standard size of a trailer or semi-trailer as in the preferred embodiment or the size of a shipping container.
  • Pods can be manufactured in a controlled environment where labor is largely available and inexpensive and the building can be erected where labor is expensive and scarce and where weather conditions can be harsh.
  • the structure of the pod is made of steel; it can also be made of wood, concrete or other material.
  • the rest of the building being constructed using almost any other construction method or materials, in the preferred embodiment, the rest of the building is built using steel.
  • FIG. 1 is a perspective view of the main structure of the pod.
  • FIG. 2 is a partial enlarged perspective view showing different sizes of columns that can be connected together.
  • FIG. 3 is a perspective view, similar to FIG. 1 where the structure of the floor has been added.
  • FIG. 4 is a perspective view similar to FIG. 3 where the walls and the ceiling have been added.
  • FIG. 5 is a perspective view of a stack of four pods.
  • FIG. 6 is a floor plan view of the preferred embodiment.
  • FIG. 7 is a top plan view of a chassis semi-trailer used to transport pods.
  • FIG. 8 is a floor plan view of single family house built using one pod.
  • FIG. 9 is a partial plan view of a floor of a multi-family residential building using multiple pods.
  • FIG. 10 is a floor plan view of four pods and the structure of the floor attached to these four pods.
  • FIG. 11 is a perspective view of eight pods and the structure of the floor attached to the main structure of the four upper pods, the pods are shown unfinished for clarity.
  • FIG. 12 is a front elevational view of a building being erected using pods of the present invention.
  • FIG. 13 is an enlarged partial side view of two pods attached together with a structural holt and a nut.
  • FIG. 14 is an enlarged partial side view of a pod secured to a chassis semi-trailer by a structural bolt and a nut.
  • FIG. 15 is an enlarged partial side view a pod attached to the lilting device using a structural bolt and a nut.
  • FIG. 16 is a top plan view of the lifting device.
  • FIG. 17 is an enlarged plan view of one of the steel plate that carries the load of the lifting device.
  • FIG. 18 is a side plan view of the lifting device.
  • the present invention permits the construction of custom made buildings of all sizes, made using diversified materials and styles while using off-site standardized construction pods that integrate the most labour-intensive components of the edifice and a significant part of the structure of that edifice.
  • One pod can be used to build a small building like a single-family house (see FIG. 8 ), or many similar pods can be stacked on top of one another to erect a multi-story building.
  • FIGS. 1 and 2 show the main structure of the pods which is made of hot rolled steel.
  • the pod has four columns (elements 1 to 1 c ), one in each corners, the size of the columns varies depending on how many floors it has to carry.
  • the column are made of steel tubing that can go for example from a small 150 millimeters by 75 millimeters by 6 millimeters thick (6 inches by 3 inches by 1 ⁇ 4 inch thick) (element 1 ) for pods that can carry the weight of up to live floors to a 200 millimeters by 200 millimeters by 16 millimeters thick (8 inches by 8 inches by 5 ⁇ 8 inch) (element 1 c ) for pods located at the lower floors of a forty-story building.
  • a small 150 millimeters by 75 millimeters by 6 millimeters thick (6 inches by 3 inches by 1 ⁇ 4 inch thick) (element 1 ) for pods that can carry the weight of up to live floors to a 200 millimeters by 200 millimeters by 16 millimeters thick (8 inches by 8 inches by 5 ⁇ 8 inch) (element 1 c ) for pods located at the lower floors of a forty-story building.
  • Each column has two connection plates (element 2 to 2 g in FIG. 2 ), one at each end, each of these connection plates has at least one connection hole including one main connection hole (elements 6 to 6 g ), the main connection holes of different pods are all located at the same location even if pods located at the lower levels of a building with a larger structure have more connection holes to insert more structural bolts. Pods with the same size of columns can be connected together and as presented on FIGS.
  • connection hole of their lop connection plates and their bottom connection plates are located at the same place; different sizes of columns can also be connected together because even if the larger column has more connection holes in its connection plates, it has connection holes at the same location than the smaller column in order to connect these pods together using structural bolts or other connection device, for example the top column (elements 1 ) in FIG. 2 can be connected to larger columns (elements 1 a , 1 b or 1 c ), even though it has only one connection hole per connection plate, its lower connection hole (element 6 a ) matches the main connection hole of the top connection plate of all of the columns below (elements 6 h , 6 d and 6 f ). A connection plate is always fully supported by the identical or the larger connection plate of the pod beneath.
  • every two columns are attached together by a cross member (element 3 ) made of steel tubing in the preferred embodiment, these components as well as the connection plates are welded together.
  • the rest of the structure of the building is made of cold-formed steel, in FIG. 3 , cold-formed steel floor joists (elements 4 ) are attached to the cross members (element 3 ) using common end tracks, L-shaped brackets and self-drilling screws (not show), bolts or other connection device can also be used.
  • FIGS. 1 , 3 , 4 , 5 and 11 every two columns are attached together by a cross member (element 3 ) made of steel tubing in the preferred embodiment, these components as well as the connection plates are welded together.
  • the rest of the structure of the building is made of cold-formed steel, in FIG. 3 , cold-formed steel floor joists (elements 4 ) are attached to the cross members (element 3 ) using common end tracks, L-shaped brackets and self-drilling screws (not
  • the rest of the building is built using steel studs, for both the walls (elements 5 ) and the ceiling (element 5 a ), these studs are also connected together using common end tracks, L-shaped brackets and self-drilling screws (not show) or other connection device.
  • pods can be used to make the restrooms (toilets) and mechanical rooms of an office tower, an industrial building, a restaurant, a mall or a government building, pods can also be used for the bathrooms of a hotel, a hospital or a student or retirement residence.
  • pods are used for residential purposes and include one kitchen (elements 7 - 7 d ), one laundry room (element 8 - 8 d ), and two bathrooms (elements 9 - 9 i ), the very same pod can be used to built a single family house ( FIG. 8 ) or can be combine to similar pods to make a multi-family building including a 40-story high-rise.
  • FIG. 9 A partial plan view of a floor of a multi-family residential building using multiple pods is presented in FIG. 9 . In a different embodiment not shown here, a large house can be built using 2 or more pods.
  • the structure of the floors built between pods can be attached to the main structure of the pods as shown in FIGS. 10 and 11 .
  • the structure built outside the pods is made of cold-formed steel joists and tracks.
  • Primary cold-formed steel tracks (elements 11 ) are attached to the outside of the cross members of two pods (elements 3 in drawings 1 , 3 , 4 and 5 ) using self-drilling screws, bolts, rivets or other fastener; primary cold-formed steel tracks (elements 11 ) are backed by secondary cold-formed steel tracks (elements 11 a ) where primary cold-formed steel tracks (elements 11 ) are not hacked by the main structure of the pod, secondary cold-formed steel tracks (elements 11 a ) are attached to primary steel track using self-drilling screws and are attached to the pods' columns (elements 1 to 1 c ) at each end using L-shaped brackets and self-drilling screws, bolts, rivets or other fast
  • the pods of the present invention have a very strong structure that improve the structural integrity of a building, however, until these pods are placed on well leveled foundations or on top of similar pods, they are vulnerable to deformation that can cause cracks in tiles, stone counter tops, plaster panels (drywall), cement boards and joints. It is important that the four columns of the pod being aligned at all time to avoid these problems and that is why this method of construction could only be possible with custom-made trailers or semi-trailers and the lifting device that is part of the present invention.
  • a pod can be built directly on a chassis semi-trailer (element 10 in FIGS. 7 and 12 ) or trailer (element 10 a in FIG. 12 ); it can be built on a production line and be moved to the different stages of the production process on that very same chassis trailer or semi-trailer that will transport that pod to the construction site.
  • Pods are secured to chassis trailers or semi-trailer at each corner with a structural bolt (element 15 in FIG. 14 ) and a nut (element 16 in FIG. 15 ) or other connection device, custom-made chassis trailer or semi-trailers have four main connection holes (elements 611 in FIG.
  • one chassis trailer (element 10 a ) and one chassis semi-trailer (element 10 ) can be pulled by a truck to deliver two pods at a time.
  • the moment where the pod is the most vulnerable for deformation is during lifting, because there is nothing to support the pod underneath.
  • Pods are lifted from the chassis trailer to their permanent location on the construction site using a crane (element 13 in FIG. 12 ) and the lifting device (element 14 in FIGS. 12 , 15 , 16 and 17 ) that is not only part of the present invention but one of its most important parts.
  • the lifting device of the present invention permits the lifting of the pod from the top of its (bur columns in a leveled position.
  • connection holes of the lifting device (elements 6 i on FIGS. 16 and 17 ) being aligned with the main connection holes of the top connection plates of the pod (elements 6 , 6 h , 6 d or 6 f ) and one structural bolt (element 15 in FIG. 15 ) and nut (element 16 in FIG. 15 ) or other connection device is being used to secure each corner.
  • the bolts used to connect the pods together or to the lifting device or to the trailer or semi-trailer are 2.5 centimeters (1 inch) high-strength structural bolts.
  • the main structure of the lifting device is made of two steel I-beams (elements 17 in FIGS. 16 , 17 and 18 ) and two end members (elements 18 in FIGS. 16 and 17 ) made of steel tubes as well as lateral support made of smaller steel tubes (elements 20 , 21 and 21 a ) all welded together, the connection holes (elements 6 i ) are drilled directly into the end members.
  • the many hooking plates, seven in the preferred embodiment, have many hooking holes (elements 22 in FIG.
  • the hybrid method of construction of the present invention makes the conception of the building easier which brings additional savings.
  • the architect and the draftsperson do not have to draw the repetitive details of the elements included in the pods, they just have to ad each pod as a block in the drawings and still they can create buildings of all sizes and shapes and spend more time being creative.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Health & Medical Sciences (AREA)
  • Epidemiology (AREA)
  • Public Health (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Off-site load-bearing construction pod (module) that incorporate the vertical structure to carry similar pods placed on top of it and part of the on-site structure built around and above these pods. Hybrid method of construction where buildings are erected by combining standardized pods which incorporate smaller, most labor-intensive rooms and components of the edifice to conventional methods of construction for larger, less labor-intensive rooms and components. The very same mass-manufactured pod that incorporates kitchen, bathrooms, laundry room and most of the plumbing and the electric system of a dwelling can be used to build the top floor of a skyscraper or a single-family house.

