US20040020138A1 - Modular platform system - Google Patents
Modular platform system Download PDFInfo
- Publication number
- US20040020138A1 US20040020138A1 US10/632,889 US63288903A US2004020138A1 US 20040020138 A1 US20040020138 A1 US 20040020138A1 US 63288903 A US63288903 A US 63288903A US 2004020138 A1 US2004020138 A1 US 2004020138A1
- Authority
- US
- United States
- Prior art keywords
- framing member
- respect
- platform module
- platform
- framing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000009432 framing Methods 0.000 claims abstract description 212
- 239000000725 suspension Substances 0.000 claims abstract description 68
- 238000000034 method Methods 0.000 claims abstract description 19
- 230000004888 barrier function Effects 0.000 claims description 5
- 239000002904 solvent Substances 0.000 claims description 3
- 125000006850 spacer group Chemical group 0.000 claims description 3
- 239000000463 material Substances 0.000 description 12
- 239000011120 plywood Substances 0.000 description 9
- 239000003973 paint Substances 0.000 description 7
- 239000002023 wood Substances 0.000 description 7
- 238000010276 construction Methods 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000004567 concrete Substances 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 239000002184 metal Substances 0.000 description 4
- 239000002131 composite material Substances 0.000 description 3
- 231100001261 hazardous Toxicity 0.000 description 3
- 239000000383 hazardous chemical Substances 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 238000012423 maintenance Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 238000010422 painting Methods 0.000 description 3
- 238000005488 sandblasting Methods 0.000 description 3
- 231100000331 toxic Toxicity 0.000 description 3
- 230000002588 toxic effect Effects 0.000 description 3
- 238000013459 approach Methods 0.000 description 2
- 238000005422 blasting Methods 0.000 description 2
- 239000011810 insulating material Substances 0.000 description 2
- 230000003068 static effect Effects 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 239000011152 fibreglass Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 239000002990 reinforced plastic Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/10—Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
- E01D19/106—Movable inspection or maintenance platforms, e.g. travelling scaffolding or vehicles specially designed to provide access to the undersides of bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
- E04G3/30—Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
- E04G2003/283—Mobile scaffolds; Scaffolds with mobile platforms mobile horizontally
Definitions
- This invention relates to a modular platform system and a method of installing the modular platform system, wherein a plurality of operatively connected platform modules can be quickly and efficiently suspended with respect to a working location. More specifically, this invention relates to a modular platform system and method of installing the system wherein a plurality of platform modules can be installed and suspended with respect to a bottom or underside support surface of a bridge structure or other structure, for example.
- deck structures are supported by an angle bracket having one leg structurally welded to an edge portion or an underside of a horizontal flange of a steel stringer, a steel plate, a girder, or another suitable steel primary structural member.
- Deck pans or other suitable deck panels of these deck structures are individually positioned between opposing angle brackets which are welded into place in the field. Each deck pan is positioned upon horizontal flanges of such field-installed opposing angle brackets. The deck pan is then secured with a sheet metal screw or a weld, also at the job site.
- each vertical height adjustment to vary the elevation of the top of the deck pan requires labor-intensive field adjustments, of ten accomplished with welded connections. Further, many of these deck framing systems have welded connections or metal fasteners exposed beneath the deck structure.
- a problem associated with deck framing systems and methods therefor that precede the present invention is that they do not facilitate quick installation of the deck panels by permitting pre-placement of the securement means prior to installation of the deck panels, and movement of the securement means as the deck panels are installed.
- Still a further problem associated with deck framing systems and methods therefor that precede the present invention is that they do not facilitate efficient transportation to a job site in a manner that saves shipping space and thereby saves time, energy and money.
- the above and other objects of this invention are accomplished with a platform module suspendable from a structure.
- the platform module includes a first framing member suspended with respect to the structure and a second framing member suspended with respect to the structure and mounted with respect to the first framing member.
- At least one deck panel is positioned between the first framing member and the second framing member and suspended with respect to the structure to provide a working surface for the contractors working on the structure.
- the platform modules are removably mounted or suspended with respect to the structure using adjustable suspension members connected or attached to the first framing member and the second framing member.
- the modular platform system includes a second platform module that is movably connected to the first platform module so that it is movable between a first position operatively connected to the first platform module and a second or extended position wherein the second platform module is linearly aligned with the first platform module and suspended with respect to the structure.
- a second platform module that is movably connected to the first platform module so that it is movable between a first position operatively connected to the first platform module and a second or extended position wherein the second platform module is linearly aligned with the first platform module and suspended with respect to the structure.
- at least one and preferably a plurality of channel trolleys are mounted to each framing member of the first platform module.
- the channel trolleys include rotatable wheels that can be positioned within a channel formed by the corresponding framing member of the second platform module to allow the second platform module to move with respect to the first platform module suspended from the structure.
- the second platform module can be the same or similar to the first platform module, or different.
- the second platform module includes a first framing member operatively connected to the first platform module first framing member and a second framing member operatively connected to the first platform module second framing member.
- a deck panel is positioned between the first framing member and the second framing member.
- the second platform module can be removably mounted or suspended with respect to the structure using adjustable suspension members attached to each framing member, in the second position. In the second position, the first platform module and the second platform module can be connected or secured in linear alignment using any suitable mechanical connection known to those having ordinary skill in the art.
- linear alignment as used throughout this specification refers to alignment of abutting framing members generally parallel in a direction along a width of the structure so that the upper surfaces of adjacent platform modules are flush.
- the deck panel may be any suitable material depending upon the intended use for the platform module.
- the deck panel may be made of wood panels or wood composite materials, concrete, metal, fiberglass or other suitable insulating materials, composites and combinations thereof. Further, the deck panel may provide a barrier to vapor, heat, and/or solvents, for example.
- the deck panel may have any suitable size to span between the first framing member and the second framing member along a length of the framing members.
- the modular platform system can be easily installed to suspend from a structure, such as a support structure of a bridge construction.
- the suspended modular platform system of the present invention preferably comprises a plurality of operatively connected platform modules stacked or otherwise configured in a compact or efficient manner.
- independent platform modules may be connected together to form the suspended modular platform system.
- the platform modules can be raised from a ground surface or can be lowered from a surface of the bridge structure to position the suspended modular platform system with respect to the underside support surface of the bridge construction.
- the modular platform system can be hoisted using a crane or other suitable machinery and suspended over an edge portion of the bridge.
- the modular platform system is positioned with respect to the underside support surface of the bridge structure and the first platform module is secured in position with respect to the support surface using at least one support member.
- the first and second framing members are suspended from the support surface of the structure.
- the framing members can be securely connected to the stringers of the bridge using suitable beam clamps, for example, and run or extend perpendicular to the stringers, i.e. towards the centerline of the bridge.
- a preferred beam clamp is available from Multuloc Corp. located in Park Ridge, Ill., U.S.A. under the trade name Tuloc beam clamp.
- the second framing members are suspended from the support surface and run or extend parallel with the first framing members.
- the first and second framing members may not run or extend in a parallel direction. Rather, in such an embodiment, the framing members may converge or diverge with respect to each other as the framing members approach the centerline of the bridge.
- the first platform module is suspended with respect to the structure.
- a second platform module is extended from a first position operatively connected to the first platform module to a second position linearly aligned with the first platform module and suspended with respect to the structure.
- the second platform module can be connected to the first platform module in the second position using any suitable mechanical connection.
- Each of the platform modules are suspended with respect to the structure using at least one adjustable suspension member attached to the first framing member and at least one adjustable suspension member attached to the second framing member.
- each suspension member is removably mounted with respect to a support surface of the structure, such as a support beam or stringer.
- a second modular platform system can be constructed laterally adjacent to the first modular platform system and suspended with respect to the structure.
- the second modular platform system can be connected to the first modular platform system.
- the vertical distance of adjacent panel structures with respect to the support surface may be adjusted to form a level panel structure surface.
- the adjacent panel structures may form steps or a “stepped” panel structure surface.
- the framing members may be adjustably connected to the support surface using threaded rods and/or turn buckles.
- the modular platform system is easily removed from the structure and can be reused.
- the extended platform modules can be retracted from the second position to the first position after the suspension members are disconnected from the support stringers.
- the retracted modular platform system can then be hoisted up to the upper surface of the structure using a crane or other suitable machinery and easily loaded onto a truck for removal from the work location. Any number of modular platform systems can be used to form a suitable platform, depending upon the size of the job.
- FIG. 1A is a side view of a modular platform system comprising a platform module suspended with respect to a structure, according to one preferred embodiment of this invention
- FIG. 1B is a side view of a modular platform system comprising a platform module suspended with respect to a structure, according to one preferred embodiment of this invention
- FIG. 2 is a side view of a platform module removably connected with respect to a structure, according to one preferred embodiment of this invention
- FIG. 3A is a side view of a platform module removably connected with respect to a structure, according to one preferred embodiment of this invention.
- FIG. 3B is a front view of a platform module removably connected with respect to a structure, according to one preferred embodiment of this invention.
- FIG. 3C is a front view of a platform module removably connected with respect to a structure, according to one preferred embodiment of this invention.
- FIG. 4 is a perspective view of a channel trolley, according to one preferred embodiment of this invention.
- FIG. 5 is a perspective view of a channel trolley, according to one preferred embodiment of this invention.
- FIG. 6 is a front view of a modular platform system comprising a plurality of operatively connected platform modules, according to one preferred embodiment of this invention.
- FIG. 7 is a side view of a modular platform system comprising a plurality of operatively connected platform modules in a first position and a first platform module removably suspended from adjacent stringers of the structure, according to one preferred embodiment of this invention
- FIG. 8 is a side view of a modular platform system comprising a plurality of platform modules each in a second or extended position, according to one preferred embodiment of this invention.
- FIG. 9 is a front view of a platform module connected to adjacent platform modules and suspended with respect to a structure, according to one preferred embodiment of this invention.
- FIG. 10 is a front view of a platform module connected in a stepped fashion to adjacent platform modules and suspended with respect to an angled or sloped bottom support surface of a structure, according to one preferred embodiment of this invention
- FIG. 11 is a perspective view of a platform module, according to one preferred embodiment of this invention.
- FIG. 12 is a perspective view of a platform module, according to one preferred embodiment of this invention.
- FIG. 13 is a perspective view of a modular platform system having a guard rail system, according to one preferred embodiment of this invention.
- FIG. 14 is a front view of a guard rail system post secured within a framing member, according to one preferred embodiment of this invention.
- FIG. 15 is a front view of a modular platform system comprising a first platform module operatively connected to a second platform module, according to one preferred embodiment of this invention.
- the modular platform system 10 of the present invention can be suspended with respect to a structure to support a dynamic and/or static load with respect to an underside surface of the structure.
- the structure may comprise a bridge construction having a plurality of support beams or stringers extending along a length of the bridge to form support surfaces.
- modular platform system 10 can be installed to suspend from the underside of the bridge to allow access to desired areas of the structure. Such repair may include slab demolition, sand or shot blasting the supporting steel and painting the steel structure.
- modular platform system 10 can be adapted to contain debris, such as concrete pieces, removed from the bridge to prevent the debris from falling to the ground or into the water.
- modular platform system 10 includes a containment means for containing environmentally hazardous or toxic material, such as lead-based paint, after the hazardous or toxic material has been removed from the structure.
- the containment means prevents the environmentally hazardous or toxic material from entering into the atmosphere.
- Modular platform system 10 can be constructed and/or installed from the ground, where the structure spans a street or highway, or can be constructed and/or installed from the structure itself, where the structure spans a body of water, for example.
- Modular platform system 10 can span any suitable distance, for example about 10 feet to at least about 100 feet, in order to allow access to the entire underside of the bridge structure or other structure. Further, modular platform system 10 may extend past the edge portion of the structure for easy access to materials and/or a side portion of the structure. It is apparent to those skilled in the art that the modular platform system of the present invention can be adapted to span any desired distance with respect to the structure.
- modular platform system 10 comprises a plurality of platform modules 12 .
- Each platform module 12 is suspendable with respect to a structure 100 , such as a bridge structure.
- each platform module 12 may be mounted or secured to at least one support surface, such as a support beam or stringer positioned on an underside or bottom surface of the bridge structure.
- the support stringers are typically positioned generally parallel to a longitudinal centerline of the bridge structure along a length of the bridge.
- platform module 12 comprises a first framing member 14 suspended with respect to the structure.
- first framing member 14 may be suspended to extend or span between adjacent support stringers.
- a second framing member 16 is suspended with respect to the structure and mounted with respect to first framing member 14 .
- second framing member 16 can be suspended to extend or span between the adjacent support stringers and extend or run generally parallel to first framing member 14 .
- first framing member 14 may or may not be parallel to second framing member 16 .
- adjacent modular platform systems 10 may be positioned in a skewed position, a fanned position or a straight position with respect to each other.
- At least one deck panel 18 is positioned between first framing member 14 and second framing member 16 and suspended with respect to the structure 100 .
- Deck panel 18 may comprise any suitable material having sufficient strength to support contractors, materials, tools and debris. Suitable deck panel materials include metal sheets such as shown in FIG. 11, wood, concrete, composite materials including insulating materials such as shown in FIG. 12, and combinations thereof, depending upon the overall size and intended use of modular platform system 10 , for example. Further, deck panel 18 may have any suitable length, width and/or thickness.
- deck panel 18 comprises a suitable material to provide a barrier or seal, such as a vapor barrier, an insulating barrier, a heat seal, or a solvent seal.
- a barrier or seal such as a vapor barrier, an insulating barrier, a heat seal, or a solvent seal.
- Adjacent decl panels 18 positioned between first framing member 14 and second framing member 16 may be flush or may overlap with respect to adjacent deck panels 18 .
- At least one suspension member 20 is used to suspend each of first framing member 14 and second framing member 16 with respect to the structure 100 .
- a length of suspension member 20 is adjustable.
- at least one suspension member 20 is connected or attached between first framing member 14 and the structure 100 .
- suspension member 20 comprises a clamp or other suitable mechanical connection at a first end portion of suspension member 20 to removably mount first framing member 14 to a support stringer 110 of the structure 100 .
- at least one suspension member 20 is connected or attached to second framing member 16 and removably mounted with respect to the structure.
- Suspension member 20 preferably comprises a chain or cable 40 having a first connection, such as hook 42 , positioned at a first end portion 44 and a second connection, such as hook 46 , positioned at a second end portion 48 , as shown in FIG. 1A.
- Hooks 42 and/or 46 allow the framing members to be suspended from the support stringers quickly and easily.
- each hook 42 , 46 comprises a pivot arm to allow the hook to “snap” connect with a corresponding loop fastener.
- Cable 40 may have any suitable length to suspend first framing member 14 and/or second framing member 16 at a desired position or distance with respect to support stringer 110 .
- the length of cable 40 is adjustable.
- At least one loop fastener 50 is secured to first framing member 14 .
- loop fastener 50 may be threadedly connected to a bolt 52 that is secured to first framing member 14 .
- a bracket 54 is in contacting relation with an inner surface of first framing member 14 .
- bracket 54 and at least a portion of bolt 52 are positioned within a cavity 55 formed by first framing member 14 .
- Loop fastener 50 and bolt 52 are rotatable with respect to each other to tighten or secure fastener 50 to first framing member 14 .
- a beam clamp 80 is positioned and secured to a support beam or stringer 110 , as shown in FIG. 1A.
- Beam clamp 80 comprises a bolt 84 connected to a bracket or transport trolley 81 .
- a suitable transport trolley is available from Multuloc Corp. located in Park Ridge, Ill., U.S.A. under the trademark TULOC.
- Bolt 84 can be connected or mounted to transport trolley 81 using a weld or a suitable mechanical connection.
- transport trolley 81 preferably runs generally parallel with a side edge of the stringer 110 .
- a bottom bracket 85 is in contacting relation with a bottom surface of the stringer 110 .
- bottom bracket 85 is threadedly connected to bolt 84 to maintain bottom bracket 85 in contacting relation with support stringer 110 .
- a top bracket 86 is positioned about bolt 84 and maintained in contacting relation with support stringer 110 by a nut arrangement 87 .
- a set screw 91 is threadedly connected to top bracket 86 and rotatable with respect to top bracket 86 to secure beam clamp 80 with respect to the support stringer.
- Nut arrangement 87 comprises a beveled washer 90 which allows beam clamp 80 to be secured to a support beam or stringer having any suitable thickness, regardless of whether the stringer has a flat contacting surface or a sloped contacting surface.
- some old beams and channels have an interior flange surface with a 1 to 6 slope.
- Beam clamp 80 compensates for the sloped top flange surface by providing beveled washer 90 and a tolerance between bolt 84 and an aperture formed in top bracket 86 within which bolt 84 is positioned.
- bolt 84 has a 1 ⁇ 2 inch diameter and the aperture formed in the top bracket 86 has a ⁇ fraction (9/16) ⁇ inch diameter.
- top bracket 86 has a 1 to 6 slope with respect to bolt 84 to maintain a contacting relation with the sloped flange surface of the stringer.
- Beam clamp 80 maintains maximum torque, and coupled with set screw 91 , resists lateral forces to provide full contact at the beam edge and point contact bearing through set screw 91 while adjusting for any tolerance variances.
- a wire or cable 88 can be connected between suspension members 20 at beam clamp 80 positioned with respect to the support stringer 110 to maintain beam clamp 80 securely connected with respect to the support stringer 110 .
- At least one channel trolley 70 is mounted with respect to transport trolley 81 .
- channel trolley 70 is positioned within a channel 83 formed by transport trolley 81 .
- channel trolley 70 comprises at least one rotatable wheel 72 .
- Rotatable wheels 72 are positionable within channel 83 to allow relative movement of platform module 12 with respect to the stringer 110 .
- Suspension member 20 preferably comprises a second connection, such as hook 46 , positioned at a second end portion 48 , as shown in FIG. 1A.
- Hook 46 allows the framing members to be suspended from the support stringers quickly and easily.
- each hook 46 comprises a pivot arm to allow the hook to “snap” connect with an aperture formed in channel trolley 70 .
- At least one loop fastener 50 is secured to first framing member 14 .
- loop fastener 50 may be threadedly connected to a bolt 52 that is secured to first framing member 14 .
- a bracket 54 is in contacting relation with an inner surface of first framing member 14 .
- bracket 54 and at least a portion of bolt 52 are positioned within a cavity 55 formed by first framing member 14 .
- Loop fastener 50 and bolt 52 are rotatable with respect to each other to tighten or secure fastener 50 to first framing member 14 .
- a fastener 50 can be connected directly to bolt 84 .
- fastener 50 contacts bottom bracket 85 to maintain beam clamp 80 securely fastened to the stringer 110 .
- hook 46 is easily connected to fastener 50 to suspend platform module 12 with respect to the structure.
- cable 40 can be positioned between bottom bracket 85 and the stringer so that hook 42 and hook 46 each are connected to loop fastener 50 , connected to framing member 14 , 16 .
- Beam clamp 80 allows a containment or safety system, such as a net or fence suspended with respect to the structure and/or a load bearing system, such as modular platform system 10 , for supporting a load, for example contractors working on the structure, to be connected with respect to the structure.
- a containment or safety system such as a net or fence suspended with respect to the structure
- a load bearing system such as modular platform system 10
- each of first framing member 14 and second framing member 16 is removably suspended or mounted to the structure using beam clamp 80 , as shown in FIGS. 3 A- 3 C.
- Beam clamp 80 comprises a strut 82 .
- At least one suspension member 20 is mounted or connected with respect to strut 82 which extends along a width of support stringer 110 .
- a suspension member 20 is connected at first end portion 44 having a first hook 42 to a first loop fastener 50 mounted to first framing member 14 and at a second end portion 48 having a second hook 46 to a second loop fastener 50 mounted to first framing member 14 .
- At least one suspension member 20 runs through at least a portion of a channel formed by strut 82 and around at least one pin connection 93 positioned within an aperture 92 formed in strut 82 .
- two suspension members 20 may be independently connected to strut 82 using pin connections 93 positioned within a desired aperture 92 .
- Bolt 84 is connected to strut 82 , for example, using a weld or a suitable mechanical connection.
- Bottom bracket 85 and top bracket 86 are positioned about bolt 84 and maintained in contacting relation with support stringer 110 by nut arrangement 87 .
- bottom bracket 85 is threadedly connected to bolt 84 to maintain bottom bracket 85 in contacting relation with support stringer 110 .
- Set screw 91 is threadedly connected to top bracket 86 and rotatable with respect to top bracket 86 to secure beam clamp 80 with respect to the support stringer.
- Beveled washer 90 allows beam clamp 80 to be secured to a support beam or stringer having any suitable thickness, regardless of whether the stringer has a flat contacting surface or a sloped contacting surface.
- strut 82 forms a plurality of apertures 92 for mounting each suspension member 20 with respect to strut 82 .
- a distance between the framing member and the support stringer is adjustable by selecting a desired or appropriate aperture 92 within which pin connection 93 can be secured to adjust a length of suspension member 20 positioned between strut 82 and framing members 14 , 16 , depending upon the physical limitations associated with the intended use of modular platform system 10 .
- two or more suspension members 20 can be connected with respect to strut. 82 to allow framing member 14 , 16 of laterally adjacent platform modules 12 to be suspended with respect to structure 100 .
- a strut 95 can be connected to adjacent beam clamps 80 .
- Strut 95 forms a channel within which at least one channel trolley 70 can be movably positioned.
- At least one suspension member 20 can be connected to channel trolley 70 to suspend platform module 12 with respect to structure 100 .
- Channel trolley 70 comprises rotatable wheels 72 which can be movably positioned within the strut channel to allow suspended platform module 12 to move with respect to the structure.
- modular platform system 10 comprises a plurality of operatively connected platform modules 12 which are suspended or supported with respect to the structure.
- Each platform module 12 comprises a first framing member 14 , a second framing member 16 and at least one deck panel 18 positioned between first framing member 14 and second framing member 16 and suspendable with respect to structure 100 , as shown for example in FIG. 6.
- a second platform module 12 ′ is movable with respect to the first platform module 12 between a first position operatively connected to first platform module 12 and a second or extended position linearly aligned with first platform module 12 .
- second platform module 12 ′ is the same or similar to first platform module 12 .
- Second platform module 12 ′ comprises a first framing member 14 ′ movably mounted to at least one channel trolley 70 secured or mounted with respect to first platform module first framing member 14 and a second platform module second framing member 16 ′ movably mounted to at least one channel trolley 70 secured or mounted with respect to first platform module second framing member 14 .
- Rotatable wheels 72 are positionable within a channel 75 , 76 formed by the second platform module framing member 14 ′, 16 ′, respectively.
- second platform module 12 ′ is removably suspended with respect to the structure from a support beam or stringer for example, and in linear alignment with platform module 12 , using at least one suspension member 20 attached to first framing member 14 ′ and at least one suspension member 20 attached to second framing member 16 ′.
- a connecting bracket or other suitable mechanical connection can be used to connect first framing member 14 ′ in linear alignment with first framing member 14 and second framing member 16 ′ in linear alignment with second framing member 16 .
- deck panel 18 ′ positioned between first framing member 14 ′ and second framing member 16 ′, is suspended with respect to the structure.
- first framing member 14 and corresponding second framing member 16 extend between the first support stringer 110 and a second support stringer 110 ′ of the structure, generally parallel to the first support stringer 110 . It is apparent to those skilled in the art and guided by the teachings herein provided, that each of first framing member 14 and second framing member 16 may have any suitable length, as required by the size of the structure and the system application.
- a second plurality of operatively connected platform modules 12 can be suspended or supported from the structure and positioned laterally adjacent the first plurality of platform modules 12 , as shown in FIGS. 9 and 10, such that first framing member 14 of platform module 12 contacts or approaches second framing member 16 of the laterally adjacent platform modular 12 .
- Laterally adjacent platform modules 12 can be connected using a connecting bracket or other suitable mechanical connection.
- a closure element 98 can be “snap-fitted” into a space formed at a connection of adjacent platform modules 12 , as shown in FIG. 9.
- Closure element 98 contains debris, including hazardous materials such as lead-paint.
- a panel for example wood or a containment tarp 99 , such as shown in FIG. 10, is positioned across the laterally adjacent platform modules 12 to maintain a tight seal between the platform modules 12 to contain debris and/or environmentally hazardous materials, such as lead paint removed from the structure.
- containment tarp 99 is preferably flexible to connect laterally adjacent platform modules 12 that are not level, or stepped, as a result of the structure or its support stringers being angled or sloped.
- One suitable material for containment tarp 99 is a reinforced plastic material having a thickness of about 6 mils. It should be apparent to those having ordinary skill in the art and guided by the teachings herein that other materials are suitable for containment tarp 99 .
- modular platform system 10 is installed on a structure, such as a highway or road bridge, having a plurality of support beams or stringers generally parallel the longitudinal centerline of the bridge along the length of the bridge.