Description

    CROSS REFERENCE TO RELATED APPLICATIONS
  • U.S. PATENT DOCUMENTS
    3,952,465 April 1976 Masiello 52/73
    3,990,193 November 1976 Ray et al 52/79
    4,050,215 September 1977 Fisher 52/79.3
    4,083,154 October 1978 Klink 52/79.9
    4,118,905 October 1978 Shelly 52/79.2
    4,136,492 January 1979 Willingham 52/79.7
    4,135,833 February 1979 Townend 52/745
    4,194,339 March 1980 Fisher 52/745
    4,485,608 December 1984 Kaufman 52/745
    4,512,120 April 1985 Lindal 52/79.1
    4,599,829 July 1986 DiMartino, Sr 52/79
    4,891,919 January 1990 Palibroda 52/79.5
    5,447,000 September 1995 Larsen 52/79.1
    5,706,614 January 1998 Wiley 52/79.1
    6,493,996 December 2002 Alexander et al 52/79.9
    6,625,937 B1 September 2003 Parker et al 52/79.7
    6,826,879 B1 December 2004 Allen et al 52/236.3
    FOREIGN PATENT DOCUMENT
    WO 2009/005449 January 2009 E04B  1/348
  • BACKGROUND OF THE INVENTION
  • 1. Field of the Invention
  • The present invention relates generally to building construction. The present invention relates to a construction method combining conventional methods of construction and prefabricated, mass-manufactured load-bearing pods (modules).
  • 2. Prior Art
  • Many patents have been granted for prefabricated or industrialized modular buildings. The simplest form of prefabricated building would be a small self-contained building; an example of such building is disclosed in U.S. Pat. No. 4,485,608. A steel shipping container can be transformed into a small building as disclosed in U.S. Pat. No. 5,706,614. Then there are modular buildings where two or more modules are joined together to form a single story building, examples of such buildings are disclosed in U.S. Pat. Nos. 4,083,154, and 4,512,120. There are also larger modular buildings where many modules are attached together both vertically and horizontally; examples of such buildings are disclosed in U.S. Pat. Nos. 3,952,465, 3,990,193, 4,599,829, 6,625,937 B1, and 6,826,879 B1. The above buildings all have in common that the square footage of the building is simply the sum of the square footage of all its components and are therefore very expensive to transport.
  • To reduce transportation costs, U.S. Pat. Nos. 5,447,000 and 4,891,919 disclose a containerized prefabricated building kits, the shipping container module becomes part of the building, the rest of the building being made of panels that fit inside the container for transportation purposes. These two patents relate to small buildings (single or double family buildings) where the square footage of a building is slightly larger than the combine size of the container that has to be transported.
  • There are many industrialized modular construction systems to build the shell of the building using very elaborate mechanism to fasten the precast modules together, and a lot of specialized work is needed to build everything inside the empty shell, like bathrooms, kitchens, outdoor walls and windows, plumbing, heating system, electricity and so on. Examples of such buildings are disclosed in U.S. Pat. Nos. 4,050,215, 4,118,905, 4,136,492, 4,135,833, 4,194,339 and 6,493,996.
  • Finally, WO 2009/005449 discloses a building system where bathroom modules are integrated into a shaft on top of one another, the rest of the building being erected using factory pre-fitted panels and pillars.
  • All of the above methods use a specific technique and specific modules, panels or other components to erect the whole building. There is a need for a method construction that combines the advantages of modular off-site construction to the advantages of on-site construction. There is a need for a method of construction that integrates the same standardized mass-manufactured key components into custom made buildings of all shapes and heights.
  • BRIEF SUMMARY OF THE INVENTION
  • The present invention substantially reduces the cost of construction, drastically improves quality and considerably reduces construction time by having the most repetitive and labor intensive parts of the building being incorporated into factory-made standardized pods (modules); thus having specialized construction site work replaced by more productive factory work while making construction simpler for both the conception and erection of the building.
  • The pods of the present invention are fully finished inside and easy to inspect and connect from the outside. Pods can include the bathrooms, the kitchens, the utility rooms, most of the plumbing system, the electric panels and most of the wiring and electrical receptacle outlets. Many of the smaller rooms can be integrated into a pod while larger rooms are being located outside pods. Transportation costs are reasonable because the pods can easily be the standard size of a trailer or semi-trailer as in the preferred embodiment or the size of a shipping container. Pods can be manufactured in a controlled environment where labor is largely available and inexpensive and the building can be erected where labor is expensive and scarce and where weather conditions can be harsh.
  • In the preferred embodiment, the structure of the pod is made of steel; it can also be made of wood, concrete or other material. The rest of the building being constructed using almost any other construction method or materials, in the preferred embodiment, the rest of the building is built using steel.
  • BRIEF DESCRIPTION OF THE SEVERAL VIEWS OF THE DRAWINGS
  • FIG. 1 is a perspective view of the main structure of the pod.
  • FIG. 2 is a partial enlarged perspective view showing different sizes of columns that can be connected together.
  • FIG. 3 is a perspective view, similar to FIG. 1 where the structure of the floor has been added.
  • FIG. 4 is a perspective view similar to FIG. 3 where the walls and the ceiling have been added.
  • FIG. 5 is a perspective view of a stack of four pods.
  • FIG. 6 is a floor plan view of the preferred embodiment.
  • FIG. 7 is a top plan view of a chassis semi-trailer used to transport pods.
  • FIG. 8 is a floor plan view of single family house built using one pod.
  • FIG. 9 is a partial plan view of a floor of a multi-family residential building using multiple pods.
  • FIG. 10 is a floor plan view of four pods and the structure of the floor attached to these four pods.
  • FIG. 11 is a perspective view of eight pods and the structure of the floor attached to the main structure of the four upper pods, the pods are shown unfinished for clarity.
  • FIG. 12 is a front elevational view of a building being erected using pods of the present invention.
  • FIG. 13 is an enlarged partial side view of two pods attached together with a structural holt and a nut.
  • FIG. 14 is an enlarged partial side view of a pod secured to a chassis semi-trailer by a structural bolt and a nut.
  • FIG. 15 is an enlarged partial side view a pod attached to the lilting device using a structural bolt and a nut.
  • FIG. 16 is a top plan view of the lifting device.
  • FIG. 17 is an enlarged plan view of one of the steel plate that carries the load of the lifting device.
  • FIG. 18 is a side plan view of the lifting device.
  • DETAILED DESCRIPTION OF THE INVENTION
  • The present invention permits the construction of custom made buildings of all sizes, made using diversified materials and styles while using off-site standardized construction pods that integrate the most labour-intensive components of the edifice and a significant part of the structure of that edifice. One pod can be used to build a small building like a single-family house (see FIG. 8), or many similar pods can be stacked on top of one another to erect a multi-story building.
  • Pods can be connected on top of one another; the pod located on top of another pod can have a similar structure or a lighter structure since it has to carry a lighter load. FIGS. 1 and 2 show the main structure of the pods which is made of hot rolled steel. The pod has four columns (elements 1 to 1 c), one in each corners, the size of the columns varies depending on how many floors it has to carry. In the preferred embodiment the column are made of steel tubing that can go for example from a small 150 millimeters by 75 millimeters by 6 millimeters thick (6 inches by 3 inches by ¼ inch thick) (element 1) for pods that can carry the weight of up to live floors to a 200 millimeters by 200 millimeters by 16 millimeters thick (8 inches by 8 inches by ⅝ inch) (element 1 c) for pods located at the lower floors of a forty-story building.