- Modular platform system 10 is preferably, but not necessarily, installed laterally across the bridge, i.e. generally perpendicular to the length of the support beams or stringers.
- Modular platform system 10 including a plurality of operatively connected platform modules 12 is temporarily suspended with respect to the underside of the bridge, for example using a crane or other suitable machinery positioned on a top or road surface of the bridge.
- first framing member 14 is removably mounted to a first support beam or stringer using suspension member 20 .
- second framing member 16 is removably mounted to the first support beam or stringer using suspension member 20 .
- each of first framing member 14 and second framing member 16 is suspended with respect to the structure using adjustable suspension members 20 so that the distance between panel 18 and the underside of the bridge can be adjusted according to the work scheduled on the bridge.
- Platform module 12 ′ is extended from the first position below platform module 12 to the second or extended position linearly aligned with platform modular 12 .
- Platform module 12 ′ is suspended from the structure.
- First framing member 14 ′ and second framing member 16 ′ are removably mounted to the support beam or stringer using suspension member 20 .
- platform module 12 ′ With platform module 12 ′ in the second position and in linear alignment with platform module 12 , platform module 12 ′ can be connected or attached to platform module 12 using a suitable mechanical connection.
- first framing member 14 ′ can be fastened or connected to first framing member 14 and second framing member 16 ′ can be fastened or connected to second framing member 16 using a connecting bracket.
- a second modular platform system preferably the same or similar to the first modular platform system, is constructed with respect to the structure.
- the second modular platform system can be suspended with respect to the structure laterally adjacent the first modular platform system comprising a plurality of operatively connected platform modules.
- the second modular platform system can be suspended with respect to the structure as the first modular platform system is suspended.
- second modular platform system is connected to the first modular platform system using any suitable mechanical connections.
- wood pieces and/or tarp pieces can be positioned at the abutting framing members to provide containment or seal spaces between adjacent framing members.
- modular platform system 10 may be suspended from support stringer 110 , at a first vertical distance to preform one process, such as sandblasting, and then lowered or raised to a second vertical distance with respect to support stringer 110 to perform another process, such as painting.
- a threaded rod extension coupled to a coupler nut can be connected with respect to the structure.
- the coupler nut can be rotated to allow a plate securing each structure to a beam flange to be rotated by a suitable rotational distance, for example about 180°, to allow the panel structure to be raised or lowered with respect to the beam flange in order to continue work on the structure, if desired.
- the coupler nut or other suitable mechanical connection can also prevent or limit damage to the threaded rod extension as a result of processes such as sandblasting and painting. It is apparent that suitable mechanical connections may be used to secure the structures directly or indirectly to the support surface.
- a counter-balancing weight 101 such as shown in FIG. 7, for example a suitably-sized concrete block, can be positioned on one end portion of modular platform system 10 so that the modular platform system 10 is cantilevered over the edge portion of the bridge. Adjustments can be made, for example in increments of about 6 inches, with respect to balancing modular platform system 10 by positioning the counter-balancing weight with respect to a length of modular platform system 10 .
- one counter-balancing weight can handle a variety of loads by moving the weight along a length of modular platform system 10 .
- modular platform system 10 spans a hard surface, for example a road or highway
- modular platform system can be suspended with respect to the structure from the surface below.
- a rough terrain scissors lift or other suitable machine can move or lift modular platform system 10 into position with respect to the structure and suspension members 20 may be connected to beam clamps 80 properly positioned on the support stringers of the structure to suspend modular platform system 10 with respect to the structure.
- platform module 12 comprises an absorbing layer of plywood applied over deck panels 18 to protect platform module 12 so that modular platform system 10 is reusable.
- the plywood panels or sheets absorb the weight of concrete pieces dropping onto modular platform system 10 during demolition, for example.
- tight seals can be formed using the plywood to contain lead-base paint dust, for example, created during sand blasting or shot blasting procedures.
- the plywood sheets are attached to modular platform system 10 by nailing the plywood and/or plywood clamping strips to wood, for example pieces of standard 2 ⁇ 4s, positioned within each framing member.
- the pieces of wood are inserted into the rolled shape of the framing member.
- any suitable mechanical connection may be used to secure the plywood sheets to the platform panels.
- the top piece of plywood may clamp a 4 foot standard width plywood piece in place.
- platform module 12 may further comprise at least one adjustable strut spacer 97 , such as shown in FIG. 11, having a first end portion connected with respect to first framing member 14 and a second end portion connected with respect to second framing member 16 .
- Strut spacer 97 provides increased strength and rigidity to the platform module 12 , particularly when platform module 12 is subjected to large loads.
- a guard rail system 120 suitable for adhering to government safety standards, such as O.S.H.A., is connected to modular platform system 10 .
- Guard rail system 120 preferably comprises a plurality of posts 122 positioned within and secured to first framing member 14 and/or second framing member 16 .
- a chain or cable 124 extends between the posts 122 to provide perimeter protection and prevent workers from falling from the side of modular platform system 10 .
- posts 122 are positioned within and secured to framing member 14 , 16 using a bolt and nut combination.
- bolt 126 is threadedly connected to a bottom portion 128 of post 122 .
- Bolt 126 is rotatable with respect to a plate or bracket 130 positioned within the framing member to tighten and secure post 122 with respect to the framing member. It should be apparent to those skilled in the art and guided by the teachings herein that other suitable mechanical connections may be used to secure each post 122 to the corresponding framing member 14 , 16 .
- platform module 212 comprises a first framing member 214 suspended with respect to the structure, and a second framing member 216 , the same or similar to first framing member 214 , suspended with respect to the structure and mounted with respect to first framing member 214 .
- At least one suspension member 220 is used to suspend each of first framing member 214 and second framing member 216 with respect to the structure 100 .
- at least one suspension member 220 is connected or attached between first framing member 214 and the structure 100 .
- at least one suspension member 220 ′ is connected or attached to second framing member 216 and removably mounted with respect to the structure.
- suspension member 220 and suspension member 220 ′ may be shown according to different embodiments of this invention. However, it should be apparent to those having ordinary skill in the art that suspension member 220 may be the same or similar to suspension member 220 ′.
- Suspension member 220 may comprise a threaded rod 221 connected at a first end portion 222 to one of first framing member 214 and second framing member 216 , and at a second end portion 224 to the structure.
- a lower bracket 225 is positioned at a first edge surface 215 of first framing member 214 .
- a nut 226 is threadedly connected to an end portion of threaded rod 221 to maintain lower bracket 225 in contacting relation with first edge surface 215 .
- nut 226 is positioned within a cavity 227 formed by first framing member 214 .
- An upper bracket 229 is positioned at a second edge surface 217 of first framing member 214 and a nut 230 is threadedly connected to threaded rod 221 to maintain upper bracket 229 in contacting relation with second edge surface 217 .
- Nut 226 and nut 230 are rotatable with respect to each other about threaded rod 221 to tighten or secure suspension member 220 to first framing member 214 .
- nut 226 can be positioned along a length of threaded rod 221 to position first framing member 214 at a desired position or distance with respect to the structure 100 .
- a similar mechanical connection can be used to secure second end portion 224 to the structure 100 .
- an upper bracket 232 is positioned at second end portion 224 .
- a nut 234 is threadedly connected to second end portion 224 to maintain upper bracket 232 in contacting relation with a top surface of support stringer 110 .
- a lower bracket 236 is positioned at a bottom surface of support stringer 110 and a nut 238 is threadedly connected to threaded rod 221 to maintain lower bracket 236 in contacting relation with the bottom surface of support stringer 110 .
- Nut 234 and nut 238 are rotatable with respect to each other about threaded rod 221 to tighten or secure suspension member 220 to support stringer 110 .
- nut 238 can be positioned along a length of threaded rod 221 to position first framing member 214 at a desired position or distance with respect to the structure 100 .
- Second suspension member 220 ′ can be the same or similar to first suspension member 220 .
- second suspension member 220 ′ comprises a chain or cable 240 having a first connection, such as hook 242 , positioned at a first end portion 244 and a second connection, such as hook 246 , positioned at a second end portion 248 , as shown in FIG. 15.
- Hooks 242 and/or 246 allow the framing members to be suspended from the support stringers quickly and easily.
- each hook 242 , 246 comprises a pivot arm to allow the hook to “snap” connect with a corresponding loop fastener.
- Cable 240 may have any suitable length to suspend second framing member 216 at a desired position or distance with respect to support stringer 110 .
- the length of cable 240 is adjustable.
- a loop fastener 250 is secured to second framing member 216 .
- loop fastener 250 may be threadedly connected to a bolt 252 that is secured to second framing member 216 .
- a bracket 254 is in contacting relation with a first edge surface 255 of second framing member 216 .
- bracket 254 and a head portion 253 of bolt 252 is positioned within a cavity 257 formed by second framing member 216 .
- Loop fastener 250 and bolt 252 are rotatable with respect to each other to tighten or secure suspension member 220 ′ to second framing member 216 .
- a similar mechanical connection can be used to secure second end portion 248 to the structure 100 .
- an upper bracket 256 is in contacting relation with a top surface of support stringer 110 .
- a lower bracket 258 is positioned at a bottom surface of support stringer 110 and a hoop fastener 260 is threadedly connected to a bolt 262 to maintain lower bracket 258 in contacting relation with the bottom surface of support stringer 110 .
- Hoop fastener 260 and bolt 262 are rotatable with respect to each other to tighten or secure suspension member 220 ′ to support surface 110 .
- At least one channel trolley 270 is mounted with respect to platform module 212 .
- Channel trolley 270 can be connected to platform module 212 using any suitable connection, such as a weld or a suitable mechanical arrangement.
- at least one channel trolley 270 is connected to each of first framing member 214 and second framing member 216 , as shown for example in FIG. 15.
- Rotatable wheels 272 are positionable within a channel formed by a framing member to allow relative movement of a framing member with respect to an adjacent or operatively connected framing member.
- the modular platform system of the present invention provides quick deployment and installation of the system, thereby decreasing costs associated with project set-up and labor charges. Further, the containment means can be used where government regulations and restrictions must be satisfied, such as when removing lead-based paint from the structure.
- the modular platform system of the present invention can be used in general construction projects for demolition and/or inspection by inspectors or foreman, for example. Additionally, the modular platform system of the present invention can be used within an industrial or manufacturing facility.
- the modular platform system can be temporarily or permanently suspended from ceiling trusses to permit work to be performed above equipment and machinery without the need to shut down the equipment or delay the manufacturing processes, for example.
- this invention has been described as a modular platform system suspendable with respect to a support structure of a bridge construction, this invention is also suitable for other purposes, such as a suspended building ceiling, capable of supporting dynamic loads, such as people, and/or static loads, such as cables and wires.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
A platform module suspendable from a structure for supporting a dynamic load with respect to a support surface of the structure including a first framing member suspended with respect to the structure. A second framing member is suspended with respect to the structure and mounted with respect to the first framing member. A deck panel is positioned between the first framing member and the second framing member and suspended with respect to the structure. At least one adjustable suspension member is attached to each of the first framing member and the second framing member, and removably mounted with respect to the structure. Also disclosed is a modular platform system including a plurality of platform modules and a method for suspending a modular platform system with respect to the structure.
Description
- This application claims the benefit of U.S. Provisional Application No.60/400,827, filed 02 Aug. 2002.
- 1. Field of the Invention
- This invention relates to a modular platform system and a method of installing the modular platform system, wherein a plurality of operatively connected platform modules can be quickly and efficiently suspended with respect to a working location. More specifically, this invention relates to a modular platform system and method of installing the system wherein a plurality of platform modules can be installed and suspended with respect to a bottom or underside support surface of a bridge structure or other structure, for example.
- 2. Description of Prior Art
- Many deck structures are supported by an angle bracket having one leg structurally welded to an edge portion or an underside of a horizontal flange of a steel stringer, a steel plate, a girder, or another suitable steel primary structural member. Deck pans or other suitable deck panels of these deck structures are individually positioned between opposing angle brackets which are welded into place in the field. Each deck pan is positioned upon horizontal flanges of such field-installed opposing angle brackets. The deck pan is then secured with a sheet metal screw or a weld, also at the job site.
- With these deck framing systems, each vertical height adjustment to vary the elevation of the top of the deck pan requires labor-intensive field adjustments, of ten accomplished with welded connections. Further, many of these deck framing systems have welded connections or metal fasteners exposed beneath the deck structure.
- Thus, a problem associated with deck framing systems and methods therefor that precede the present invention is that they do not facilitate quick installation of the deck panels by permitting pre-placement of the securement means prior to installation of the deck panels, and movement of the securement means as the deck panels are installed.
- Still a further problem associated with deck framing systems and methods therefor that precede the present invention is that they do not facilitate efficient transportation to a job site in a manner that saves shipping space and thereby saves time, energy and money.
- Yet an additional problem associated with deck framing systems and methods therefor that precede the present invention is that they do not enable efficient assembly and erection of the deck framing system.
- Still a further problem associated with deck framing systems and methods therefor that precede the present invention is that the vertical height of each deck panel structure cannot be quickly adjusted using simple mechanical elements to accommodate the varying dimensional characteristics of the prefabricated deck panel structures.
- For the foregoing reasons, there has been defined a long felt and unsolved need for a modular platform system and method that can be quickly and easily suspended and removed from a structure in order to maintain and/or repair the structure, inexpensive to manufacture and adjustable to accommodate a variety of prefabricated parts of differing sizes and dimensions.
- It is one object of this invention to provide a platform module for use in a modular platform system that can be suspended with respect to a structure, for example an underside support surface of a bridge construction.
- It is another object of this invention to provide a modular platform system that is easily suspended from a structure in order to access areas of the structure for maintenance and/or repair.
- It is another object of this invention to provide a modular platform system that can be easily removed from the structure after scheduled maintenance and/or repair.
- It is another object of this invention to provide a modular platform system having containment means for containing debris, including hazardous materials, such as lead paint, removed from a structure during maintenance and/or repair procedures.
- The above and other objects of this invention are accomplished with a platform module suspendable from a structure. The platform module includes a first framing member suspended with respect to the structure and a second framing member suspended with respect to the structure and mounted with respect to the first framing member. At least one deck panel is positioned between the first framing member and the second framing member and suspended with respect to the structure to provide a working surface for the contractors working on the structure. The platform modules are removably mounted or suspended with respect to the structure using adjustable suspension members connected or attached to the first framing member and the second framing member.
- The modular platform system includes a second platform module that is movably connected to the first platform module so that it is movable between a first position operatively connected to the first platform module and a second or extended position wherein the second platform module is linearly aligned with the first platform module and suspended with respect to the structure. For example, at least one and preferably a plurality of channel trolleys are mounted to each framing member of the first platform module. The channel trolleys include rotatable wheels that can be positioned within a channel formed by the corresponding framing member of the second platform module to allow the second platform module to move with respect to the first platform module suspended from the structure.
- The second platform module can be the same or similar to the first platform module, or different. Preferably, the second platform module includes a first framing member operatively connected to the first platform module first framing member and a second framing member operatively connected to the first platform module second framing member. A deck panel is positioned between the first framing member and the second framing member. The second platform module can be removably mounted or suspended with respect to the structure using adjustable suspension members attached to each framing member, in the second position. In the second position, the first platform module and the second platform module can be connected or secured in linear alignment using any suitable mechanical connection known to those having ordinary skill in the art. The term “linear alignment” as used throughout this specification refers to alignment of abutting framing members generally parallel in a direction along a width of the structure so that the upper surfaces of adjacent platform modules are flush.
- The deck panel may be any suitable material depending upon the intended use for the platform module. For example, the deck panel may be made of wood panels or wood composite materials, concrete, metal, fiberglass or other suitable insulating materials, composites and combinations thereof. Further, the deck panel may provide a barrier to vapor, heat, and/or solvents, for example. The deck panel may have any suitable size to span between the first framing member and the second framing member along a length of the framing members.
- The modular platform system can be easily installed to suspend from a structure, such as a support structure of a bridge construction. The suspended modular platform system of the present invention preferably comprises a plurality of operatively connected platform modules stacked or otherwise configured in a compact or efficient manner. Alternatively, independent platform modules may be connected together to form the suspended modular platform system. The platform modules can be raised from a ground surface or can be lowered from a surface of the bridge structure to position the suspended modular platform system with respect to the underside support surface of the bridge construction.
- The modular platform system can be hoisted using a crane or other suitable machinery and suspended over an edge portion of the bridge. The modular platform system is positioned with respect to the underside support surface of the bridge structure and the first platform module is secured in position with respect to the support surface using at least one support member.
- In one preferred embodiment of this invention, the first and second framing members are suspended from the support surface of the structure. The framing members can be securely connected to the stringers of the bridge using suitable beam clamps, for example, and run or extend perpendicular to the stringers, i.e. towards the centerline of the bridge. A preferred beam clamp is available from Multuloc Corp. located in Park Ridge, Ill., U.S.A. under the trade name Tuloc beam clamp. Preferably, the second framing members are suspended from the support surface and run or extend parallel with the first framing members. In certain embodiments of this invention wherein the structure and/or the support surface has a general arcuate or non-linear shape, the first and second framing members may not run or extend in a parallel direction. Rather, in such an embodiment, the framing members may converge or diverge with respect to each other as the framing members approach the centerline of the bridge.
- The first platform module is suspended with respect to the structure. A second platform module is extended from a first position operatively connected to the first platform module to a second position linearly aligned with the first platform module and suspended with respect to the structure. The second platform module can be connected to the first platform module in the second position using any suitable mechanical connection. Each of the platform modules are suspended with respect to the structure using at least one adjustable suspension member attached to the first framing member and at least one adjustable suspension member attached to the second framing member. Preferably, each suspension member is removably mounted with respect to a support surface of the structure, such as a support beam or stringer.
- In one preferred embodiment of this invention, a second modular platform system can be constructed laterally adjacent to the first modular platform system and suspended with respect to the structure. The second modular platform system can be connected to the first modular platform system.
- Additionally, where the structure and/or the support surface slopes in a lateral direction generally perpendicular to the centerline of the bridge, the vertical distance of adjacent panel structures with respect to the support surface may be adjusted to form a level panel structure surface. Alternatively, the adjacent panel structures may form steps or a “stepped” panel structure surface. For example, the framing members may be adjustably connected to the support surface using threaded rods and/or turn buckles.
- After the repair and/or repainting project is completed, the modular platform system is easily removed from the structure and can be reused. The extended platform modules can be retracted from the second position to the first position after the suspension members are disconnected from the support stringers. The retracted modular platform system can then be hoisted up to the upper surface of the structure using a crane or other suitable machinery and easily loaded onto a truck for removal from the work location. Any number of modular platform systems can be used to form a suitable platform, depending upon the size of the job.
- The above-mentioned and other features and objects of this invention will be better understood from the following detailed description when taken in view of the drawings wherein:
- FIG. 1A is a side view of a modular platform system comprising a platform module suspended with respect to a structure, according to one preferred embodiment of this invention;
- FIG. 1B is a side view of a modular platform system comprising a platform module suspended with respect to a structure, according to one preferred embodiment of this invention;
- FIG. 2 is a side view of a platform module removably connected with respect to a structure, according to one preferred embodiment of this invention;
- FIG. 3A is a side view of a platform module removably connected with respect to a structure, according to one preferred embodiment of this invention;
- FIG. 3B is a front view of a platform module removably connected with respect to a structure, according to one preferred embodiment of this invention;
- FIG. 3C is a front view of a platform module removably connected with respect to a structure, according to one preferred embodiment of this invention;
- FIG. 4 is a perspective view of a channel trolley, according to one preferred embodiment of this invention;
- FIG. 5 is a perspective view of a channel trolley, according to one preferred embodiment of this invention;
- FIG. 6 is a front view of a modular platform system comprising a plurality of operatively connected platform modules, according to one preferred embodiment of this invention;
- FIG. 7 is a side view of a modular platform system comprising a plurality of operatively connected platform modules in a first position and a first platform module removably suspended from adjacent stringers of the structure, according to one preferred embodiment of this invention;
- FIG. 8 is a side view of a modular platform system comprising a plurality of platform modules each in a second or extended position, according to one preferred embodiment of this invention;
- FIG. 9 is a front view of a platform module connected to adjacent platform modules and suspended with respect to a structure, according to one preferred embodiment of this invention;
- FIG. 10 is a front view of a platform module connected in a stepped fashion to adjacent platform modules and suspended with respect to an angled or sloped bottom support surface of a structure, according to one preferred embodiment of this invention;
- FIG. 11 is a perspective view of a platform module, according to one preferred embodiment of this invention;
- FIG. 12 is a perspective view of a platform module, according to one preferred embodiment of this invention;
- FIG. 13 is a perspective view of a modular platform system having a guard rail system, according to one preferred embodiment of this invention;
- FIG. 14 is a front view of a guard rail system post secured within a framing member, according to one preferred embodiment of this invention; and
- FIG. 15 is a front view of a modular platform system comprising a first platform module operatively connected to a second platform module, according to one preferred embodiment of this invention.
- The
modular platform system 10 of the present invention can be suspended with respect to a structure to support a dynamic and/or static load with respect to an underside surface of the structure. For example, the structure may comprise a bridge construction having a plurality of support beams or stringers extending along a length of the bridge to form support surfaces. In order to repair and/or paint the bridge, particularly an underside or bottom support surface of the bridge,modular platform system 10 can be installed to suspend from the underside of the bridge to allow access to desired areas of the structure. Such repair may include slab demolition, sand or shot blasting the supporting steel and painting the steel structure. Additionally,modular platform system 10 can be adapted to contain debris, such as concrete pieces, removed from the bridge to prevent the debris from falling to the ground or into the water. In one preferred embodiment of this invention,modular platform system 10 includes a containment means for containing environmentally hazardous or toxic material, such as lead-based paint, after the hazardous or toxic material has been removed from the structure. The containment means prevents the environmentally hazardous or toxic material from entering into the atmosphere.Modular platform system 10 can be constructed and/or installed from the ground, where the structure spans a street or highway, or can be constructed and/or installed from the structure itself, where the structure spans a body of water, for example. -
Modular platform system 10 can span any suitable distance, for example about 10 feet to at least about 100 feet, in order to allow access to the entire underside of the bridge structure or other structure. Further,modular platform system 10 may extend past the edge portion of the structure for easy access to materials and/or a side portion of the structure. It is apparent to those skilled in the art that the modular platform system of the present invention can be adapted to span any desired distance with respect to the structure. - In one preferred embodiment of this invention,
modular platform system 10 comprises a plurality ofplatform modules 12. Eachplatform module 12 is suspendable with respect to astructure 100, such as a bridge structure. For example, eachplatform module 12 may be mounted or secured to at least one support surface, such as a support beam or stringer positioned on an underside or bottom surface of the bridge structure. The support stringers are typically positioned generally parallel to a longitudinal centerline of the bridge structure along a length of the bridge. - Referring to FIGS.1A-3C,
platform module 12 comprises a first framingmember 14 suspended with respect to the structure. For example, first framingmember 14 may be suspended to extend or span between adjacent support stringers. Preferably, a second framingmember 16, the same or similar to first framingmember 14, is suspended with respect to the structure and mounted with respect to first framingmember 14. For example, second framingmember 16 can be suspended to extend or span between the adjacent support stringers and extend or run generally parallel to first framingmember 14. It should be apparent to those skilled in the art and guided by the teachings herein provided that, depending upon whether the bridge section is straight or curved, first framingmember 14 may or may not be parallel to second framingmember 16. Further, in order to compensate for curvature in the bridge structure, adjacentmodular platform systems 10 may be positioned in a skewed position, a fanned position or a straight position with respect to each other. - As shown for example in FIGS. 3B and 3C, at least one