  • Each column has two connection plates (element 2 to 2 g in FIG. 2), one at each end, each of these connection plates has at least one connection hole including one main connection hole (elements 6 to 6 g), the main connection holes of different pods are all located at the same location even if pods located at the lower levels of a building with a larger structure have more connection holes to insert more structural bolts. Pods with the same size of columns can be connected together and as presented on FIGS. 5, 11, 12 and 13 because all of the connection hole of their lop connection plates and their bottom connection plates are located at the same place; different sizes of columns can also be connected together because even if the larger column has more connection holes in its connection plates, it has connection holes at the same location than the smaller column in order to connect these pods together using structural bolts or other connection device, for example the top column (elements 1) in FIG. 2 can be connected to larger columns (elements 1 a, 1 b or 1 c), even though it has only one connection hole per connection plate, its lower connection hole (element 6 a) matches the main connection hole of the top connection plate of all of the columns below ( elements 6 h, 6 d and 6 f). A connection plate is always fully supported by the identical or the larger connection plate of the pod beneath.
  • As presented in FIGS. 1, 3, 4, 5 and 11, every two columns are attached together by a cross member (element 3) made of steel tubing in the preferred embodiment, these components as well as the connection plates are welded together. The rest of the structure of the building is made of cold-formed steel, in FIG. 3, cold-formed steel floor joists (elements 4) are attached to the cross members (element 3) using common end tracks, L-shaped brackets and self-drilling screws (not show), bolts or other connection device can also be used. As presented in FIGS. 4, 5, 6 and 12, the rest of the building is built using steel studs, for both the walls (elements 5) and the ceiling (element 5 a), these studs are also connected together using common end tracks, L-shaped brackets and self-drilling screws (not show) or other connection device.
  • Pods can be used to make the restrooms (toilets) and mechanical rooms of an office tower, an industrial building, a restaurant, a mall or a government building, pods can also be used for the bathrooms of a hotel, a hospital or a student or retirement residence. In the preferred embodiment as presented in FIG. 6, pods are used for residential purposes and include one kitchen (elements 7-7 d), one laundry room (element 8-8 d), and two bathrooms (elements 9-9 i), the very same pod can be used to built a single family house (FIG. 8) or can be combine to similar pods to make a multi-family building including a 40-story high-rise. A partial plan view of a floor of a multi-family residential building using multiple pods is presented in FIG. 9. In a different embodiment not shown here, a large house can be built using 2 or more pods.
  • The structure of the floors built between pods can be attached to the main structure of the pods as shown in FIGS. 10 and 11. In the preferred embodiment the structure built outside the pods is made of cold-formed steel joists and tracks. Primary cold-formed steel tracks (elements 11) are attached to the outside of the cross members of two pods (elements 3 in drawings 1, 3, 4 and 5) using self-drilling screws, bolts, rivets or other fastener; primary cold-formed steel tracks (elements 11) are backed by secondary cold-formed steel tracks (elements 11 a) where primary cold-formed steel tracks (elements 11) are not hacked by the main structure of the pod, secondary cold-formed steel tracks (elements 11 a) are attached to primary steel track using self-drilling screws and are attached to the pods' columns (elements 1 to 1 c) at each end using L-shaped brackets and self-drilling screws, bolts, rivets or other fasteners. Floor joists (elements 12 and 12 a) are attached to these tracks using L-shaped brackets and self-drilling screws.
  • The pods of the present invention have a very strong structure that improve the structural integrity of a building, however, until these pods are placed on well leveled foundations or on top of similar pods, they are vulnerable to deformation that can cause cracks in tiles, stone counter tops, plaster panels (drywall), cement boards and joints. It is important that the four columns of the pod being aligned at all time to avoid these problems and that is why this method of construction could only be possible with custom-made trailers or semi-trailers and the lifting device that is part of the present invention.
  • A pod can be built directly on a chassis semi-trailer (element 10 in FIGS. 7 and 12) or trailer (element 10 a in FIG. 12); it can be built on a production line and be moved to the different stages of the production process on that very same chassis trailer or semi-trailer that will transport that pod to the construction site. Pods are secured to chassis trailers or semi-trailer at each corner with a structural bolt (element 15 in FIG. 14) and a nut (element 16 in FIG. 15) or other connection device, custom-made chassis trailer or semi-trailers have four main connection holes (elements 611 in FIG. 7) which fit with the four main connection holes of the lower connection plates of the pod (elements 6 a, 6 c, 6 e, or 6 g). In the preferred embodiment, as shown in FIG. 12 one chassis trailer (element 10 a) and one chassis semi-trailer (element 10) can be pulled by a truck to deliver two pods at a time.
  • The moment where the pod is the most vulnerable for deformation is during lifting, because there is nothing to support the pod underneath. Pods are lifted from the chassis trailer to their permanent location on the construction site using a crane (element 13 in FIG. 12) and the lifting device (element 14 in FIGS. 12, 15, 16 and 17) that is not only part of the present invention but one of its most important parts. The lifting device of the present invention permits the lifting of the pod from the top of its (bur columns in a leveled position.
  • The lifting device is placed on top of the pod, the connection holes of the lifting device (elements 6 i on FIGS. 16 and 17) being aligned with the main connection holes of the top connection plates of the pod ( elements 6, 6 h, 6 d or 6 f) and one structural bolt (element 15 in FIG. 15) and nut (element 16 in FIG. 15) or other connection device is being used to secure each corner. In the preferred embodiment the bolts used to connect the pods together or to the lifting device or to the trailer or semi-trailer are 2.5 centimeters (1 inch) high-strength structural bolts.
  • The main structure of the lifting device is made of two steel I-beams (elements 17 in FIGS. 16, 17 and 18) and two end members (elements 18 in FIGS. 16 and 17) made of steel tubes as well as lateral support made of smaller steel tubes ( elements 20, 21 and 21 a) all welded together, the connection holes (elements 6 i) are drilled directly into the end members. There are many hooking steel plates (elements 19 in FIG. 16-18) at and around the middle of the lifting device, welded between the two long I-beams. The many hooking plates, seven in the preferred embodiment, have many hooking holes (elements 22 in FIG. 18), seven in the preferred embodiment, so in the preferred embodiment, there are 49 hooking hole to choose from to make sure the pod is lifted leveled with a single hook (element 23) from its center of gravity that can vary depending on the configuration of the pod and the options it carries.
  • Finally, the hybrid method of construction of the present invention makes the conception of the building easier which brings additional savings. The architect and the draftsperson do not have to draw the repetitive details of the elements included in the pods, they just have to ad each pod as a block in the drawings and still they can create buildings of all sizes and shapes and spend more time being creative.