deck panel 18 is positioned between first framingmember 14 and second framingmember 16 and suspended with respect to thestructure 100.Deck panel 18 may comprise any suitable material having sufficient strength to support contractors, materials, tools and debris. Suitable deck panel materials include metal sheets such as shown in FIG. 11, wood, concrete, composite materials including insulating materials such as shown in FIG. 12, and combinations thereof, depending upon the overall size and intended use ofmodular platform system 10, for example. Further,deck panel 18 may have any suitable length, width and/or thickness. In one preferred embodiment of this invention,deck panel 18 comprises a suitable material to provide a barrier or seal, such as a vapor barrier, an insulating barrier, a heat seal, or a solvent seal.Adjacent decl panels 18 positioned between first framingmember 14 and second framingmember 16 may be flush or may overlap with respect toadjacent deck panels 18. - In one preferred embodiment of this invention, at least one
suspension member 20 is used to suspend each of first framingmember 14 and second framingmember 16 with respect to thestructure 100. Preferably, but not necessarily, a length ofsuspension member 20 is adjustable. Referring to FIG. 1A, at least onesuspension member 20 is connected or attached between first framingmember 14 and thestructure 100. For example,suspension member 20 comprises a clamp or other suitable mechanical connection at a first end portion ofsuspension member 20 to removably mount first framingmember 14 to asupport stringer 110 of thestructure 100. Similarly, at least onesuspension member 20 is connected or attached to second framingmember 16 and removably mounted with respect to the structure. -
Suspension member 20 preferably comprises a chain orcable 40 having a first connection, such ashook 42, positioned at afirst end portion 44 and a second connection, such ashook 46, positioned at asecond end portion 48, as shown in FIG. 1A.Hooks 42 and/or 46 allow the framing members to be suspended from the support stringers quickly and easily. Preferably, eachhook Cable 40 may have any suitable length to suspend first framingmember 14 and/or second framingmember 16 at a desired position or distance with respect to supportstringer 110. Preferably, the length ofcable 40 is adjustable. - At least one
loop fastener 50 is secured to first framingmember 14. For example,loop fastener 50 may be threadedly connected to abolt 52 that is secured to first framingmember 14. As shown in FIG. 1A for example, abracket 54 is in contacting relation with an inner surface of first framingmember 14. Preferably, but not necessarily,bracket 54 and at least a portion ofbolt 52 are positioned within acavity 55 formed by first framingmember 14.Loop fastener 50 andbolt 52 are rotatable with respect to each other to tighten orsecure fastener 50 to first framingmember 14. - In one preferred embodiment of this invention, a
beam clamp 80 is positioned and secured to a support beam orstringer 110, as shown in FIG. 1A. Beam clamp 80 comprises abolt 84 connected to a bracket ortransport trolley 81. A suitable transport trolley is available from Multuloc Corp. located in Park Ridge, Ill., U.S.A. under the trademark TULOC.Bolt 84 can be connected or mounted to transporttrolley 81 using a weld or a suitable mechanical connection. As shown in FIG. 1A,transport trolley 81 preferably runs generally parallel with a side edge of thestringer 110. Abottom bracket 85 is in contacting relation with a bottom surface of thestringer 110. Preferably,bottom bracket 85 is threadedly connected to bolt 84 to maintainbottom bracket 85 in contacting relation withsupport stringer 110. Atop bracket 86 is positioned aboutbolt 84 and maintained in contacting relation withsupport stringer 110 by anut arrangement 87. Aset screw 91 is threadedly connected totop bracket 86 and rotatable with respect totop bracket 86 to securebeam clamp 80 with respect to the support stringer.Nut arrangement 87 comprises abeveled washer 90 which allowsbeam clamp 80 to be secured to a support beam or stringer having any suitable thickness, regardless of whether the stringer has a flat contacting surface or a sloped contacting surface. - For example, some old beams and channels have an interior flange surface with a 1 to 6 slope. Beam clamp80 compensates for the sloped top flange surface by providing
beveled washer 90 and a tolerance betweenbolt 84 and an aperture formed intop bracket 86 within whichbolt 84 is positioned. For example, in one preferred embodiment of this invention,bolt 84 has a ½ inch diameter and the aperture formed in thetop bracket 86 has a {fraction (9/16)} inch diameter. Thus,top bracket 86 has a 1 to 6 slope with respect to bolt 84 to maintain a contacting relation with the sloped flange surface of the stringer. Beam clamp 80 maintains maximum torque, and coupled withset screw 91, resists lateral forces to provide full contact at the beam edge and point contact bearing through setscrew 91 while adjusting for any tolerance variances. - As shown in FIGS.1A-2, a wire or
cable 88 can be connected betweensuspension members 20 atbeam clamp 80 positioned with respect to thesupport stringer 110 to maintainbeam clamp 80 securely connected with respect to thesupport stringer 110. - At least one
channel trolley 70 is mounted with respect to transporttrolley 81. Preferably,channel trolley 70 is positioned within achannel 83 formed bytransport trolley 81. Referring further to FIGS. 4 and 5,channel trolley 70 comprises at least onerotatable wheel 72.Rotatable wheels 72 are positionable withinchannel 83 to allow relative movement ofplatform module 12 with respect to thestringer 110.Suspension member 20 preferably comprises a second connection, such ashook 46, positioned at asecond end portion 48, as shown in FIG. 1A.Hook 46 allows the framing members to be suspended from the support stringers quickly and easily. Preferably, eachhook 46 comprises a pivot arm to allow the hook to “snap” connect with an aperture formed inchannel trolley 70. - At least one
loop fastener 50 is secured to first framingmember 14. For example,loop fastener 50 may be threadedly connected to abolt 52 that is secured to first framingmember 14. As shown in FIG. 1A for example, abracket 54 is in contacting relation with an inner surface of first framingmember 14. Preferably, but not necessarily,bracket 54 and at least a portion ofbolt 52 are positioned within acavity 55 formed by first framingmember 14.Loop fastener 50 andbolt 52 are rotatable with respect to each other to tighten orsecure fastener 50 to first framingmember 14. - In one preferred embodiment as shown in FIG. 1B, a
fastener 50 can be connected directly to bolt 84. Preferably, but not necessarily,fastener 50 contactsbottom bracket 85 to maintainbeam clamp 80 securely fastened to thestringer 110. In this embodiment,hook 46 is easily connected tofastener 50 to suspendplatform module 12 with respect to the structure. Alternatively,cable 40 can be positioned betweenbottom bracket 85 and the stringer so thathook 42 andhook 46 each are connected toloop fastener 50, connected to framingmember -
Beam clamp 80 allows a containment or safety system, such as a net or fence suspended with respect to the structure and/or a load bearing system, such asmodular platform system 10, for supporting a load, for example contractors working on the structure, to be connected with respect to the structure. - In one preferred embodiment of this invention, each of first framing
member 14 and second framingmember 16 is removably suspended or mounted to the structure usingbeam clamp 80, as shown in FIGS. 3A-3C. Beam clamp 80 comprises astrut 82. At least onesuspension member 20 is mounted or connected with respect to strut 82 which extends along a width ofsupport stringer 110. For example as shown in FIG. 3A, asuspension member 20 is connected atfirst end portion 44 having afirst hook 42 to afirst loop fastener 50 mounted to first framingmember 14 and at asecond end portion 48 having asecond hook 46 to asecond loop fastener 50 mounted to first framingmember 14. In this embodiment, at least onesuspension member 20 runs through at least a portion of a channel formed bystrut 82 and around at least onepin connection 93 positioned within anaperture 92 formed instrut 82. Alternatively, twosuspension members 20 may be independently connected to strut 82 usingpin connections 93 positioned within a desiredaperture 92.Bolt 84 is connected to strut 82, for example, using a weld or a suitable mechanical connection.Bottom bracket 85 andtop bracket 86 are positioned aboutbolt 84 and maintained in contacting relation withsupport stringer 110 bynut arrangement 87. Preferably,bottom bracket 85 is threadedly connected to bolt 84 to maintainbottom bracket 85 in contacting relation withsupport stringer 110. Setscrew 91 is threadedly connected totop bracket 86 and rotatable with respect totop bracket 86 to securebeam clamp 80 with respect to the support stringer.Beveled washer 90 allowsbeam clamp 80 to be secured to a support beam or stringer having any suitable thickness, regardless of whether the stringer has a flat contacting surface or a sloped contacting surface. - In one preferred embodiment of this invention, strut82 forms a plurality of
apertures 92 for mounting eachsuspension member 20 with respect to strut 82. A distance between the framing member and the support stringer is adjustable by selecting a desired orappropriate aperture 92 within whichpin connection 93 can be secured to adjust a length ofsuspension member 20 positioned betweenstrut 82 and framingmembers modular platform system 10. As shown in FIG. 3B, two ormore suspension members 20 can be connected with respect to strut. 82 to allow framingmember adjacent platform modules 12 to be suspended with respect tostructure 100. - In one embodiment of this invention as shown in FIG. 3C, a
strut 95 can be connected to adjacent beam clamps 80.Strut 95 forms a channel within which at least onechannel trolley 70 can be movably positioned. At least onesuspension member 20 can be connected to channeltrolley 70 to suspendplatform module 12 with respect tostructure 100.Channel trolley 70 comprisesrotatable wheels 72 which can be movably positioned within the strut channel to allow suspendedplatform module 12 to move with respect to the structure. - Referring to FIGS.6-8, in one preferred embodiment of this invention,
modular platform system 10 comprises a plurality of operatively connectedplatform modules 12 which are suspended or supported with respect to the structure. Eachplatform module 12 comprises a first framingmember 14, a second framingmember 16 and at least onedeck panel 18 positioned between first framingmember 14 and second framingmember 16 and suspendable with respect tostructure 100, as shown for example in FIG. 6. - A
second platform module 12′ is movable with respect to thefirst platform module 12 between a first position operatively connected tofirst platform module 12 and a second or extended position linearly aligned withfirst platform module 12. Preferably,second platform module 12′ is the same or similar tofirst platform module 12.Second platform module 12′ comprises a first framingmember 14′ movably mounted to at least onechannel trolley 70 secured or mounted with respect to first platform module first framingmember 14 and a second platform module second framingmember 16′ movably mounted to at least onechannel trolley 70 secured or mounted with respect to first platform module second framingmember 14.Rotatable wheels 72 are positionable within achannel 75, 76 formed by the second platformmodule framing member 14′, 16′, respectively. - In the second position,
second platform module 12′ is removably suspended with respect to the structure from a support beam or stringer for example, and in linear alignment withplatform module 12, using at least onesuspension member 20 attached to first framingmember 14′ and at least onesuspension member 20 attached to second framingmember 16′. Further, a connecting bracket or other suitable mechanical connection can be used to connect first framingmember 14′ in linear alignment with first framingmember 14 and second framingmember 16′ in linear alignment with second framingmember 16. In the second position,deck panel 18′, positioned between first framingmember 14′ and second framingmember 16′, is suspended with respect to the structure. - Preferably, as shown in FIG. 7, first framing
member 14 and corresponding second framingmember 16 extend between thefirst support stringer 110 and asecond support stringer 110′ of the structure, generally parallel to thefirst support stringer 110. It is apparent to those skilled in the art and guided by the teachings herein provided, that each of first framingmember 14 and second framingmember 16 may have any suitable length, as required by the size of the structure and the system application. - A second plurality of operatively connected
platform modules 12 can be suspended or supported from the structure and positioned laterally adjacent the first plurality ofplatform modules 12, as shown in FIGS. 9 and 10, such that first framingmember 14 ofplatform module 12 contacts or approaches second framingmember 16 of the laterally adjacent platform modular 12. Laterallyadjacent platform modules 12 can be connected using a connecting bracket or other suitable mechanical connection. Additionally, aclosure element 98 can be “snap-fitted” into a space formed at a connection ofadjacent platform modules 12, as shown in FIG. 9.Closure element 98 contains debris, including hazardous materials such as lead-paint. Further, in one preferred embodiment of this invention, a panel, for example wood or acontainment tarp 99, such as shown in FIG. 10, is positioned across the laterallyadjacent platform modules 12 to maintain a tight seal between theplatform modules 12 to contain debris and/or environmentally hazardous materials, such as lead paint removed from the structure. As shown in FIG. 10,containment tarp 99 is preferably flexible to connect laterallyadjacent platform modules 12 that are not level, or stepped, as a result of the structure or its support stringers being angled or sloped. One suitable material forcontainment tarp 99 is a reinforced plastic material having a thickness of about 6 mils. It should be apparent to those having ordinary skill in the art and guided by the teachings herein that other materials are suitable forcontainment tarp 99. - In one preferred embodiment of this invention,
modular platform system 10 is installed on a structure, such as a highway or road bridge, having a plurality of support beams or stringers generally parallel the longitudinal centerline of the bridge along the length of the bridge.Modular platform system 10 is preferably, but not necessarily, installed laterally across the bridge, i.e. generally perpendicular to the length of the support beams or stringers.Modular platform system 10 including a plurality of operatively connectedplatform modules 12 is temporarily suspended with respect to the underside of the bridge, for example using a crane or other suitable machinery positioned on a top or road surface of the bridge. Withmodular platform system 10 positioned with respect to the underside of the structure, themodular platform system 10 is suspended with respect to at least one structure support beam or stringer. For example, theplatform module 12 is secured to the structure. First framingmember 14 is removably mounted to a first support beam or stringer usingsuspension member 20. Similarly, second framingmember 16 is removably mounted to the first support beam or stringer usingsuspension member 20. Preferably, each of first framingmember 14 and second framingmember 16 is suspended with respect to the structure usingadjustable suspension members 20 so that the distance betweenpanel 18 and the underside of the bridge can be adjusted according to the work scheduled on the bridge. -
Platform module 12′ is extended from the first position belowplatform module 12 to the second or extended position linearly aligned with platform modular 12.Platform module 12′ is suspended from the structure. First framingmember 14′ and second framingmember 16′ are removably mounted to the support beam or stringer usingsuspension member 20. Withplatform module 12′ in the second position and in linear alignment withplatform module 12,platform module 12′ can be connected or attached toplatform module 12 using a suitable mechanical connection. For example, first framingmember 14′ can be fastened or connected to first framingmember 14 and second framingmember 16′ can be fastened or connected to second framingmember 16 using a connecting bracket. - A second modular platform system, preferably the same or similar to the first modular platform system, is constructed with respect to the structure. For example, the second modular platform system can be suspended with respect to the structure laterally adjacent the first modular platform system comprising a plurality of operatively connected platform modules. The second modular platform system can be suspended with respect to the structure as the first modular platform system is suspended. Preferably, second modular platform system is connected to the first modular platform system using any suitable mechanical connections. For example, in order to provide for containment of debris removed from the structure, wood pieces and/or tarp pieces can be positioned at the abutting framing members to provide containment or seal spaces between adjacent framing members.
- In one preferred embodiment of this invention,
modular platform system 10 may be suspended fromsupport stringer 110, at a first vertical distance to preform one process, such as sandblasting, and then lowered or raised to a second vertical distance with respect to supportstringer 110 to perform another process, such as painting. For example, a threaded rod extension coupled to a coupler nut can be connected with respect to the structure. In one embodiment of this invention, the coupler nut can be rotated to allow a plate securing each structure to a beam flange to be rotated by a suitable rotational distance, for example about 180°, to allow the panel structure to be raised or lowered with respect to the beam flange in order to continue work on the structure, if desired. The coupler nut or other suitable mechanical connection can also prevent or limit damage to the threaded rod extension as a result of processes such as sandblasting and painting. It is apparent that suitable mechanical connections may be used to secure the structures directly or indirectly to the support surface. - In one embodiment of this invention, a
counter-balancing weight 101 such as shown in FIG. 7, for example a suitably-sized concrete block, can be positioned on one end portion ofmodular platform system 10 so that themodular platform system 10 is cantilevered over the edge portion of the bridge. Adjustments can be made, for example in increments of about 6 inches, with respect to balancingmodular platform system 10 by positioning the counter-balancing weight with respect to a length ofmodular platform system 10. Thus, one counter-balancing weight can handle a variety of loads by moving the weight along a length ofmodular platform system 10. - If
modular platform system 10 spans a hard surface, for example a road or highway, modular platform system can be suspended with respect to the structure from the surface below. For example, a rough terrain scissors lift or other suitable machine can move or liftmodular platform system 10 into position with respect to the structure andsuspension members 20 may be connected to beam clamps 80 properly positioned on the support stringers of the structure to suspendmodular platform system 10 with respect to the structure. - In one embodiment of this invention,
platform module 12 comprises an absorbing layer of plywood applied overdeck panels 18 to protectplatform module 12 so thatmodular platform system 10 is reusable. The plywood panels or sheets absorb the weight of concrete pieces dropping ontomodular platform system 10 during demolition, for example. Further, tight seals can be formed using the plywood to contain lead-base paint dust, for example, created during sand blasting or shot blasting procedures. Preferably, but not necessarily, the plywood sheets are attached tomodular platform system 10 by nailing the plywood and/or plywood clamping strips to wood, for example pieces of standard 2×4s, positioned within each framing member. Preferably, the pieces of wood are inserted into the rolled shape of the framing member. It is apparent to those skilled in the art that any suitable mechanical connection may be used to secure the plywood sheets to the platform panels. For example, the top piece of plywood may clamp a 4 foot standard width plywood piece in place. - Preferably, but not necessarily,
platform module 12 may further comprise at least oneadjustable strut spacer 97, such as shown in FIG. 11, having a first end portion connected with respect to first framingmember 14 and a second end portion connected with respect to second framingmember 16.Strut spacer 97 provides increased strength and rigidity to theplatform module 12, particularly whenplatform module 12 is subjected to large loads. - Referring to FIGS. 13 and 14, in one embodiment of this invention, a
guard rail system 120 suitable for adhering to government safety standards, such as O.S.H.A., is connected tomodular platform system 10.Guard rail system 120 preferably comprises a plurality ofposts 122 positioned within and secured to first framingmember 14 and/or second framingmember 16. A chain orcable 124 extends between theposts 122 to provide perimeter protection and prevent workers from falling from the side ofmodular platform system 10. As shown in FIG. 14,posts 122 are positioned within and secured to framingmember bolt 126 is threadedly connected to abottom portion 128 ofpost 122.Bolt 126 is rotatable with respect to a plate orbracket 130 positioned within the framing member to tighten andsecure post 122 with respect to the framing member. It should be apparent to those skilled in the art and guided by the teachings herein that other suitable mechanical connections may be used to secure eachpost 122 to the corresponding framingmember - In one preferred embodiment of this invention as shown in FIG. 15,
platform module 212 comprises afirst framing member 214 suspended with respect to the structure, and asecond framing member 216, the same or similar to first framingmember 214, suspended with respect to the structure and mounted with respect to first framingmember 214. At least one suspension member 220 is used to suspend each of first framingmember 214 and second framingmember 216 with respect to thestructure 100. Referring to FIG. 15, at least one suspension member 220 is connected or attached between first framingmember 214 and thestructure 100. Similarly, at least one suspension member 220′ is connected or attached tosecond framing member 216 and removably mounted with respect to the structure. In the figures, suspension member 220 and suspension member 220′ may be shown according to different embodiments of this invention. However, it should be apparent to those having ordinary skill in the art that suspension member 220 may be the same or similar to suspension member 220′. - Suspension member220 may comprise a threaded
rod 221 connected at afirst end portion 222 to one of first framingmember 214 and second framingmember 216, and at asecond end portion 224 to the structure. Alower bracket 225 is positioned at afirst edge surface 215 of first framingmember 214. Anut 226 is threadedly connected to an end portion of threadedrod 221 to maintainlower bracket 225 in contacting relation withfirst edge surface 215. Preferably, but not necessarily,nut 226 is positioned within a cavity 227 formed by first framingmember 214. Anupper bracket 229 is positioned at asecond edge surface 217 of first framingmember 214 and anut 230 is threadedly connected to threadedrod 221 to maintainupper bracket 229 in contacting relation withsecond edge surface 217.Nut 226 andnut 230 are rotatable with respect to each other about threadedrod 221 to tighten or secure suspension member 220 to first framingmember 214. Further,nut 226 can be positioned along a length of threadedrod 221 to position first framingmember 214 at a desired position or distance with respect to thestructure 100. - A similar mechanical connection can be used to secure
second end portion 224 to thestructure 100. For example, as shown in FIG. 15, anupper bracket 232 is positioned atsecond end portion 224. Anut 234 is threadedly connected tosecond end portion 224 to maintainupper bracket 232 in contacting relation with a top surface ofsupport stringer 110. Alower bracket 236 is positioned at a bottom surface ofsupport stringer 110 and anut 238 is threadedly connected to threadedrod 221 to maintainlower bracket 236 in contacting relation with the bottom surface ofsupport stringer 110.Nut 234 andnut 238 are rotatable with respect to each other about threadedrod 221 to tighten or secure suspension member 220 to supportstringer 110. Further,nut 238 can be positioned along a length of threadedrod 221 to position first framingmember 214 at a desired position or distance with respect to thestructure 100. - Second suspension member220′ can be the same or similar to first suspension member 220. Alternatively, second suspension member 220′ comprises a chain or
cable 240 having a first connection, such ashook 242, positioned at afirst end portion 244 and a second connection, such ashook 246, positioned at asecond end portion 248, as shown in FIG. 15.Hooks 242 and/or 246 allow the framing members to be suspended from the support stringers quickly and easily. Preferably, eachhook Cable 240 may have any suitable length to suspend second framingmember 216 at a desired position or distance with respect to supportstringer 110. Preferably, the length ofcable 240 is adjustable. A loop fastener 250 is secured tosecond framing member 216. For example, loop fastener 250 may be threadedly connected to abolt 252 that is secured tosecond framing member 216. As shown in FIG. 15 for example, abracket 254 is in contacting relation with afirst edge surface 255 of second framingmember 216. Preferably, but not necessarily,bracket 254 and ahead portion 253 ofbolt 252 is positioned within acavity 257 formed by second framingmember 216. Loop fastener 250 and bolt 252 are rotatable with respect to each other to tighten or secure suspension member 220′ tosecond framing member 216. - A similar mechanical connection can be used to secure
second end portion 248 to thestructure 100. For example, as shown in FIG. 15, anupper bracket 256 is in contacting relation with a top surface ofsupport stringer 110. Alower bracket 258 is positioned at a bottom surface ofsupport stringer 110 and ahoop fastener 260 is threadedly connected to abolt 262 to maintainlower bracket 258 in contacting relation with the bottom surface ofsupport stringer 110.Hoop fastener 260 and bolt 262 are rotatable with respect to each other to tighten or secure suspension member 220′ to supportsurface 110. - In one preferred embodiment of this invention, at least one
channel trolley 270 is mounted with respect toplatform module 212.Channel trolley 270 can be connected toplatform module 212 using any suitable connection, such as a weld or a suitable mechanical arrangement. Preferably, at least onechannel trolley 270 is connected to each of first framingmember 214 and second framingmember 216, as shown for example in FIG. 15.Rotatable wheels 272 are positionable within a channel formed by a framing member to allow relative movement of a framing member with respect to an adjacent or operatively connected framing member. - The modular platform system of the present invention provides quick deployment and installation of the system, thereby decreasing costs associated with project set-up and labor charges. Further, the containment means can be used where government regulations and restrictions must be satisfied, such as when removing lead-based paint from the structure. The modular platform system of the present invention can be used in general construction projects for demolition and/or inspection by inspectors or foreman, for example. Additionally, the modular platform system of the present invention can be used within an industrial or manufacturing facility. The modular platform system can be temporarily or permanently suspended from ceiling trusses to permit work to be performed above equipment and machinery without the need to shut down the equipment or delay the manufacturing processes, for example.
- While in the foregoing specification this invention has been described as a modular platform system suspendable with respect to a support structure of a bridge construction, this invention is also suitable for other purposes, such as a suspended building ceiling, capable of supporting dynamic loads, such as people, and/or static loads, such as cables and wires.
- While in the foregoing specification this invention has been described in relation to certain preferred embodiments thereof, and many details have been set forth for purpose of illustration, it will be apparent to those skilled in the art that the invention is susceptible to additional embodiments and that certain of the details described can be varied considerably without departing from the basic principles of the invention.
Claims (24)
1. A modular platform system suspendable with respect to an underside of a structure for supporting a dynamic load comprising:
a first platform module comprising a first framing member suspendable with respect to the structure; a second framing member suspendable with respect to the structure and mounted with respect to the first framing member; and a deck panel positioned between the first framing member and the second framing member and suspendable with respect to the structure;
a second platform module comprising a first framing member suspendable with respect to the structure; a second framing member suspendable with respect to the structure and mounted with respect to the first framing member; and a deck panel positioned between the first framing member and the second framing member and suspendable with respect to the structure; and
at least one channel trolley mounted with respect to the first platform module, wherein the second platform module movably connected to the at least one channel trolley and movable with respect to the first platform module between a first position operatively connected to the first platform module and a second position linearly aligned with the first platform module.
2. The platform module of claim 1 further comprising:
a plurality of suspension members connected with respect to the first platform module, at least one adjustable suspension member attached to each of the first framing member and the second framing member, and each suspension member removably mountable with respect to the structure; and
a plurality of suspension members connected with respect to the second platform module, at least one adjustable suspension member attached to each of the first framing member and the second framing member, and each suspension member removably mountable with respect to the structure with the second platform module in the second position.
3. The platform module of claim 1 wherein the second platform module first framing member is operatively connected to the first platform module first framing member, and at least one channel trolley is mounted to the first platform module first framing member and positioned within a channel formed by the second platform module first framing member; and the second platform module second framing member is operatively connected to the first platform module second framing member, and at least one channel trolley is mounted to the first platform module second framing member and positioned within a channel formed by the second platform module second framing member.