Claims (14)

What is claimed is:
1. A prefabricated load-bearing pod that comprise a vertical structure, which vertical structure comprise four vertical members in its four corners, which said structure can carry the weight of the said pod, the weight of other similar pods place on top of it and part of the weight of the on-site structure built around and on top the said pods as well as the potential live load to be included in these pods and said on-site structure.
2. A pod according to claim 1 that has a floor, a ceiling and walls.
3. A pod according to claim 1 that can be fully finished inside and easy to inspect and connect from the outside and that can include bathrooms, kitchen, laundry room and utility room.
4. A vertical member according to claim 1 that has two connection plates, one at its bottom and one at its top, each said connection plate has at least one connection hole including one main connection hole and the main connection holes of different pods of the same series of pods are located at the same location. The said connection holes are used to insert structural bolts or other connection devices to secure a first pod to the foundations of a building and to secure pods together one on top of the other. The said connection plates and main connection holes also allow the lining of the pod and the securing of the pod during transportation.
5. A pod according to claim 1 with connection plates according to claim 4 that can be connected on top of another pod having the exact same structure where all the connection holes are located at the same place in order to connect these pods using structural bolts or other connection device; or that same pod can be connected to another pod having a stronger structure, larger connection plates having more connection holes because the lower connection plate of the said pod would be fully supported by the larger top connection plate of the pod beneath and the top connection plate of the pod beneath, even if it has more connection holes, has matching connection holes with smaller connection plates of the pods of the same series.
6. Each pair of vertical members according to claim 1 is join together by at least one cross member.
7. A vertical member according to claim 1, a connection plate according to claim 4 and a cross member according to claim 6 that are made of hot-rolled steel and welded together.
8. A floor according to claim 2 which structure is made of cold-formed steel or other material and is connected using screws, tracks, L-shaped brackets, bolts or other connection device to the cross members according to claim 6 and to the vertical structure according to claim 1.
9. A ceiling and walls according to claim 2 which structure is made of cold-formed steel or other material.
10. An hybrid method of construction where pods according to claims 1 become part of the structure of the building, the said pods are combined to on-site construction so that floor joists and the ceiling trusses built outside the pod can be attached to one or two pods. The said structure built outside the pod is attached to the vertical members according to claim 1 and to the cross members according to claim 6.
11. A chassis trailer or semi-trailer to carry the pod according to claims 1 that has four connection holes located at the same locations than the pods' main connection holes according to claim 4, in order to secure the said pod to the chassis trailer from the said pod four bottom connection plates according to claim 4 using structural bolts or other connection device.
12. A pod according to claims 1 and 4 that can be built directly on the chassis trailer or semi-trailer according to claim 11.
13. A lifting device that permits to crane up the pods according to claims 1 and 4, that has four connection holes located at the same locations than the said pods' top main connection holes according to claim 4; in order to attached the pod at its four top corners using bolts or other connection devices inserted at the same location where the upper pod is to be connected.
14. A lifting device according to claim 13 with many hooking holes located at and around its center in order to lift a pod according to claims 1 and 4 from its center of gravity, which center of gravity can vary depending on the configuration of the said pod and the options it carries, using one crane with one hook while keeping the said pod leveled until it reaches its permanent location.
US12/584,582 2009-09-09 2009-09-09 Load-bearing construction pod and hybrid method of construction using pods Abandoned US20110056147A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US12/584,582 US20110056147A1 (en) 2009-09-09 2009-09-09 Load-bearing construction pod and hybrid method of construction using pods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US12/584,582 US20110056147A1 (en) 2009-09-09 2009-09-09 Load-bearing construction pod and hybrid method of construction using pods

Publications (1)

Publication Number Publication Date
US20110056147A1 true US20110056147A1 (en) 2011-03-10

Family

ID=43646574

Family Applications (1)

Application Number Title Priority Date Filing Date
US12/584,582 Abandoned US20110056147A1 (en) 2009-09-09 2009-09-09 Load-bearing construction pod and hybrid method of construction using pods

Country Status (1)

Country Link
US (1) US20110056147A1 (en)

Cited By (59)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100132271A1 (en) * 2006-12-01 2010-06-03 Habidite, S.A. Constructive system
US20110036018A1 (en) * 2009-08-12 2011-02-17 Hong Fu Jin Precision Industry (Shenzhen) Co., Ltd. Movable building
US20110179721A1 (en) * 2010-01-25 2011-07-28 Barry Michael I Prefabricated building modules for multi-unit housing
CN102261189A (en) * 2011-04-08 2011-11-30 应惠清 Assembly-cast-in-situ type close column structure used in residential building with shear wall system
US20110296789A1 (en) * 2010-06-08 2011-12-08 Sustainable Living Technology, Llc Construction System and Method for Constructing Buildings Using Premanufactured Structures
US20120240482A1 (en) * 2011-03-22 2012-09-27 XSite Modular Components for a Modular High-Rise Structures And Method For Assembling Same
JP2014020001A (en) * 2012-07-12 2014-02-03 Misawa Homes Co Ltd Building
US20140259977A1 (en) * 2013-03-15 2014-09-18 Timothy McDonald Sustainable Building System
US20140352232A1 (en) * 2012-01-23 2014-12-04 Inter Hospitality Holding B.V. Method and system for construction of a building
US8950132B2 (en) 2010-06-08 2015-02-10 Innovative Building Technologies, Llc Premanufactured structures for constructing buildings
US8978324B2 (en) 2010-06-08 2015-03-17 Innovative Building Technologies, Llc Pre-manufactured utility wall
CN104420575A (en) * 2013-09-01 2015-03-18 孙善骏 Notch plate, bevel plate and jointed plate matched with cylindrical container combination unit combined body
GB2524303A (en) * 2014-03-20 2015-09-23 Show Block Ltd Pre-fitted customisable temporary structure module
USD765266S1 (en) 2013-07-22 2016-08-30 Vastint Hospitablity B.V. Prefabricated module design
US9464436B2 (en) 2012-01-23 2016-10-11 Vastint Hospitality B.V. Prefabricated panel for a building
FR3035892A1 (en) * 2015-05-07 2016-11-11 Didier Goy ASSEMBLY OF BEAMS AND POSTS FOR STACK CONSTRUCTION
US9493940B2 (en) 2010-06-08 2016-11-15 Innovative Building Technologies, Llc Slab construction system and method for constructing multi-story buildings using pre-manufactured structures
US9631359B2 (en) * 2012-01-23 2017-04-25 Vastint Hospitality B.V. Prefabricated module for a building
US9702138B1 (en) * 2013-05-17 2017-07-11 Modula S, Inc. Modular building construction
US9914467B2 (en) 2015-08-14 2018-03-13 Oldcastle Light Building Products, LLC Attachment and support members for modular building structures
US9963877B2 (en) * 2016-05-18 2018-05-08 David R. Hall Modular prismatic box-like structure-based building method and infrastructure
US10011982B1 (en) * 2015-09-23 2018-07-03 Theodore W. Baker School spaces retrofitted for alternative uses and related technology
US20180195266A1 (en) * 2014-09-11 2018-07-12 Panasonic Intellectual Property Management Co., Ltd. Building unit and building
US20180209136A1 (en) * 2017-01-24 2018-07-26 Affordable Modular Systems, LLC Lightweight steel parallel modular constructions system with synthetic modules
US10041289B2 (en) 2014-08-30 2018-08-07 Innovative Building Technologies, Llc Interface between a floor panel and a panel track
US20190032327A1 (en) * 2017-07-31 2019-01-31 Brent Musson Permanent building structure with reusable modular building units
US10260250B2 (en) 2014-08-30 2019-04-16 Innovative Building Technologies, Llc Diaphragm to lateral support coupling in a structure
US20190153720A1 (en) * 2016-04-29 2019-05-23 Rbon Holdings Pty Ltd Modular beam structure and modular base structure
US10301813B1 (en) * 2016-10-31 2019-05-28 John P. Hawkins Portable core facility for a building
US10323428B2 (en) * 2017-05-12 2019-06-18 Innovative Building Technologies, Llc Sequence for constructing a building from prefabricated components
US10329764B2 (en) 2014-08-30 2019-06-25 Innovative Building Technologies, Llc Prefabricated demising and end walls
US10344487B2 (en) 2015-08-14 2019-07-09 Oldcastle Light Building Products, LLC Attachment and support members for modular building structures
US20190226199A1 (en) * 2015-04-07 2019-07-25 Storage Ip Llc Self-storage facility, fabrication, and methodology
US10364572B2 (en) 2014-08-30 2019-07-30 Innovative Building Technologies, Llc Prefabricated wall panel for utility installation
US10450739B1 (en) * 2017-10-13 2019-10-22 Ob Development Llc Temporary or semi-permanent structure and method of increasing usable space
US10487493B2 (en) * 2017-05-12 2019-11-26 Innovative Building Technologies, Llc Building design and construction using prefabricated components
US10508442B2 (en) 2016-03-07 2019-12-17 Innovative Building Technologies, Llc Floor and ceiling panel for slab-free floor system of a building
US10676923B2 (en) 2016-03-07 2020-06-09 Innovative Building Technologies, Llc Waterproofing assemblies and prefabricated wall panels including the same
US10704251B1 (en) * 2017-07-25 2020-07-07 Vessel Technologies, Inc. Modular housing system and methods for using the same
US10724228B2 (en) 2017-05-12 2020-07-28 Innovative Building Technologies, Llc Building assemblies and methods for constructing a building using pre-assembled floor-ceiling panels and walls
US10900224B2 (en) 2016-03-07 2021-01-26 Innovative Building Technologies, Llc Prefabricated demising wall with external conduit engagement features
US10961710B2 (en) 2016-03-07 2021-03-30 Innovative Building Technologies, Llc Pre-assembled wall panel for utility installation
US11054148B2 (en) 2014-08-30 2021-07-06 Innovative Building Technologies, Llc Heated floor and ceiling panel with a corrugated layer for modular use in buildings
US11098475B2 (en) 2017-05-12 2021-08-24 Innovative Building Technologies, Llc Building system with a diaphragm provided by pre-fabricated floor panels
US11130625B2 (en) 2016-11-01 2021-09-28 Storage Ip Llc Self-storage facility, fabrication, and methodology
US20210334425A1 (en) * 2020-04-22 2021-10-28 SNL Fund, LLC Method of designing, configuring and accessing a modular self-storage facility
US20220042342A1 (en) * 2020-08-05 2022-02-10 Empowerment Innovation Lab Modular shelter pods
US20220145611A1 (en) * 2020-06-09 2022-05-12 Sma Solar Technology Ag Platform for stacking containers as housings of components of an energy conversion system, and energy conversion system
US11359365B2 (en) * 2015-11-02 2022-06-14 Orient Holding As Heating and cooling system of a modular residential building
US20220282474A1 (en) * 2019-08-06 2022-09-08 Jgc Corporation Module for separate conveyance, structure for plant, and method of constructing structure for plant
US20220341156A1 (en) * 2019-09-18 2022-10-27 Storage Ip Llc Self-Storage Facility, Fabrication, and Methodology
USD968650S1 (en) * 2020-05-20 2022-11-01 Alibaba Group Holding Limited Mobile conference room
US11505939B2 (en) * 2018-03-21 2022-11-22 Best Gen Modular, Inc. Reinforcing structure for modular building construction
US11536043B2 (en) * 2018-08-06 2022-12-27 Jeffrey J. Konczak Modular mini building system for parking lots
US20230048518A1 (en) * 2021-08-10 2023-02-16 Surepods, Llc Systems and methods for providing modular building structures based on site-specific conditions
US11629491B1 (en) * 2021-04-01 2023-04-18 Factory OS Inc. Interchangable modular construction method
US20230203829A1 (en) * 2021-05-20 2023-06-29 Sano Development Limited Hybrid building system, building and method
US20230295939A1 (en) * 2022-03-18 2023-09-21 Cary James Henson Modular dwelling constructed from vertically oriented intermodal containers
WO2024023342A1 (en) * 2022-07-29 2024-02-01 Sano Development Limited Modular building unit, building system, building and associated methods

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1362069A (en) * 1919-05-06 1920-12-14 Joseph R Witzel Building construction
US3162863A (en) * 1962-09-27 1964-12-29 Albert L Wokas Prefabricated bathrooms and prefabricated restrooms
US3229431A (en) * 1963-09-16 1966-01-18 John M Paul Frameless modular multistory building
US3256652A (en) * 1960-10-08 1966-06-21 Patent Concern Nv Building of assembled box-shaped elements
US3492767A (en) * 1968-02-19 1970-02-03 Core Properties Dev Corp Prefabricated building construction
US3965627A (en) * 1974-07-15 1976-06-29 Miroslav Fencl Interconnection of modular structures
US6298617B1 (en) * 1996-07-19 2001-10-09 Jorge De Quesada High rise building system using steel wall panels
US6625937B1 (en) * 2000-12-27 2003-09-30 Sunrise Holding, Ltd. Modular building and method of construction
US20110000147A1 (en) * 2007-12-28 2011-01-06 Bernd Heidenreich Modular Building and Method for the Production Thereof

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1362069A (en) * 1919-05-06 1920-12-14 Joseph R Witzel Building construction
US3256652A (en) * 1960-10-08 1966-06-21 Patent Concern Nv Building of assembled box-shaped elements
US3162863A (en) * 1962-09-27 1964-12-29 Albert L Wokas Prefabricated bathrooms and prefabricated restrooms
US3229431A (en) * 1963-09-16 1966-01-18 John M Paul Frameless modular multistory building
US3492767A (en) * 1968-02-19 1970-02-03 Core Properties Dev Corp Prefabricated building construction
US3965627A (en) * 1974-07-15 1976-06-29 Miroslav Fencl Interconnection of modular structures
US6298617B1 (en) * 1996-07-19 2001-10-09 Jorge De Quesada High rise building system using steel wall panels
US6625937B1 (en) * 2000-12-27 2003-09-30 Sunrise Holding, Ltd. Modular building and method of construction
US20110000147A1 (en) * 2007-12-28 2011-01-06 Bernd Heidenreich Modular Building and Method for the Production Thereof

Cited By (87)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8297002B2 (en) * 2006-12-01 2012-10-30 Habidite, S.A. Constructive system
US20100132271A1 (en) * 2006-12-01 2010-06-03 Habidite, S.A. Constructive system
US20110036018A1 (en) * 2009-08-12 2011-02-17 Hong Fu Jin Precision Industry (Shenzhen) Co., Ltd. Movable building
US8333039B2 (en) * 2009-08-12 2012-12-18 Hong Fu Jin Precision Industry (Shenzhen) Co., Ltd. Movable building
US20110179721A1 (en) * 2010-01-25 2011-07-28 Barry Michael I Prefabricated building modules for multi-unit housing
US8621787B2 (en) * 2010-01-25 2014-01-07 Ironstate Development, Llc Prefabricated building modules for multi-unit housing
US8950132B2 (en) 2010-06-08 2015-02-10 Innovative Building Technologies, Llc Premanufactured structures for constructing buildings
US9382709B2 (en) 2010-06-08 2016-07-05 Innovative Building Technologies, Llc Premanufactured structures for constructing buildings
US20110296789A1 (en) * 2010-06-08 2011-12-08 Sustainable Living Technology, Llc Construction System and Method for Constructing Buildings Using Premanufactured Structures
US10190309B2 (en) 2010-06-08 2019-01-29 Innovative Building Technologies, Llc Slab construction system and method for constructing multi-story buildings using pre-manufactured structures
US9493940B2 (en) 2010-06-08 2016-11-15 Innovative Building Technologies, Llc Slab construction system and method for constructing multi-story buildings using pre-manufactured structures
US9027307B2 (en) * 2010-06-08 2015-05-12 Innovative Building Technologies, Llc Construction system and method for constructing buildings using premanufactured structures
US10145103B2 (en) 2010-06-08 2018-12-04 Innovative Building Technologies, Llc Premanufactured structures for constructing buildings
US8978324B2 (en) 2010-06-08 2015-03-17 Innovative Building Technologies, Llc Pre-manufactured utility wall
US20120240482A1 (en) * 2011-03-22 2012-09-27 XSite Modular Components for a Modular High-Rise Structures And Method For Assembling Same
CN102261189A (en) * 2011-04-08 2011-11-30 应惠清 Assembly-cast-in-situ type close column structure used in residential building with shear wall system
US9631359B2 (en) * 2012-01-23 2017-04-25 Vastint Hospitality B.V. Prefabricated module for a building
US9464436B2 (en) 2012-01-23 2016-10-11 Vastint Hospitality B.V. Prefabricated panel for a building
US9556632B2 (en) * 2012-01-23 2017-01-31 Vastint Hospitality B.V. Method and system for construction of a building
US20140352232A1 (en) * 2012-01-23 2014-12-04 Inter Hospitality Holding B.V. Method and system for construction of a building
JP2014020001A (en) * 2012-07-12 2014-02-03 Misawa Homes Co Ltd Building
US20140259977A1 (en) * 2013-03-15 2014-09-18 Timothy McDonald Sustainable Building System
US9702138B1 (en) * 2013-05-17 2017-07-11 Modula S, Inc. Modular building construction
USD765266S1 (en) 2013-07-22 2016-08-30 Vastint Hospitablity B.V. Prefabricated module design
USD867616S1 (en) 2013-07-22 2019-11-19 Vastint Hospitality B.V. Prefabricated module
CN104420575A (en) * 2013-09-01 2015-03-18 孙善骏 Notch plate, bevel plate and jointed plate matched with cylindrical container combination unit combined body
GB2524303A (en) * 2014-03-20 2015-09-23 Show Block Ltd Pre-fitted customisable temporary structure module
US10364572B2 (en) 2014-08-30 2019-07-30 Innovative Building Technologies, Llc Prefabricated wall panel for utility installation
US11060286B2 (en) 2014-08-30 2021-07-13 Innovative Building Technologies, Llc Prefabricated wall panel for utility installation
US10041289B2 (en) 2014-08-30 2018-08-07 Innovative Building Technologies, Llc Interface between a floor panel and a panel track
US11054148B2 (en) 2014-08-30 2021-07-06 Innovative Building Technologies, Llc Heated floor and ceiling panel with a corrugated layer for modular use in buildings
US10975590B2 (en) 2014-08-30 2021-04-13 Innovative Building Technologies, Llc Diaphragm to lateral support coupling in a structure
US10260250B2 (en) 2014-08-30 2019-04-16 Innovative Building Technologies, Llc Diaphragm to lateral support coupling in a structure
US10329764B2 (en) 2014-08-30 2019-06-25 Innovative Building Technologies, Llc Prefabricated demising and end walls
US10563394B2 (en) * 2014-09-11 2020-02-18 Panasonic Intellectual Property Management Co., Ltd. Building unit and building
US20180195266A1 (en) * 2014-09-11 2018-07-12 Panasonic Intellectual Property Management Co., Ltd. Building unit and building
US20190226199A1 (en) * 2015-04-07 2019-07-25 Storage Ip Llc Self-storage facility, fabrication, and methodology
US10876283B2 (en) * 2015-04-07 2020-12-29 Storage Ip Llc Self-storage facility, fabrication, and methodology
FR3035892A1 (en) * 2015-05-07 2016-11-11 Didier Goy ASSEMBLY OF BEAMS AND POSTS FOR STACK CONSTRUCTION
US9914467B2 (en) 2015-08-14 2018-03-13 Oldcastle Light Building Products, LLC Attachment and support members for modular building structures
US10344487B2 (en) 2015-08-14 2019-07-09 Oldcastle Light Building Products, LLC Attachment and support members for modular building structures
US10011982B1 (en) * 2015-09-23 2018-07-03 Theodore W. Baker School spaces retrofitted for alternative uses and related technology
US11359365B2 (en) * 2015-11-02 2022-06-14 Orient Holding As Heating and cooling system of a modular residential building
US10961710B2 (en) 2016-03-07 2021-03-30 Innovative Building Technologies, Llc Pre-assembled wall panel for utility installation
US10508442B2 (en) 2016-03-07 2019-12-17 Innovative Building Technologies, Llc Floor and ceiling panel for slab-free floor system of a building
US10676923B2 (en) 2016-03-07 2020-06-09 Innovative Building Technologies, Llc Waterproofing assemblies and prefabricated wall panels including the same
US10900224B2 (en) 2016-03-07 2021-01-26 Innovative Building Technologies, Llc Prefabricated demising wall with external conduit engagement features
US20190153720A1 (en) * 2016-04-29 2019-05-23 Rbon Holdings Pty Ltd Modular beam structure and modular base structure
US10689840B2 (en) * 2016-04-29 2020-06-23 Rbon Holdings Pty Ltd Modular beam structure and modular base structure
US9963877B2 (en) * 2016-05-18 2018-05-08 David R. Hall Modular prismatic box-like structure-based building method and infrastructure
US10301813B1 (en) * 2016-10-31 2019-05-28 John P. Hawkins Portable core facility for a building
US11130625B2 (en) 2016-11-01 2021-09-28 Storage Ip Llc Self-storage facility, fabrication, and methodology
US20180209136A1 (en) * 2017-01-24 2018-07-26 Affordable Modular Systems, LLC Lightweight steel parallel modular constructions system with synthetic modules
US11002003B2 (en) * 2017-01-24 2021-05-11 Affordable Modular Systems, LLC Lightweight steel parallel modular constructions system with synthetic modules
US10724228B2 (en) 2017-05-12 2020-07-28 Innovative Building Technologies, Llc Building assemblies and methods for constructing a building using pre-assembled floor-ceiling panels and walls
US10323428B2 (en) * 2017-05-12 2019-06-18 Innovative Building Technologies, Llc Sequence for constructing a building from prefabricated components
US11098475B2 (en) 2017-05-12 2021-08-24 Innovative Building Technologies, Llc Building system with a diaphragm provided by pre-fabricated floor panels
US10487493B2 (en) * 2017-05-12 2019-11-26 Innovative Building Technologies, Llc Building design and construction using prefabricated components
US10704251B1 (en) * 2017-07-25 2020-07-07 Vessel Technologies, Inc. Modular housing system and methods for using the same
US20190032327A1 (en) * 2017-07-31 2019-01-31 Brent Musson Permanent building structure with reusable modular building units
US10731328B1 (en) * 2017-10-13 2020-08-04 Ob Development Llc Temporary or semi-permanent structure and method of increasing usable space
US10450739B1 (en) * 2017-10-13 2019-10-22 Ob Development Llc Temporary or semi-permanent structure and method of increasing usable space
US11505939B2 (en) * 2018-03-21 2022-11-22 Best Gen Modular, Inc. Reinforcing structure for modular building construction
US11536043B2 (en) * 2018-08-06 2022-12-27 Jeffrey J. Konczak Modular mini building system for parking lots
US20220282474A1 (en) * 2019-08-06 2022-09-08 Jgc Corporation Module for separate conveyance, structure for plant, and method of constructing structure for plant
US12188220B2 (en) * 2019-09-18 2025-01-07 Gs Licenseco Llc Self-storage facility, fabrication, and methodology
US20220341156A1 (en) * 2019-09-18 2022-10-27 Storage Ip Llc Self-Storage Facility, Fabrication, and Methodology
US20210334425A1 (en) * 2020-04-22 2021-10-28 SNL Fund, LLC Method of designing, configuring and accessing a modular self-storage facility
USD968650S1 (en) * 2020-05-20 2022-11-01 Alibaba Group Holding Limited Mobile conference room
US11959269B2 (en) * 2020-06-09 2024-04-16 Sma Solar Technology Ag Platform for stacking containers as housings of components of an energy conversion system, and energy conversion system
US20220145611A1 (en) * 2020-06-09 2022-05-12 Sma Solar Technology Ag Platform for stacking containers as housings of components of an energy conversion system, and energy conversion system
US20220042342A1 (en) * 2020-08-05 2022-02-10 Empowerment Innovation Lab Modular shelter pods
US11739546B2 (en) * 2020-08-05 2023-08-29 Empowerment Innovation Lab Modular shelter pods
US11629491B1 (en) * 2021-04-01 2023-04-18 Factory OS Inc. Interchangable modular construction method
US12091872B2 (en) * 2021-05-20 2024-09-17 Sano Development Limited Hybrid building system, building and method
US20230250656A1 (en) * 2021-05-20 2023-08-10 Sano Development Limited Hybrid building system, building and method
US12203281B2 (en) * 2021-05-20 2025-01-21 Sano Development Limited Hybrid building system, building and method
US11885145B2 (en) 2021-05-20 2024-01-30 Sano Development Limited Hybrid building system, building and method
US12180730B2 (en) * 2021-05-20 2024-12-31 Sano Development Limited Hybrid building system, building and method
US12180731B2 (en) 2021-05-20 2024-12-31 Sano Development Limited Hybrid building system, building and method
US20240229449A1 (en) * 2021-05-20 2024-07-11 Sano Development Limited Hybrid building system, building and method
US20230203829A1 (en) * 2021-05-20 2023-06-29 Sano Development Limited Hybrid building system, building and method
US12065823B2 (en) * 2021-08-10 2024-08-20 Surepods, Llc Systems and methods for providing modular building structures based on site-specific conditions
US20230048518A1 (en) * 2021-08-10 2023-02-16 Surepods, Llc Systems and methods for providing modular building structures based on site-specific conditions
US11976484B2 (en) * 2022-03-18 2024-05-07 Cary James Henson Modular dwelling constructed from vertically oriented intermodal containers
US20230295939A1 (en) * 2022-03-18 2023-09-21 Cary James Henson Modular dwelling constructed from vertically oriented intermodal containers
WO2024023342A1 (en) * 2022-07-29 2024-02-01 Sano Development Limited Modular building unit, building system, building and associated methods

Similar Documents

Publication Publication Date Title
US20110056147A1 (en) Load-bearing construction pod and hybrid method of construction using pods
US10323428B2 (en) Sequence for constructing a building from prefabricated components
US6625937B1 (en) Modular building and method of construction
US9556632B2 (en) Method and system for construction of a building
US9464436B2 (en) Prefabricated panel for a building
US11505939B2 (en) Reinforcing structure for modular building construction
US3822519A (en) Building structure
CN105863110A (en) Modular assembling type cold-bent thin-wall type steel wall board structural system
CN103821229A (en) Rapid assembly type integrated house and installation method
TWI814113B (en) Pre-manufactured floor-ceiling corridor panel for a multi-story building having load bearing walls
CN104641048A (en) Waffle Box Building Techniques
US11713582B2 (en) Building structure and method of construction
US11274430B2 (en) Building structure and method of construction
CN211172365U (en) Assembled low-rise residential structure system
AU2011276960A1 (en) A method of transportation and assembly of building modules
US20230374805A1 (en) Building Structure and Method of Construction
JP5736168B2 (en) Wooden building
AU2024219487A1 (en) Prefabricated Construction Modules
JP4201209B1 (en) Support framework structure
AU2009243510A1 (en) Construction, construction method, and method of relocation of a construction
KR20140120193A (en) Seismic reinforcement structure type articulated and reinforcement method of using it
AU2012216447A1 (en) A Method of Assembly of Single and/or Multi Storey Dwelling from Transportable Modules

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION

点击 这是indexloc提供的php浏览器服务,不要输入任何密码和下载