4. The platform module of claim 3 wherein the at least one channel trolley comprises at least one rotatable wheel positionable within the channel of one of the second platform module first framing member and the second platform module second framing member.
5. The platform module of claim 2 wherein the at least one adjustable suspension member comprises at least one of a cable, a chain, a rod, a hook, and a threaded rod.
6. The platform module of claim 1 wherein the first platform module and the second platform module are connected in the second position.
7. The platform module of claim 2 wherein the at least one adjustable suspension member attached to each of the first framing member and the second framing member is removably mounted to a support surface of the structure.
8. The platform module of claim 2 further comprising a strut connected between a first suspension member and a second suspension member and contacting a support surface of the structure.
9. A modular platform system suspendable from a structure for supporting a load with respect to an underside of the structure comprising a plurality of platform modules, each platform module comprising:
a first framing member suspended between a first support surface of the structure and a second support surface of the structure;
a second framing member suspended between the first support surface and the second support surface and mounted with respect to the first framing member;
a deck panel positioned between the first framing member and the second framing member and suspended with respect to the structure;
a plurality of suspension members each attached to the first framing member and removably mounted with respect to one of the first support surface and the second support surface; and
a plurality of suspension members each attached to the second framing member and removably mounted with respect to one of the first support surface and the second support surface.
10. The modular platform system of claim 9 wherein each platform module further comprises at least one adjustable strut spacer having a first end portion and a second end portion, the first end portion connected to the first framing member and the second end portion connected to the second framing member.
11. The modular platform system of claim 9 wherein the deck panel comprises at least one of a vapor barrier, a heat seal and a solvent seal.
12. A modular platform system supported from a structure comprising:
a plurality of operatively connected platform modules, each platform module comprising a first framing member, a second framing member and at least one deck panel positioned between the first framing member and the second framing member and suspended with respect to the structure;
wherein a second platform module of the plurality of platform modules is movable with respect to a first platform module of the plurality of platform modules between a first position operatively connected to the first platform module and a second position linearly aligned with the first platform module.
13. The modular platform system of claim 12 further comprising a third platform module of the plurality of platform modules movable with respect to the second platform module of the plurality of platform modules between a first position operatively connected to the second platform module and a second position linearly aligned with the second platform module.
14. The modular platform system of claim 12 wherein the second platform module first framing member is movably mounted to at least one channel trolley secured with respect to the first platform module first framing member and the second platform module second framing member is movably mounted to at least one channel trolley secured with respect to the first platform module second framing member.
15. The modular platform system of claim 14 wherein the at least one channel trolley comprises at least one rotatable wheel, the at least one rotatable wheel positionable within a channel formed by the corresponding second platform module framing member.
16. The modular platform system of claim 12 wherein the first platform module is suspended with respect to the structure using at least one suspension member attached to the first framing member and at least one suspension member attached to the second framing member, each suspension member removably mounted with respect to the support surface.
17. The modular platform system of claim 12 wherein a length of each suspension member is adjustable.
18. The modular platform system of claim 12 wherein the second platform module is suspended with respect to the structure in the second position using at least one suspension member attached to the first framing member and at least one suspension member attached to the second framing member, each suspension member removably mounted with respect to the structure.
19. A method for installing a modular platform system supported from a structure for supporting a dynamic load with respect to a support surface of the structure comprising the steps of:
constructing the modular platform system comprising a plurality of operatively connected platform modules, each platform module comprising a first framing member, a second framing member, and at least one deck panel positioned between the first framing member and the second framing member;
suspending a platform module of the plurality of platform modules with respect to the structure;
extending one or more additional platform modules from a first position operatively connected to an adjacent platform module to a second position linearly aligned with the adjacent platform module; and
suspending the additional platform modules with respect to the structure.
20. The method of claim 19 wherein each of the plurality of platform modules is suspended with respect to the structure using at least one adjustable suspension member attached to the first framing member and at least one adjustable suspension member attached to the second framing member.
21. The method of claim 20 wherein each of the adjustable suspension members is removably mounted with respect to a support surface of the structure.
22. The method of claim 19 further comprising connecting the first platform module to the second platform module in the second position.
23. The method of claim 19 further comprising the steps of:
constructing a second modular platform system laterally adjacent the first modular platform system comprising a plurality of operatively connected platform modules;
suspending a first platform module of the second modular platform system with respect to the structure;
extending a second platform module from a first position operatively connected to the first platform module to a second position linearly aligned with the first platform module; and
suspending the second platform module with respect to the structure.
24. The method of claim 23 further comprising connecting the second modular platform system to the first modular platform system.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US10/632,889 US20040020138A1 (en) | 2002-08-02 | 2003-08-01 | Modular platform system |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US40082702P | 2002-08-02 | 2002-08-02 | |
US10/632,889 US20040020138A1 (en) | 2002-08-02 | 2003-08-01 | Modular platform system |
Publications (1)
Publication Number | Publication Date |
---|---|
US20040020138A1 true US20040020138A1 (en) | 2004-02-05 |
Family
ID=31191409
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US10/632,889 Abandoned US20040020138A1 (en) | 2002-08-02 | 2003-08-01 | Modular platform system |
Country Status (1)
Country | Link |
---|---|
US (1) | US20040020138A1 (en) |
Cited By (29)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050144892A1 (en) * | 2003-10-28 | 2005-07-07 | Strickland Michael R. | Cold-formed steel joists |
US20050217936A1 (en) * | 2004-03-31 | 2005-10-06 | Paul Jolicoeur | Articulating work platform support system, work platform system, and methods of use thereof |
US20060065165A1 (en) * | 2004-09-25 | 2006-03-30 | Michael Baez | Overhead storage system |
US20060065164A1 (en) * | 2004-09-25 | 2006-03-30 | Michael Baez | Overhead storage system |
US7228669B1 (en) * | 2005-06-13 | 2007-06-12 | Yaraschefski Steven M | Suspended table assembly |
US20070283992A1 (en) * | 2006-06-10 | 2007-12-13 | Timothy Joseph Hennessy | Embrace-Air "TM" situates air conditioner and method for use with tent |
CN100425771C (en) * | 2006-04-29 | 2008-10-15 | 四川省交通厅公路规划勘察设计研究院 | Longitudinal limiting device for half-through and through type arch bridge short suspension arm |
CN102979036A (en) * | 2012-12-25 | 2013-03-20 | 上海普英特高层设备有限公司 | Bridge inspection vehicle |
US20130284078A1 (en) * | 2012-04-25 | 2013-10-31 | Domenick Francis De Rose | Suspension of a storage framework from a beam |
US20130341125A1 (en) * | 2011-03-08 | 2013-12-26 | Ideas - Creative Design Ltd. | Suspended scaffolding system |
GB2511847A (en) * | 2013-03-15 | 2014-09-17 | Apollo Cradles Ltd | Suspended platform system |
US20150041252A1 (en) * | 2013-08-08 | 2015-02-12 | Safway Services, Llc | Access structure integration assembly and integrated access systems and methods of using the same |
US20150068841A1 (en) * | 2013-09-10 | 2015-03-12 | 9020-4983 Quebec, Inc. | Vertical Support Member for a Suspended Scaffold Assembly, Kit for Mounting a Suspended Scaffold Assembly, Suspended Scaffold Assembly and Method for Mounting the Same |
US9103081B1 (en) | 2013-08-23 | 2015-08-11 | Platform Easy, L.L.C. | Below main cable work platform support |
US20150361679A1 (en) * | 2014-06-17 | 2015-12-17 | Jereme Kent | Suspended Deck Systems, Kits, and Methods of Installing, Inspecting, and Repairing a Suspended Deck System |
JP2016079584A (en) * | 2014-10-10 | 2016-05-16 | 株式会社杉孝 | Chain hanging metal fitting |
EP3049592A1 (en) * | 2013-09-23 | 2016-08-03 | Brand Energy Holdings B.V. | Suspended scaffolding and suspending device therefore |
US20160221621A1 (en) * | 2013-09-24 | 2016-08-04 | Torsten Hösker | Overhead Conveying Apparatus for Mounting on the Ceiling of an Assembly Plant |
CN105926917A (en) * | 2016-06-16 | 2016-09-07 | 中建七局建筑装饰工程有限公司 | Suspension platform for construction of steel structure cornice exterior facing, and construction method and detaching method of suspension platform |
US9784001B1 (en) * | 2011-05-03 | 2017-10-10 | Paul Kristen, Inc | Adjustable scaffolding suspension assembly |
US10119229B1 (en) | 2015-04-27 | 2018-11-06 | New Access Solutions, Inc. | Work platform rail system |
US10165853B2 (en) * | 2016-10-05 | 2019-01-01 | Reza Omidinejad | Foldable table attached to the ceiling |
CN109469302A (en) * | 2018-12-28 | 2019-03-15 | 中冶天工集团天津有限公司 | A kind of modular structure, method of construction and the method for dismounting of fast demountable modular platform |
US10738423B1 (en) * | 2018-11-26 | 2020-08-11 | Paul Kristen, Inc. | Platform and the hanging thereof from a bridge main cable |
IT201900013140A1 (en) * | 2019-07-29 | 2021-01-29 | Euroedile Srl | Monorail guide and mounting system for the creation of suspended worktops using said guide |
US11002026B1 (en) * | 2020-03-06 | 2021-05-11 | Paul Kristen, Inc. | Adjustable suspension assembly |
US11136967B2 (en) * | 2018-07-02 | 2021-10-05 | Inventus Holdings, Llc | Articulating joint for wind turbine |
US11421432B1 (en) * | 2017-12-29 | 2022-08-23 | Paul Kristen, Inc. | Shield |
IT202100015329A1 (en) * | 2021-06-11 | 2022-12-11 | Euroedile S R L | Mounting method for making suspended worktops |
Citations (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3953980A (en) * | 1975-01-13 | 1976-05-04 | Floyd William Bennett | Dock structure |
US4284010A (en) * | 1977-07-11 | 1981-08-18 | The Port Authority Of New York And New Jersey | Conveyance system |
US4671186A (en) * | 1985-06-04 | 1987-06-09 | Kunczynski Jan K | Positive drive assembly for automatic, rail-based transportation system |
US4702175A (en) * | 1984-03-16 | 1987-10-27 | Mannesmann Ag | Trolley with cable suspension |
US5074382A (en) * | 1987-06-03 | 1991-12-24 | Iev International Pty. Limited | Offshore access systems |
US5145032A (en) * | 1990-11-13 | 1992-09-08 | Figgie International, Inc. | Mason's scaffold |
US5299655A (en) * | 1993-05-20 | 1994-04-05 | Nicholas Margaritis | Workplace support and enclosure |
US5394956A (en) * | 1993-08-30 | 1995-03-07 | Hulse; James M. | Suspended tender box |
US5590602A (en) * | 1993-03-19 | 1997-01-07 | The Titan Corporation | Article carrier for conveyor system |
US5671824A (en) * | 1994-11-16 | 1997-09-30 | Keegan; E. Kevin | Vertically movable emergency egress system |
US5720067A (en) * | 1996-02-12 | 1998-02-24 | Multuloc International Systems Corporation | System and method for installing deck framing |
US5730248A (en) * | 1995-07-25 | 1998-03-24 | Paul Kristen, Inc. | Bridge platform |
US5896609A (en) * | 1997-11-21 | 1999-04-27 | Lin; Wei-Hwang | Safety method of construction a prestressed cable-stay bridge |
US6301735B1 (en) * | 1998-06-19 | 2001-10-16 | Freyssinet International Stup | Method and device for attaching a load-transmitting element to a cable, and suspension bridge comprising such devices |
US6317915B1 (en) * | 1998-10-30 | 2001-11-20 | Multuloc International Systems | Energy efficient deck framing system and method |
US6324989B1 (en) * | 1999-01-14 | 2001-12-04 | Three One Systems, Llc | Load bearing material handling system having pneumatic and electrical delivery capabilities |
US6386319B2 (en) * | 1995-07-25 | 2002-05-14 | Paul Kristen, Inc. | Scaffolding for bridges and other structures |
US6698544B2 (en) * | 2001-05-24 | 2004-03-02 | Michael P. Kurtgis | Fall protection lanyard apparatus |
US6817444B1 (en) * | 2002-09-10 | 2004-11-16 | George Shinas | Suspended work platform |
-
2003
- 2003-08-01 US US10/632,889 patent/US20040020138A1/en not_active Abandoned
Patent Citations (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3953980A (en) * | 1975-01-13 | 1976-05-04 | Floyd William Bennett | Dock structure |
US4284010A (en) * | 1977-07-11 | 1981-08-18 | The Port Authority Of New York And New Jersey | Conveyance system |
US4702175A (en) * | 1984-03-16 | 1987-10-27 | Mannesmann Ag | Trolley with cable suspension |
US4671186A (en) * | 1985-06-04 | 1987-06-09 | Kunczynski Jan K | Positive drive assembly for automatic, rail-based transportation system |
US5074382A (en) * | 1987-06-03 | 1991-12-24 | Iev International Pty. Limited | Offshore access systems |
US5145032A (en) * | 1990-11-13 | 1992-09-08 | Figgie International, Inc. | Mason's scaffold |
US5590602A (en) * | 1993-03-19 | 1997-01-07 | The Titan Corporation | Article carrier for conveyor system |
US5299655A (en) * | 1993-05-20 | 1994-04-05 | Nicholas Margaritis | Workplace support and enclosure |
US5394956A (en) * | 1993-08-30 | 1995-03-07 | Hulse; James M. | Suspended tender box |
US5671824A (en) * | 1994-11-16 | 1997-09-30 | Keegan; E. Kevin | Vertically movable emergency egress system |
US6302237B1 (en) * | 1995-07-25 | 2001-10-16 | Paul Kristen, Inc. | Bridge platform |
US5730248A (en) * | 1995-07-25 | 1998-03-24 | Paul Kristen, Inc. | Bridge platform |
US6386319B2 (en) * | 1995-07-25 | 2002-05-14 | Paul Kristen, Inc. | Scaffolding for bridges and other structures |
US5720067A (en) * | 1996-02-12 | 1998-02-24 | Multuloc International Systems Corporation | System and method for installing deck framing |
US5896609A (en) * | 1997-11-21 | 1999-04-27 | Lin; Wei-Hwang | Safety method of construction a prestressed cable-stay bridge |
US6301735B1 (en) * | 1998-06-19 | 2001-10-16 | Freyssinet International Stup | Method and device for attaching a load-transmitting element to a cable, and suspension bridge comprising such devices |
US6317915B1 (en) * | 1998-10-30 | 2001-11-20 | Multuloc International Systems | Energy efficient deck framing system and method |
US6324989B1 (en) * | 1999-01-14 | 2001-12-04 | Three One Systems, Llc | Load bearing material handling system having pneumatic and electrical delivery capabilities |
US6698544B2 (en) * | 2001-05-24 | 2004-03-02 | Michael P. Kurtgis | Fall protection lanyard apparatus |
US6817444B1 (en) * | 2002-09-10 | 2004-11-16 | George Shinas | Suspended work platform |
Cited By (53)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050144892A1 (en) * | 2003-10-28 | 2005-07-07 | Strickland Michael R. | Cold-formed steel joists |
US7779599B2 (en) | 2004-03-31 | 2010-08-24 | Safway Services, Llc | Articulating work platform support system, work platform system, and methods of use thereof |
US20050217936A1 (en) * | 2004-03-31 | 2005-10-06 | Paul Jolicoeur | Articulating work platform support system, work platform system, and methods of use thereof |
US9783939B2 (en) | 2004-03-31 | 2017-10-10 | Safway Services, Llc | Articulating work platform support system, work platform system, and methods of use thereof |
EP1753925A2 (en) * | 2004-03-31 | 2007-02-21 | Safway Services, Inc. | Articulating work platform support system, work platform system, and methods of use thereof |
US9103080B2 (en) | 2004-03-31 | 2015-08-11 | Safway Services, Llc | Articulating work platform support system, work platform system, and methods of use thereof |
US20110214945A1 (en) * | 2004-03-31 | 2011-09-08 | Safway Services, Llc | Articulating Work Platform Support System, Work Platform System, and Methods of Use Thereof |
US7941986B2 (en) | 2004-03-31 | 2011-05-17 | Safway Services, Llc | Articulating work platform support system, work platform system, and methods of use thereof |
US20110010913A1 (en) * | 2004-03-31 | 2011-01-20 | Safway Services, Llc | Articulating Work Platform Support System, Work Platform System, and Methods of Use Thereof |
US10563365B2 (en) | 2004-03-31 | 2020-02-18 | Brandsafway Services Llc | Articulating work platform support system, work platform system, and methods of use thereof |
EP1753925A4 (en) * | 2004-03-31 | 2010-07-07 | Safway Services Llc | ARTICULATED WORK PLATFORM SUPPORT SYSTEM, WORK PLATFORM SYSTEM, AND METHODS OF USING THE SAME |
US7543538B2 (en) | 2004-09-25 | 2009-06-09 | Michael Baez | Overhead storage system |
US7421957B2 (en) | 2004-09-25 | 2008-09-09 | Michael Baez | Overhead storage system |
US8117970B1 (en) | 2004-09-25 | 2012-02-21 | Michael Baez | Overhead storage system |
US20060065165A1 (en) * | 2004-09-25 | 2006-03-30 | Michael Baez | Overhead storage system |
US20060065164A1 (en) * | 2004-09-25 | 2006-03-30 | Michael Baez | Overhead storage system |
US7228669B1 (en) * | 2005-06-13 | 2007-06-12 | Yaraschefski Steven M | Suspended table assembly |
CN100425771C (en) * | 2006-04-29 | 2008-10-15 | 四川省交通厅公路规划勘察设计研究院 | Longitudinal limiting device for half-through and through type arch bridge short suspension arm |
US20070283992A1 (en) * | 2006-06-10 | 2007-12-13 | Timothy Joseph Hennessy | Embrace-Air "TM" situates air conditioner and method for use with tent |
US9556625B2 (en) * | 2011-03-08 | 2017-01-31 | Jerzy Meldner | Suspended scaffolding system |
US11028602B2 (en) | 2011-03-08 | 2021-06-08 | Jerzy J. MELDNER | Suspended scaffolding system |
US20130341125A1 (en) * | 2011-03-08 | 2013-12-26 | Ideas - Creative Design Ltd. | Suspended scaffolding system |
US10640993B2 (en) * | 2011-05-03 | 2020-05-05 | Paul Kristen, Inc. | Method for adjustably suspending a structure |
US9784001B1 (en) * | 2011-05-03 | 2017-10-10 | Paul Kristen, Inc | Adjustable scaffolding suspension assembly |
US20130284078A1 (en) * | 2012-04-25 | 2013-10-31 | Domenick Francis De Rose | Suspension of a storage framework from a beam |
CN102979036A (en) * | 2012-12-25 | 2013-03-20 | 上海普英特高层设备有限公司 | Bridge inspection vehicle |
GB2511847A (en) * | 2013-03-15 | 2014-09-17 | Apollo Cradles Ltd | Suspended platform system |
GB2511847B (en) * | 2013-03-15 | 2017-04-12 | Apollo Cradles Ltd | Suspended platform system |
US10704276B2 (en) | 2013-08-08 | 2020-07-07 | Brandsafway Services Llc | Access structure integration assembly and integrated access systems and methods of using the same |
US20150041252A1 (en) * | 2013-08-08 | 2015-02-12 | Safway Services, Llc | Access structure integration assembly and integrated access systems and methods of using the same |
US9611597B2 (en) * | 2013-08-08 | 2017-04-04 | Safway Services, Llc | Access structure integration assembly and integrated access systems and methods of using the same |
US9103081B1 (en) | 2013-08-23 | 2015-08-11 | Platform Easy, L.L.C. | Below main cable work platform support |
US9765537B2 (en) * | 2013-09-10 | 2017-09-19 | 9020-4983 Quebec Inc. | Vertical support member for a suspended scaffold assembly, kit for mounting a suspended scaffold assembly, suspended scaffold assembly and method for mounting the same |
US20150068841A1 (en) * | 2013-09-10 | 2015-03-12 | 9020-4983 Quebec, Inc. | Vertical Support Member for a Suspended Scaffold Assembly, Kit for Mounting a Suspended Scaffold Assembly, Suspended Scaffold Assembly and Method for Mounting the Same |
EP3049592A1 (en) * | 2013-09-23 | 2016-08-03 | Brand Energy Holdings B.V. | Suspended scaffolding and suspending device therefore |
EP3049592B1 (en) * | 2013-09-23 | 2023-03-15 | Brand Energy Holdings B.V. | Suspended scaffolding and suspending device therefore |
US20160221621A1 (en) * | 2013-09-24 | 2016-08-04 | Torsten Hösker | Overhead Conveying Apparatus for Mounting on the Ceiling of an Assembly Plant |
US9783250B2 (en) * | 2013-09-24 | 2017-10-10 | Torsten Hösker | Overhead conveying apparatus for mounting on the ceiling of an assembly plant |
US20150361679A1 (en) * | 2014-06-17 | 2015-12-17 | Jereme Kent | Suspended Deck Systems, Kits, and Methods of Installing, Inspecting, and Repairing a Suspended Deck System |
US9487960B2 (en) * | 2014-06-17 | 2016-11-08 | One Energy Enterprises Llc | Suspended deck systems, kits, and methods of installing, inspecting, and repairing a suspended deck system |
JP2016079584A (en) * | 2014-10-10 | 2016-05-16 | 株式会社杉孝 | Chain hanging metal fitting |
US10119229B1 (en) | 2015-04-27 | 2018-11-06 | New Access Solutions, Inc. | Work platform rail system |
CN105926917A (en) * | 2016-06-16 | 2016-09-07 | 中建七局建筑装饰工程有限公司 | Suspension platform for construction of steel structure cornice exterior facing, and construction method and detaching method of suspension platform |
US10165853B2 (en) * | 2016-10-05 | 2019-01-01 | Reza Omidinejad | Foldable table attached to the ceiling |
US11421432B1 (en) * | 2017-12-29 | 2022-08-23 | Paul Kristen, Inc. | Shield |
US11136967B2 (en) * | 2018-07-02 | 2021-10-05 | Inventus Holdings, Llc | Articulating joint for wind turbine |
US11401668B1 (en) * | 2018-11-26 | 2022-08-02 | Paul Kristen, Inc. | Method of suspending a platform from a bridge main cable |
US10738423B1 (en) * | 2018-11-26 | 2020-08-11 | Paul Kristen, Inc. | Platform and the hanging thereof from a bridge main cable |
CN109469302A (en) * | 2018-12-28 | 2019-03-15 | 中冶天工集团天津有限公司 | A kind of modular structure, method of construction and the method for dismounting of fast demountable modular platform |
IT201900013140A1 (en) * | 2019-07-29 | 2021-01-29 | Euroedile Srl | Monorail guide and mounting system for the creation of suspended worktops using said guide |
US11002026B1 (en) * | 2020-03-06 | 2021-05-11 | Paul Kristen, Inc. | Adjustable suspension assembly |
US11261610B1 (en) * | 2020-03-06 | 2022-03-01 | Paul Kristen, Inc. | Suspension assembly |
IT202100015329A1 (en) * | 2021-06-11 | 2022-12-11 | Euroedile S R L | Mounting method for making suspended worktops |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20040020138A1 (en) | Modular platform system | |
CA2554320C (en) | Rapidly deployable temporary modular structures and component elements thereof | |
US5299655A (en) | Workplace support and enclosure | |
US5730245A (en) | Safety cable deck anchor | |
CN202324568U (en) | Scaffold | |
US20020029932A1 (en) | Bridge platform | |
JP6786070B2 (en) | Permanent scaffolding installation method for bridge inspection | |
US6848221B1 (en) | Overhang falsework | |
US7000733B2 (en) | Work platform | |
US6227331B1 (en) | Bridge platform | |
JP3991067B1 (en) | Temporary bridge between railway platforms | |
US20080250579A1 (en) | Modular Support Catch System | |
US6267201B1 (en) | Work platform for roof construction work | |
KR101807406B1 (en) | Scaffolding equipment for bridge maintenance | |
EP1206611B1 (en) | Scaffolding | |
CN114045752B (en) | Floating crane aerial positioning cantilever assembling method for large-section steel truss box girder | |
CN218758596U (en) | Finalized temporary bearing operation platform | |
JP2006118191A (en) | Construction method and formwork structure of concrete floor slab for composite floor slab bridge | |
AU707069B2 (en) | Work platform for roof construction work | |
CN213171372U (en) | Light-duty assembled vertical transportation device | |
AU2004200088B2 (en) | Work platform | |
JP3746567B2 (en) | Reinforced steel plate installation method | |
CN218541682U (en) | Steel ramp | |
GB2322899A (en) | A work platform for a roof | |
CN116397523A (en) | Steel springboard manned platform for repairing bridge bottom of highway and railway dual-purpose bridge and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |