US20030101661A1 - Diversion system and method - Google Patents
Diversion system and method Download PDFInfo
- Publication number
- US20030101661A1 US20030101661A1 US10/001,005 US100501A US2003101661A1 US 20030101661 A1 US20030101661 A1 US 20030101661A1 US 100501 A US100501 A US 100501A US 2003101661 A1 US2003101661 A1 US 2003101661A1
- Authority
- US
- United States
- Prior art keywords
- deflector
- trough
- hanger
- containment
- machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 36
- 238000009434 installation Methods 0.000 claims abstract description 31
- 230000015572 biosynthetic process Effects 0.000 claims abstract description 12
- 239000000463 material Substances 0.000 claims description 18
- 230000000149 penetrating effect Effects 0.000 claims description 5
- 230000013011 mating Effects 0.000 claims description 3
- 230000006835 compression Effects 0.000 abstract description 9
- 238000007906 compression Methods 0.000 abstract description 9
- 230000008569 process Effects 0.000 abstract description 6
- 230000000712 assembly Effects 0.000 abstract description 2
- 238000000429 assembly Methods 0.000 abstract description 2
- 239000010421 standard material Substances 0.000 description 7
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 7
- 230000008901 benefit Effects 0.000 description 5
- 238000009825 accumulation Methods 0.000 description 4
- 239000002184 metal Substances 0.000 description 4
- 238000003780 insertion Methods 0.000 description 3
- 230000037431 insertion Effects 0.000 description 3
- 230000003628 erosive effect Effects 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 239000004809 Teflon Substances 0.000 description 1
- 229920006362 Teflon® Polymers 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 230000007257 malfunction Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 230000000717 retained effect Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
- E04D13/04—Roof drainage; Drainage fittings in flat roofs, balconies or the like
- E04D13/064—Gutters
- E04D13/072—Hanging means
- E04D13/0725—Hanging means situated above or inside the gutter
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
- E04D13/04—Roof drainage; Drainage fittings in flat roofs, balconies or the like
- E04D13/064—Gutters
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
- E04D13/04—Roof drainage; Drainage fittings in flat roofs, balconies or the like
- E04D13/076—Devices or arrangements for removing snow, ice or debris from gutters or for preventing accumulation thereof
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/49—Method of mechanical manufacture
- Y10T29/49826—Assembling or joining
- Y10T29/49828—Progressively advancing of work assembly station or assembled portion of work
- Y10T29/49829—Advancing work to successive stations [i.e., assembly line]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/51—Plural diverse manufacturing apparatus including means for metal shaping or assembling
- Y10T29/5136—Separate tool stations for selective or successive operation on work
- Y10T29/5137—Separate tool stations for selective or successive operation on work including assembling or disassembling station
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/53—Means to assemble or disassemble
- Y10T29/53313—Means to interrelatedly feed plural work parts from plural sources without manual intervention
- Y10T29/53383—Means to interrelatedly feed plural work parts from plural sources without manual intervention and means to fasten work parts together
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/53—Means to assemble or disassemble
- Y10T29/534—Multiple station assembly or disassembly apparatus
- Y10T29/53417—Means to fasten work parts together
Definitions
- the present invention relates to rain and run-off collection and diversion systems and, in particular, to systems and methods for such systems that exhibit reduced debris accumulation.
- rain diversion systems employ gutters that are open channels to collect run-off from the roof.
- Diversion or gutter systems devised with open-channeled rain gutters tend to accumulate debris including sticks, leaves and other matter that is swept toward the gutter by the gravity-induced flow of water down the pitch of the roof.
- debris can cause malfunction of the system as well as significant problems with leakage and corrosion. Roof and structural rotting as well as erosion can be precipitated by the consequent accumulation of water without appropriate attendant diversion.
- troughs There are two principal sizes of coil used to form the gutter channels known in the art as “troughs.” For the widely found five inch-wide (5′′) gutter troughs, standard coil material of 11 and 7 ⁇ 8 inches (117 ⁇ 8′′) is employed (except in the Northeastern U.S. where 5′′ gutter troughs are formed from 11 and 3 ⁇ 4 inch (11 3 ⁇ 4′′) stock). For the less widely found, but still common, six inch (6′′) trough, fifteen inch (15′′) coil is used.
- the shape of the front of the gutter trough contributes to structural stability and, in some systems, provides an interface for hanger or deflector attachment.
- the shape of the border area of the gutter trough can significantly affect gutter stability during installation, an important consideration in any gutter system.
- lengths of gutter trough are formed in runs approximately 40 feet long. Without sufficient resistance to deformation, the gutter trough may fold or crease, particularly when being moved during installation, thus limiting run lengths and increasing installation difficulty.
- 5′′ gutter troughs with debris deflectors have typically used coil wider than 117 ⁇ 8′′ or 113 ⁇ 4′′ for gutter formation to provide material sufficient to provide a stabilizing front gutter channel configuration with a raised back gutter trough wall to accommodate appropriate inclination of the deflector. Consequently, because of the higher cost of non-standard material, in particular, deflector-fitted 5′′ trough gutter systems have cost significantly more than open-faced 5′′ trough gutter systems crafted from standard sized coil material.
- the deflector is opened wider to embrace coupling portions of a fastening support device. This is difficult to do with one hand. Installation flexibility is also minimal because, as described in Knudson, the hanger and trough are affixed to the structure before the deflector is attached to the gutter trough. As in other prior systems, this prevents creation of a structurally sound member before the deflector and gutter trough assembly is moved from the machine site to the eventual installation location, an advantage for installation having considerable value in reducing labor cost and inconvenience.
- Methods are provided for installation of a rain diversion system including formation of a deflector with a machine placed above a forming machine dedicated to formation of a trough.
- trough is run from a first machine, end caps are installed, outlet sites are punched and outlets installed for joinder with downspouts, miters are cut, where appropriate, and a cavity structure of the hanger is brought into place to mate a containment lip of the hanger with the containment shelf of the trough.
- Corresponding deflector is run from a second machine and the deflector is placed on the trough as deflector attachment cavities of the hanger are used to retain deflector. In alternative methods, one cavity retains the deflector for conveyance to the installation location on the structure.
- the entire assembly may then be transported to a location on a lower level such as ground, for example, corresponding to the eventual installation location on the structure.
- the deflector may be attached to a formed trough in which hangers are positioned to allow movement of the trough-deflector combination as a unit from the machine-site to the installation location on the structure. Associated installation methods are provided.
- FIG. 1 depicts a cross-sectional view of a prior art trough of a configuration that is common in the field.
- FIG. 2 depicts a cross-sectional view of a trough configured in accordance An with a preferred embodiment of the present invention.
- FIG. 3 depicts a cross-sectional view of a trough, hanger and deflector assembly in accordance with a preferred embodiment of the present invention.
- FIG. 4 depicts a cross-sectional view of a half-round trough, hanger and deflector assembly in accordance with a preferred embodiment of the present invention.
- FIG. 5 depicts a cross-section of an enlarged area of the trough, hanger, and deflector depicted in FIG. 3.
- FIG. 6 depicts another embodiment of trough, hanger, and deflector devised in accordance with a preferred embodiment of the present invention.
- FIG. 7 is an enlarged depiction showing a containment wall border area of a trough configured in accordance with a preferred embodiment of the present invention.
- FIG. 8 is an enlarged depiction of a receptive cavity structure of a hanger configured in accordance with a preferred embodiment.
- FIG. 9 depicts the border area of a trough and a receptive cavity structure of a hanger configured in accordance with a preferred embodiment of the present invention.
- FIG. 10 depicts the border area of a trough and a receptive cavity structure of a hanger configured in accordance with an alternative embodiment of the present invention.
- FIG. 11 depicts the border area of a trough and a receptive cavity structure of a hanger configured in accordance with an alternative embodiment of the present invention.
- FIG. 12 depicts the border area of a trough and a receptive cavity structure of a hanger configured in accordance with another alternative embodiment of the present invention.
- FIG. 13 is an end-on depiction of a forming machine disposed above a second forming machine as employed in a preferred embodiment of the present invention.
- FIG. 14 is a plan view of two offset forming machines as employed in a preferred embodiment of the present invention.
- FIG. 15 depicts two-armed run-out stands as employed in a preferred embodiment of the present invention.
- FIG. 1 depicts a cross-sectional view of a prior art trough 5 of standard configuration that is common in the field. As shown in FIG. 1, the depicted trough 5 has a folded edge or shelf along its front containment wall.
- FIG. 2 depicts a cross-sectional view of a trough 10 configured in accordance with a preferred embodiment of the present invention.
- Trough 10 has a front containment wall 12 that has an inwardly projecting shelf 14 that is part of containment wall border area 16 of front containment wall 12 .
- Trough 10 has a back wall 18 .
- containment wall 12 need not be a planar wall but may take a variety of shapes and configurations to provide a containment function for collected liquid.
- a channel is formed for water collection and diversion bottomed with floor 20 .
- standard material coil of 117 ⁇ 8 inches may be employed.
- standard material coil may exhibit some variation in width depending upon manufacturer or local custom. Consequently, in a preferred embodiment employing standard material, standard material between 115 ⁇ 8 inches and 12 inches in width may be employed to create trough 10 with a 5 inch opening.
- standard material between 115 ⁇ 8 inches and 12 inches in width may be employed to create trough 10 with a 5 inch opening.
- the well-known 6-inch trough can be created in conformity with an alternative embodiment of the present invention by use of 15 inch material coil.
- Containment wall border area 16 may be formed by bending, folding, forming or other of the well-known means for configuring trough 10 .
- a preferred method for creating containment wall border area 16 is with a roller-based machine at the same time that the configuration of trough 10 is created from coil stock.
- the standard material coil stock is positioned so as to move the furthest reach of the formed back wall between 3 ⁇ 4 and 1 inch from the place the furthest reach of the back wall would occupy in formation of a standard OG gutter trough so as to bring greater height to the back wall for deflector inclination during trough formation.
- the material is shifted around the form relative to the material placement employed in forming the OG gutter.
- FIG. 3 depicts as assembly 15 , a cross-sectional view of trough 10 in use with hanger 30 and deflector 40 in accordance with a preferred embodiment of the present invention.
- the system described can be used either with or without deflector 40 .
- hanger 30 includes optional deflector attachment cavities 32 and 34 .
- hanger 30 is stamped from metal, but any number of materials and formation techniques may be used to create a hanger 30 having the features described here.
- hanger 30 may be made of metal or plastic such as Teflon, or higher strength polys. If made of metal, hanger 30 can be forged, stamped, extruded, die cut or cast or other technique familiar to the trade.
- Hanger 30 includes receptive cavity structure 31 that will be later described in more detail while front containment wall 12 exhibits containment wall border area 16 that will be described in more detail.
- FIG. 4 depicts a cross-sectional view of a half-round trough assembled with a hanger and deflector in accordance with a preferred embodiment of the present invention.
- deflector 40 is selectably attached to hanger 30 by insertion of flex fold 42 into cavity 34 and insertion of attachment fold 46 into cavity 32 .
- curve 44 provides a ready method to accomplish this selective attachment.
- flex fold 42 and attachment fold 46 are first and second long axis perimeters of deflector 40 and need not be “folds” but may be any edge or fold or border of the deflector which may be inserted into the appropriate cavity of the hanger.
- This selectable attachment feature of deflector 40 as shown in this depiction of a preferred embodiment of the present invention allows assemblage of deflector 40 to hanger 30 before the assembly 15 is installed on a structure.
- hanger 30 has optional penetrative prongs 36 shown penetrating back wall 18 of trough 10 .
- prongs 36 preferably have a concavity 38 that cooperates with dimple 39 on back wall 18 to preliminarily position hanger 30 for prong insertion through back wall 18 with an appropriate compression tool such as a is specialized pliers or other readily available and adapted instrument.
- Back abutment 41 of hanger 30 is placed against back wall 18 with concavity 38 placed against dimple 39 and the compression tool pushes prongs through the back wall 18 .
- hanger 30 There need not be a specially configured structure for an abutment for hanger 30 , the back of the structure of hanger 30 disposed against back wall 18 being the abutment.
- the prongs are folded by the compression tool against the back of back wall 18 to affix hanger 30 . This operation can be performed before attachment of the trough to the structure and may be performed at the machine site or elsewhere to affix back wall 18 in relation to front containment wall 12 while creating a mechanically sound structure ready for attachment of deflector 40 .
- Hanger 30 need not have prongs 36 but their use is advantageous.
- flex fold 42 of deflector 40 cooperates with cavity 34 to allow a resistance hinge-like action of deflector 40 .
- deflector 40 may be lifted from hanger 30 by compression of curve 44 of deflector 40 to remove attachment fold 46 of deflector 40 from cavity 32 .
- the forward part of deflector 40 is then lifted from its position as flex fold 42 and cavity 32 allow a spring-like rotational opening of a gap between deflector 40 and hanger 30 through which fastener 50 may manipulated to install assembly 15 on the structure as fastener 50 is screwed or pounded or otherwise inserted into place.
- fastener 50 may be a nail or screw or spike or other such projecting fastener, many of which are common in the field.
- Hanger 30 includes, in a preferred embodiment, indent 48 to mate with ridge 52 of deflector 40 while stop 54 of hanger 30 inhibits deflector 30 from unpredicted separation from hanger 30 , particularly during installation or servicing.
- fastener 50 slides into a guide slot 56 created in hanger 30 to avoid addition of height or special platforms to hanger 30 .
- the compression fitting of deflector 40 into cavities 32 and 34 allows ready placement of deflector 40 on the trough 10 and hanger 30 combination at the machine-site to allow a single installation trip from machine site to installation site with the combined structure of deflector and trough.
- FIG. 6 depicts another embodiment of assembly 15 devised in accordance with the present invention and which employs an extruded hanger 30 .
- FIG. 6 depicts fastener 50 as it would be engaged into a structure.
- Those of skill in the art will recognize that the disclosed configuration allows the front of deflector 40 to be lifted from hanger 30 to insert fastener 50 into the structure.
- FIG. 7 is an enlarged depiction showing containment wall border area 16 of trough 10 of FIG. 3.
- containment wall border area 16 includes by containment edge or shelf 52 that extends inwardly to the trough. Either part or all of containment shelf 52 may extend inwardly to the trough and that inward extension may be at an angle or horizontal orientation.
- containment wall border area 16 includes rise 53 .
- Containment shelf 52 may be folded, or a single material thickness and may extend horizontally (as shown in the preferred embodiment view of FIG. 7) or at an angle from the horizontal as shown in FIG. 10, or have a vertical extension as shown, for example, in FIG. 11.
- Part or all of shelf 52 can, but need not, be canted at an angle to match the configuration of containment lip 54 of receptive cavity structure 31 of hanger 30 . Consequently, those of skill in the art will recognize that containment lip 54 may take a variety of configurations to cooperate with the variety of configurations of containment shelf 52 within the scope of the invention to extend a portion of containment lip 54 over a portion of containment shelf 52 and thereby, according to the vernacular of the present disclosure, “mate” containment lip 54 with containment shelf 52 .
- the part of containment shelf 52 that extends inwardly to the trough need not be the portion of shelf 52 over which a portion of containment lip 54 extends to mate with containment shelf 52 . When a portion of containment lip 54 extends over a portion of containment shelf 52 , the elements are mated.
- FIG. 8 is an enlarged depiction of receptive cavity structure 31 of hanger 30 in a preferred embodiment.
- Receptive cavity structure 31 as shown in FIG. 8, includes fulcrum ridge 56 over which, rise 53 of front containment wall border area 16 tents.
- FIG. 9 depicts a preferred disposition of containment lip 54 mated with containment shelf 52 to provide functional water bearing capacity for trough 10 while still allowing sufficient standard material coil to provide a back wall 18 of sufficient height to provide necessary inclination for deflector 40 .
- containment lip 54 is mated with containment shelf 52 .
- FIGS. 10, 11, and 12 depict alternative arrangements for the mating between containment lip 54 and containment shelf 52 and they are included only as example embodiments and not as limitations for the scope of the present invention.
- FIG. 10 depicts an alternative embodiment of the invention showing containment shelf 52 as angled upward and containment lip 54 as angled downward as shelf 52 and lip 54 are mated.
- containment lip 54 may be horizontal while containment shelf 52 is angled or containment lip 54 may be angled while containment shelf 52 exhibits a horizontal character or each may be independently angled or horizontal.
- FIG. 11 shows another alternative embodiment of the present invention in which containment lip 54 extends over a vertical extension portion of containment shelf 52 . This is another example of the mating of containment lip 54 and containment shelf 52 .
- FIG. 12 shows yet another alternative embodiment of the present invention in which containment lip 54 has an extension that deflects downward over a portion of containment shelf 52 .
- Containment lip 54 and containment shelf 52 are mated in the depiction of FIG. 12.
- a preferred method for installation includes formation of deflector 40 with a machine placed above a forming machine dedicated to formation of trough 10 .
- FIG. 13 depicts forming machine 72 disposed above forming machine 70 in the bed 74 of a truck.
- the machines need not be placed on the truck bed that is merely shown as an exemplar setting.
- a track is employed that allows forward and backward movement of upper machine 72 relative to the bottom machine 70 for maintenance of the lower machine 70 as will be recognized by those of skill in the art.
- Machine 70 is configured to form lengths of trough 10 configured in accordance with the present invention, while machine 72 is configured to form lengths of deflector 40 configured in accordance with the present invention.
- material cradles 74 and 76 of the respective machines 70 and 72 are loaded with coil.
- Trough machine 70 consumes coil material 75 of 117 ⁇ 8 inches in width in an application configured to produce troughs 5 inches in width. Other widths of coil may also be used.
- Cradle 76 of deflector machine 72 is loaded with coil material 77 of between 75 ⁇ 8 inches and 8 inches to produce deflectors. Other widths may be used for larger or smaller configurations. Emergent from machine 70 are lengths 78 of trough 10 . Emergent from machine 72 are lengths 80 of deflector 40 .
- two-armed run-out stands 82 and 84 having upper arms 86 and lower arms 88 provide work placement for lengths of deflector 40 and trough 10 .
- End caps 90 a are placed in appropriate locations.
- end caps are two-piece, with piece 90 a fitted to troughs 10 and piece 90 b fitted to deflector 40 .
- a preferred method for installation of the present system proceeds as follows. As length 78 of trough 10 is run from machine 70 , end caps 90 a are installed where appropriate, outlet sites are punched and outlets installed for joinder with downspouts, miters are cut and cavity structure 31 of hanger 30 is brought into place to mate containment lip 54 of hanger 30 with containment shelf 52 of trough 10 . Hangers 30 are punched through the back wall 18 of trough 10 and prongs 36 are crimped. These steps can be performed either at the machine or with the assistance of the run-out stands. Hanger fitted trough 10 is rested on run-out stands.
- Corresponding length 80 of deflector 40 is run from machine 72 and is installed with end caps 90 b and miters are cut appropriate. Length 80 of deflector 40 is placed on length 78 of trough 10 as deflector attachment cavities 34 and 32 are used to retain deflector 40 . In alternative methods, cavity 34 is used to retain deflector 40 for conveyance to the installation location on the structure but, where some distance is involved, use of both cavities 32 and 34 keeps deflector 40 more securely retained. In either case, the entire assembly may then be transported to a location on a lower level such as ground, for example, corresponding to the eventual installation location on the structure. The process is repeated until all assemblies of trough, hangers and deflector have been processed.
- deflector 40 is compressed to fit flex fold 42 and attachment fold 46 of deflector 40 to cavities 34 and 32 respectively of deflector 40 .
- the second installer forms downspouts and attaches them to the structure.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Details Of Indoor Wiring (AREA)
- Supports For Pipes And Cables (AREA)
- Extrusion Moulding Of Plastics Or The Like (AREA)
- Chutes (AREA)
Abstract
Description
- The present invention relates to rain and run-off collection and diversion systems and, in particular, to systems and methods for such systems that exhibit reduced debris accumulation.
- Diversion of rain from buildings is a well-known and beneficial practice. For centuries, architects and builders have understood the benefits of diverting rain to forestall erosion, maintain structural stability, and preserve vegetation. In recent decades, a multitude of systems have been developed to divert rain from structures and homes. Typically, such systems have been placed beneath or adjacent to the roofline to allow collection and diversion of rain accumulated from across the surface area of the structure roof. Such systems are sometimes called “gutter” systems.
- Frequently, rain diversion systems employ gutters that are open channels to collect run-off from the roof. Diversion or gutter systems devised with open-channeled rain gutters tend to accumulate debris including sticks, leaves and other matter that is swept toward the gutter by the gravity-induced flow of water down the pitch of the roof. Such debris can cause malfunction of the system as well as significant problems with leakage and corrosion. Roof and structural rotting as well as erosion can be precipitated by the consequent accumulation of water without appropriate attendant diversion.
- Consequently, a variety of gutter systems of varying complexity have been developed to inhibit debris accumulation in gutter systems. Simple systems have merely placed screens across open-faced gutter channels. These techniques commonly have their own debris accumulation problems. Other systems employ a deflector described by various terms such as “hood” or “shield” that deflect debris while the gutter accumulates water for diversion to determined locations. For At example, in U.S. Pat. No. 4,757,649 to Vahldieck, a system is described that purportedly preferentially collects water and deflects debris over a continuous double-curved shield through which a spike passes to affix the shield to a back support wall of the gutter. The use of shields and other deflectors is well known, and a variety of prior systems modify the shape of the deflector to purportedly take better advantage of the surface tension qualities of diverted run off. For example, in U.S. Pat. No. 4,404,775 to Demartini, a system of longitudinal ridges is imposed on a deflector and is said to improve adhesion of the water to the deflector to improve transference to the gutter.
- Others have developed systems to support debris deflectors or affix the deflector to the gutter. For example, in U.S. Pat. No. 4,497,146 to Demartini, a rain deflector support is described that purports to support the underside of a rain gutter deflector while positioning the deflector in relation to the gutter.
- As diversions systems have become more complicated, so have the associated issues of cost, specialized material stock, and installation efficiency become more unwieldy. For example, most systems that employ a deflector affix the deflector with screws or clips that reduce flexibility of the system or add an extra part (in addition to the hanger) to the assembly. If the deflector cannot be easily unfastened from the gutter, repair and maintenance are complicated.
- For a variety of reasons, diversion systems that deflect debris have not been adopted as widely as demand would suggest. There are a variety of reasons for this result. One reason for the minimal market penetration is the use of non-standard widths of metal stock or “coil” for the gutter trough above which the deflector is positioned. Non-standard coil sizes add significantly to the cost and availability of such systems.
- There are two principal sizes of coil used to form the gutter channels known in the art as “troughs.” For the widely found five inch-wide (5″) gutter troughs, standard coil material of 11 and ⅞ inches (11⅞″) is employed (except in the Northeastern U.S. where 5″ gutter troughs are formed from 11 and ¾ inch (11 ¾″) stock). For the less widely found, but still common, six inch (6″) trough, fifteen inch (15″) coil is used.
- In almost all deflection systems, when installed, a deflector must be inclined by a degree sufficient to impart velocity to the run-off great enough to impel debris from the deflector. This requires that the back of the trough, proximal to which the deflector is attached, be high enough to provide sufficient incline for the deflector. Debris deflection systems for 5″ trough gutters employ non-standard coil for the gutter as a result of taking material from the front of the trough to raise the back wall of the gutter. With known designs, if standard width coil of 11⅞ inches were used to form the trough, the shift of material around the standard trough form factor (as employed in the art to create the “OG” 5 inch gutter) from the front trough channel containment wall to the back wall of the trough to provide sufficient deflector inclination leaves insufficient material for the front This process takes, however, material from the front border area of the trough to create the stiffening front channel edge that provides installation stability and standard hanger affixation capability.
- The shape of the front of the gutter trough contributes to structural stability and, in some systems, provides an interface for hanger or deflector attachment. In particular, the shape of the border area of the gutter trough can significantly affect gutter stability during installation, an important consideration in any gutter system. Typically, lengths of gutter trough are formed in runs approximately 40 feet long. Without sufficient resistance to deformation, the gutter trough may fold or crease, particularly when being moved during installation, thus limiting run lengths and increasing installation difficulty. Consequently, 5″ gutter troughs with debris deflectors have typically used coil wider than 11⅞″ or 11¾″ for gutter formation to provide material sufficient to provide a stabilizing front gutter channel configuration with a raised back gutter trough wall to accommodate appropriate inclination of the deflector. Consequently, because of the higher cost of non-standard material, in particular, deflector-fitted 5″ trough gutter systems have cost significantly more than open-faced 5″ trough gutter systems crafted from standard sized coil material.
- Previous system design, whether with 5″ or 6″ gutter troughs, has also contributed to unwieldy installation techniques, further increasing the expense of diversion systems that employ deflection hoods or shields. Some deflection systems form the trough and deflector from one piece of material. More commonly, the trough and deflector are separately formed and joined in place at the structure roof edge. Typically, two forming machines are employed during installation of a two-piece deflection system. One machine is dedicated to gutter trough formation, while the other is configured to form the deflector. The machines are typically placed side-by-side. The installation team typically first forms trough lengths sufficient to gutter the structure. The troughs are then affixed in place on the structure. After the troughs are fastened to the building, corresponding deflectors are formed and affixed to the in-place troughs. This process requires multiple trips to and from the forming machines as well as at least two trips up a ladder to install separately, the two large pieces of the system. The described process requires dexterity which, even if applied, cannot ameliorate the difficulty of moving long lengths of deflector that lack structural rigidity unless affixed to, and combined with, the gutter trough.
- The inflexible nature of the affixation between hood and trough in prior systems results in several shortcomings. Replacement of deflector sections is made difficult by the inflexible nature of the affixation between deflector and trough. Nail or screw attachment of the deflector is at least semi-permanent, and when the deflector is attached by such means, the system is less easily repaired, serviced, or replaced. Other systems have more sophisticated deflector-attachment techniques, but those systems lack installation flexibility. For example, in U.S. Pat. No. 5,845,435 to Knudson, there is there purportedly described a system having a hood which snaps into particularly configured hangers affixed along the length of the gutter trough. In this system however, the deflector is opened wider to embrace coupling portions of a fastening support device. This is difficult to do with one hand. Installation flexibility is also minimal because, as described in Knudson, the hanger and trough are affixed to the structure before the deflector is attached to the gutter trough. As in other prior systems, this prevents creation of a structurally sound member before the deflector and gutter trough assembly is moved from the machine site to the eventual installation location, an advantage for installation having considerable value in reducing labor cost and inconvenience.
- Consequently, what is needed therefore, is a rain collection and diversion system that employs standard-sized coil, has structural soundness and strength, and can be partially assembled close to the machine-site while being easily installed.
- Methods are provided for installation of a rain diversion system including formation of a deflector with a machine placed above a forming machine dedicated to formation of a trough. As trough is run from a first machine, end caps are installed, outlet sites are punched and outlets installed for joinder with downspouts, miters are cut, where appropriate, and a cavity structure of the hanger is brought into place to mate a containment lip of the hanger with the containment shelf of the trough. Corresponding deflector is run from a second machine and the deflector is placed on the trough as deflector attachment cavities of the hanger are used to retain deflector. In alternative methods, one cavity retains the deflector for conveyance to the installation location on the structure. In either case, the entire assembly may then be transported to a location on a lower level such as ground, for example, corresponding to the eventual installation location on the structure. In a preferred embodiment, the deflector may be attached to a formed trough in which hangers are positioned to allow movement of the trough-deflector combination as a unit from the machine-site to the installation location on the structure. Associated installation methods are provided.
- FIG. 1 depicts a cross-sectional view of a prior art trough of a configuration that is common in the field.
- FIG. 2 depicts a cross-sectional view of a trough configured in accordance An with a preferred embodiment of the present invention.
- FIG. 3 depicts a cross-sectional view of a trough, hanger and deflector assembly in accordance with a preferred embodiment of the present invention.
- FIG. 4 depicts a cross-sectional view of a half-round trough, hanger and deflector assembly in accordance with a preferred embodiment of the present invention.
- FIG. 5 depicts a cross-section of an enlarged area of the trough, hanger, and deflector depicted in FIG. 3.
- FIG. 6 depicts another embodiment of trough, hanger, and deflector devised in accordance with a preferred embodiment of the present invention.
- FIG. 7 is an enlarged depiction showing a containment wall border area of a trough configured in accordance with a preferred embodiment of the present invention.
- FIG. 8 is an enlarged depiction of a receptive cavity structure of a hanger configured in accordance with a preferred embodiment.
- FIG. 9 depicts the border area of a trough and a receptive cavity structure of a hanger configured in accordance with a preferred embodiment of the present invention.
- FIG. 10 depicts the border area of a trough and a receptive cavity structure of a hanger configured in accordance with an alternative embodiment of the present invention.
- FIG. 11 depicts the border area of a trough and a receptive cavity structure of a hanger configured in accordance with an alternative embodiment of the present invention.
- FIG. 12 depicts the border area of a trough and a receptive cavity structure of a hanger configured in accordance with another alternative embodiment of the present invention.
- FIG. 13 is an end-on depiction of a forming machine disposed above a second forming machine as employed in a preferred embodiment of the present invention.
- FIG. 14 is a plan view of two offset forming machines as employed in a preferred embodiment of the present invention.
- FIG. 15 depicts two-armed run-out stands as employed in a preferred embodiment of the present invention.
- FIG. 1 depicts a cross-sectional view of a prior art trough5 of standard configuration that is common in the field. As shown in FIG. 1, the depicted trough 5 has a folded edge or shelf along its front containment wall.
- FIG. 2 depicts a cross-sectional view of a
trough 10 configured in accordance with a preferred embodiment of the present invention.Trough 10 has afront containment wall 12 that has an inwardly projecting shelf 14 that is part of containmentwall border area 16 offront containment wall 12.Trough 10 has aback wall 18. As shown,containment wall 12 need not be a planar wall but may take a variety of shapes and configurations to provide a containment function for collected liquid. Betweenfront containment wall 12 andback wall 18, a channel is formed for water collection and diversion bottomed with floor 20. In an embodiment having a rounded or “half-round” trough, it will be recognized that there is no distinct floor 20 andfront containment wall 12 andback wall 18 will not have traditional “wall” planar areas but blend into an arcuate floor area. - In a 5-inch embodiment of
trough 10 in which there is approximately 5 inches betweenback wall 18 and the farthest reach of containmentwall border area 16, standard material coil of 11⅞ inches may be employed. As those of skill in the art will recognize, standard material coil may exhibit some variation in width depending upon manufacturer or local custom. Consequently, in a preferred embodiment employing standard material, standard material between 11⅝ inches and 12 inches in width may be employed to createtrough 10 with a 5 inch opening. Certainly other sizes of troughs can be created to advantage by employment of the present invention. For example, the well-known 6-inch trough can be created in conformity with an alternative embodiment of the present invention by use of 15 inch material coil. Containmentwall border area 16 may be formed by bending, folding, forming or other of the well-known means for configuringtrough 10. A preferred method for creating containmentwall border area 16 is with a roller-based machine at the same time that the configuration oftrough 10 is created from coil stock. When a 5 inch trough in accordance with a preferred embodiment of the present invention is created with a roller-based machine, the standard material coil stock is positioned so as to move the furthest reach of the formed back wall between ¾ and 1 inch from the place the furthest reach of the back wall would occupy in formation of a standard OG gutter trough so as to bring greater height to the back wall for deflector inclination during trough formation. As well as using forms in accordance with the present invention, the material is shifted around the form relative to the material placement employed in forming the OG gutter. - FIG. 3 depicts as
assembly 15, a cross-sectional view oftrough 10 in use withhanger 30 anddeflector 40 in accordance with a preferred embodiment of the present invention. The system described can be used either with or withoutdeflector 40. - As shown in FIG. 3,
hanger 30 includes optionaldeflector attachment cavities hanger 30 is stamped from metal, but any number of materials and formation techniques may be used to create ahanger 30 having the features described here. For example,hanger 30 may be made of metal or plastic such as Teflon, or higher strength polys. If made of metal,hanger 30 can be forged, stamped, extruded, die cut or cast or other technique familiar to the trade.Hanger 30 includesreceptive cavity structure 31 that will be later described in more detail whilefront containment wall 12 exhibits containmentwall border area 16 that will be described in more detail. FIG. 4 depicts a cross-sectional view of a half-round trough assembled with a hanger and deflector in accordance with a preferred embodiment of the present invention. - With reference to FIGS. 3 and 5 (which figure illustrates an enlarged portion of FIG. 3 about the area of flex fold42),
deflector 40 is selectably attached tohanger 30 by insertion of flex fold 42 intocavity 34 and insertion of attachment fold 46 intocavity 32. In a preferred compression embodiment,curve 44 provides a ready method to accomplish this selective attachment. Those of skill in the art will recognize thatflex fold 42 and attachment fold 46 are first and second long axis perimeters ofdeflector 40 and need not be “folds” but may be any edge or fold or border of the deflector which may be inserted into the appropriate cavity of the hanger. This selectable attachment feature ofdeflector 40 as shown in this depiction of a preferred embodiment of the present invention allows assemblage ofdeflector 40 tohanger 30 before theassembly 15 is installed on a structure. - As shown in conjunction with FIGS.3 and FIG. 5,
hanger 30 has optionalpenetrative prongs 36 shown penetratingback wall 18 oftrough 10. As shown more closely in FIG. 5, prongs 36 preferably have aconcavity 38 that cooperates with dimple 39 onback wall 18 to preliminarily positionhanger 30 for prong insertion throughback wall 18 with an appropriate compression tool such as a is specialized pliers or other readily available and adapted instrument. Backabutment 41 ofhanger 30 is placed againstback wall 18 withconcavity 38 placed against dimple 39 and the compression tool pushes prongs through theback wall 18. There need not be a specially configured structure for an abutment forhanger 30, the back of the structure ofhanger 30 disposed againstback wall 18 being the abutment. The prongs are folded by the compression tool against the back ofback wall 18 to affixhanger 30. This operation can be performed before attachment of the trough to the structure and may be performed at the machine site or elsewhere to affix backwall 18 in relation tofront containment wall 12 while creating a mechanically sound structure ready for attachment ofdeflector 40.Hanger 30 need not haveprongs 36 but their use is advantageous. - As described with continuing reference to FIGS. 3 and 5, flex fold42 of
deflector 40 cooperates withcavity 34 to allow a resistance hinge-like action ofdeflector 40. In particular,deflector 40 may be lifted fromhanger 30 by compression ofcurve 44 ofdeflector 40 to remove attachment fold 46 ofdeflector 40 fromcavity 32. The forward part ofdeflector 40 is then lifted from its position asflex fold 42 andcavity 32 allow a spring-like rotational opening of a gap betweendeflector 40 andhanger 30 through whichfastener 50 may manipulated to installassembly 15 on the structure asfastener 50 is screwed or pounded or otherwise inserted into place. In embodiments with penetrative fasteners,fastener 50 may be a nail or screw or spike or other such projecting fastener, many of which are common in the field. Other techniques for hangingassembly 15 are known in the art.Hanger 30 includes, in a preferred embodiment,indent 48 to mate withridge 52 ofdeflector 40 whilestop 54 ofhanger 30 inhibitsdeflector 30 from unpredicted separation fromhanger 30, particularly during installation or servicing. In a preferred embodiment,fastener 50 slides into aguide slot 56 created inhanger 30 to avoid addition of height or special platforms tohanger 30. The compression fitting ofdeflector 40 intocavities deflector 40 on thetrough 10 andhanger 30 combination at the machine-site to allow a single installation trip from machine site to installation site with the combined structure of deflector and trough. - FIG. 6 depicts another embodiment of
assembly 15 devised in accordance with the present invention and which employs an extrudedhanger 30. FIG. 6 depictsfastener 50 as it would be engaged into a structure. Those of skill in the art will recognize that the disclosed configuration allows the front ofdeflector 40 to be lifted fromhanger 30 to insertfastener 50 into the structure. - FIG. 7 is an enlarged depiction showing containment
wall border area 16 oftrough 10 of FIG. 3. As shown in FIG. 7, containmentwall border area 16 includes by containment edge orshelf 52 that extends inwardly to the trough. Either part or all ofcontainment shelf 52 may extend inwardly to the trough and that inward extension may be at an angle or horizontal orientation. In a preferred embodiment, containmentwall border area 16 includesrise 53.Containment shelf 52 may be folded, or a single material thickness and may extend horizontally (as shown in the preferred embodiment view of FIG. 7) or at an angle from the horizontal as shown in FIG. 10, or have a vertical extension as shown, for example, in FIG. 11. Part or all ofshelf 52 can, but need not, be canted at an angle to match the configuration ofcontainment lip 54 ofreceptive cavity structure 31 ofhanger 30. Consequently, those of skill in the art will recognize thatcontainment lip 54 may take a variety of configurations to cooperate with the variety of configurations ofcontainment shelf 52 within the scope of the invention to extend a portion ofcontainment lip 54 over a portion ofcontainment shelf 52 and thereby, according to the vernacular of the present disclosure, “mate”containment lip 54 withcontainment shelf 52. The part ofcontainment shelf 52 that extends inwardly to the trough need not be the portion ofshelf 52 over which a portion ofcontainment lip 54 extends to mate withcontainment shelf 52. When a portion ofcontainment lip 54 extends over a portion ofcontainment shelf 52, the elements are mated. - FIG. 8 is an enlarged depiction of
receptive cavity structure 31 ofhanger 30 in a preferred embodiment.Receptive cavity structure 31 as shown in FIG. 8, includesfulcrum ridge 56 over which, rise 53 of front containmentwall border area 16 tents. - FIG. 9 depicts a preferred disposition of
containment lip 54 mated withcontainment shelf 52 to provide functional water bearing capacity fortrough 10 while still allowing sufficient standard material coil to provide aback wall 18 of sufficient height to provide necessary inclination fordeflector 40. In this preferred depiction,containment lip 54 is mated withcontainment shelf 52. - FIGS. 10, 11, and12 depict alternative arrangements for the mating between
containment lip 54 andcontainment shelf 52 and they are included only as example embodiments and not as limitations for the scope of the present invention. FIG. 10 depicts an alternative embodiment of the invention showingcontainment shelf 52 as angled upward andcontainment lip 54 as angled downward asshelf 52 andlip 54 are mated. In other alternative and exemplar but not to be construed as limiting embodiments,containment lip 54 may be horizontal whilecontainment shelf 52 is angled orcontainment lip 54 may be angled whilecontainment shelf 52 exhibits a horizontal character or each may be independently angled or horizontal. - FIG. 11 shows another alternative embodiment of the present invention in which
containment lip 54 extends over a vertical extension portion ofcontainment shelf 52. This is another example of the mating ofcontainment lip 54 andcontainment shelf 52. - FIG. 12 shows yet another alternative embodiment of the present invention in which
containment lip 54 has an extension that deflects downward over a portion ofcontainment shelf 52.Containment lip 54 andcontainment shelf 52 are mated in the depiction of FIG. 12. - The present invention provides numerous advantages during installation of the system. A preferred method for installation includes formation of
deflector 40 with a machine placed above a forming machine dedicated to formation oftrough 10. FIG. 13 depicts formingmachine 72 disposed above formingmachine 70 in thebed 74 of a truck. The machines need not be placed on the truck bed that is merely shown as an exemplar setting. Preferably, a track is employed that allows forward and backward movement ofupper machine 72 relative to thebottom machine 70 for maintenance of thelower machine 70 as will be recognized by those of skill in the art.Machine 70 is configured to form lengths oftrough 10 configured in accordance with the present invention, whilemachine 72 is configured to form lengths ofdeflector 40 configured in accordance with the present invention. - In a preferred method in accordance with the present invention, material cradles74 and 76 of the
respective machines Trough machine 70 consumescoil material 75 of 11⅞ inches in width in an application configured to produce troughs 5 inches in width. Other widths of coil may also be used. Cradle 76 ofdeflector machine 72 is loaded withcoil material 77 of between 7⅝ inches and 8 inches to produce deflectors. Other widths may be used for larger or smaller configurations. Emergent frommachine 70 arelengths 78 oftrough 10. Emergent frommachine 72 arelengths 80 ofdeflector 40. - As shown in FIG. 15, two-armed run-out stands82 and 84 having upper arms 86 and
lower arms 88 provide work placement for lengths ofdeflector 40 andtrough 10. End caps 90 a are placed in appropriate locations. In a preferred embodiment, end caps are two-piece, with piece 90 a fitted totroughs 10 and piece 90 b fitted todeflector 40. - A preferred method for installation of the present system proceeds as follows. As
length 78 oftrough 10 is run frommachine 70, end caps 90 a are installed where appropriate, outlet sites are punched and outlets installed for joinder with downspouts, miters are cut andcavity structure 31 ofhanger 30 is brought into place to matecontainment lip 54 ofhanger 30 withcontainment shelf 52 oftrough 10.Hangers 30 are punched through theback wall 18 oftrough 10 andprongs 36 are crimped. These steps can be performed either at the machine or with the assistance of the run-out stands. Hanger fittedtrough 10 is rested on run-out stands. - Corresponding
length 80 ofdeflector 40 is run frommachine 72 and is installed with end caps 90 b and miters are cut appropriate.Length 80 ofdeflector 40 is placed onlength 78 oftrough 10 asdeflector attachment cavities deflector 40. In alternative methods,cavity 34 is used to retaindeflector 40 for conveyance to the installation location on the structure but, where some distance is involved, use of bothcavities deflector 40 more securely retained. In either case, the entire assembly may then be transported to a location on a lower level such as ground, for example, corresponding to the eventual installation location on the structure. The process is repeated until all assemblies of trough, hangers and deflector have been processed. - Two installers are then employed on ladders or other riser to position each length of assembled trough, hangers, and deflector into place against the structure where the assembly is fastened into place in at least two locations. This is simplified by the feature of the present invention that allows compression fitting of the deflector into the appropriate cavities of
hanger 30. The process of two-installer positioning continues around the structure. One installer takes up a position on the roof of the structure or ladder and completes the affixation of thefasteners 50. This can be readily performed by one person due to the compression fitting ofdeflector 40 that allows opening the assembly to reachfastener 50. Once fasteners for a length of the assembly have been affixed,deflector 40 is compressed to fitflex fold 42 and attachment fold 46 ofdeflector 40 tocavities deflector 40. As the roof or ladder positioned installer proceeds with this procedure of fastener affixation, the second installer forms downspouts and attaches them to the structure. - Although the present invention has been described in detail, it will be apparent to those skilled in the art that the invention may be embodied in a variety of specific forms and that various changes, substitutions and alterations can be made without departing from the spirit and scope of the invention. The described embodiments are only illustrative and not restrictive and the scope of the invention is, therefore, indicated by the following claims.
Claims (8)
Priority Applications (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US10/001,005 US6568132B1 (en) | 2001-06-12 | 2001-11-15 | Diversion system and method |
US10/105,099 US6880294B2 (en) | 2001-06-12 | 2002-03-22 | Diversion system and method |
US10/464,114 US7257933B2 (en) | 2001-06-12 | 2003-06-18 | Diversion system and method |
US11/678,534 US7895869B2 (en) | 2001-06-12 | 2007-02-23 | Diversion system and method |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US09/880,412 US6453622B1 (en) | 2001-06-12 | 2001-06-12 | Diversion system and method |
US09/962,996 US6470628B1 (en) | 2001-06-12 | 2001-09-25 | Diversion system and method |
US10/001,005 US6568132B1 (en) | 2001-06-12 | 2001-11-15 | Diversion system and method |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US09/962,996 Division US6470628B1 (en) | 2001-06-12 | 2001-09-25 | Diversion system and method |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US10/105,099 Continuation US6880294B2 (en) | 2001-06-12 | 2002-03-22 | Diversion system and method |
Publications (2)
Publication Number | Publication Date |
---|---|
US6568132B1 US6568132B1 (en) | 2003-05-27 |
US20030101661A1 true US20030101661A1 (en) | 2003-06-05 |
Family
ID=27128577
Family Applications (4)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US10/001,005 Expired - Lifetime US6568132B1 (en) | 2001-06-12 | 2001-11-15 | Diversion system and method |
US10/105,099 Expired - Lifetime US6880294B2 (en) | 2001-06-12 | 2002-03-22 | Diversion system and method |
US10/464,114 Expired - Lifetime US7257933B2 (en) | 2001-06-12 | 2003-06-18 | Diversion system and method |
US11/678,534 Expired - Fee Related US7895869B2 (en) | 2001-06-12 | 2007-02-23 | Diversion system and method |
Family Applications After (3)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US10/105,099 Expired - Lifetime US6880294B2 (en) | 2001-06-12 | 2002-03-22 | Diversion system and method |
US10/464,114 Expired - Lifetime US7257933B2 (en) | 2001-06-12 | 2003-06-18 | Diversion system and method |
US11/678,534 Expired - Fee Related US7895869B2 (en) | 2001-06-12 | 2007-02-23 | Diversion system and method |
Country Status (1)
Country | Link |
---|---|
US (4) | US6568132B1 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080041008A1 (en) * | 2002-04-03 | 2008-02-21 | Valinge Innovation Ab | Mechanical locking system for floorboards |
US20080134587A1 (en) * | 2006-12-07 | 2008-06-12 | Ealer James E | Gutter protection system having rear compound bend |
USD586436S1 (en) * | 2005-03-03 | 2009-02-10 | Sal Cangialosi | Gutter |
USD586437S1 (en) * | 2006-05-18 | 2009-02-10 | Sal Cangialosi | Gutter |
US20090139180A1 (en) * | 2007-11-30 | 2009-06-04 | Euramax International, Inc. | Water channeling system for gutters |
USD616970S1 (en) | 2009-03-13 | 2010-06-01 | Fiskars Brand, Inc. | Downspout diverter |
US20100270219A1 (en) * | 2009-04-28 | 2010-10-28 | Fiskars Brands, Inc. | Apparatus for diverting rainwater |
US20110126477A1 (en) * | 2009-11-25 | 2011-06-02 | All Clear Gutters, Llc. | Roof gutter system with removable cover |
Families Citing this family (41)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6726155B1 (en) * | 1999-12-01 | 2004-04-27 | Raymond G. Zimmerman | Gutter hanging bracket device with integral fastener retaining guide structure |
US6681527B2 (en) * | 2000-12-11 | 2004-01-27 | Joco Products Llc | Gutter protection system |
US6568132B1 (en) * | 2001-06-12 | 2003-05-27 | A. B. Walters | Diversion system and method |
US6735910B1 (en) * | 2002-01-16 | 2004-05-18 | Douglas Wade Fields | Spring loaded gutter hook |
US20040000098A1 (en) * | 2002-06-28 | 2004-01-01 | Knudson Gary A. | Fastening device, shield and shielded gutter system |
US20040244305A1 (en) * | 2003-04-09 | 2004-12-09 | Larry Hurst | Gutter protection system that utilizes a hidden clip adapted for use with gutters of different sizes and styles |
US7287356B2 (en) * | 2003-09-16 | 2007-10-30 | Sacks Industrial Corp. | Twin track wire lath |
US20050082436A1 (en) * | 2003-10-15 | 2005-04-21 | Todd Snell | Gutter cover hanger apparatus |
US6904718B2 (en) * | 2003-11-07 | 2005-06-14 | Stephen P. Fox | Leaf guard for gutters |
US20060021286A1 (en) * | 2004-07-30 | 2006-02-02 | Saville James L Jr | Dual flow gutter assembly |
US8225556B2 (en) * | 2004-10-19 | 2012-07-24 | Russell Perry Brown | Self cleaning gutter system and gutter bracket |
US7891142B1 (en) | 2004-11-12 | 2011-02-22 | Ealer Sr James E | Gutter protection system |
US7765742B2 (en) * | 2004-11-12 | 2010-08-03 | Ealer Sr James Edward | Gutter cover |
US20060117672A1 (en) * | 2004-12-07 | 2006-06-08 | Kurple William M | Cover for rain gutter |
US20070119104A1 (en) * | 2005-09-23 | 2007-05-31 | Walter Pijanowski | Covered rain gutter system |
US20070234648A1 (en) * | 2006-03-22 | 2007-10-11 | Louis Tombazzi | All in one gutter system |
US20100175331A1 (en) * | 2006-06-19 | 2010-07-15 | Pentti Piri | Roll forming apparatus and method for making a half-round gutter profile, as well as a gutter profile |
US7581356B1 (en) * | 2006-08-01 | 2009-09-01 | Balkum Frank R | Gutter shield |
US7730672B2 (en) * | 2006-11-29 | 2010-06-08 | Knudson Gary A | Integrated debris-shielding cover, flashing & mounting system for rain gutter |
US7650720B2 (en) * | 2006-12-04 | 2010-01-26 | Ealer Sr James E | Perforated gutter protection system having canals |
US20090183438A1 (en) * | 2008-01-22 | 2009-07-23 | William Lloyd Walker | Debris removal gutter system |
IE20090126A1 (en) * | 2008-02-28 | 2009-09-16 | Kingspan Res & Dev Ltd | An insulated gutter |
EP2177685B1 (en) * | 2008-10-17 | 2011-12-14 | Guy Brochu | Eavestrough cover for half round eavestroughs |
US9243386B2 (en) * | 2009-02-09 | 2016-01-26 | Seattle Tarp Company | System and method for collecting rain water |
US8075765B2 (en) * | 2009-02-09 | 2011-12-13 | Seattle Tarp Company | Rain water collection system components and method of fabrication |
US8554307B2 (en) * | 2010-04-12 | 2013-10-08 | Inneroptic Technology, Inc. | Image annotation in image-guided medical procedures |
US8176687B2 (en) * | 2009-04-03 | 2012-05-15 | Roque Alonso Ramon R | Gutter system and associated methods |
US20110232203A1 (en) * | 2010-03-24 | 2011-09-29 | M.I.C. Industries, Inc. | System and method for attaching a wall to a building structure |
US8997403B1 (en) * | 2011-02-16 | 2015-04-07 | Mark S Steinberg | Covered rain gutter assembly |
US8402697B1 (en) | 2012-10-05 | 2013-03-26 | James E. Ealer, Sr. | Gutter cover with rear compound bend |
USD722682S1 (en) | 2013-05-14 | 2015-02-17 | Stephen P. Fox | Rain gutter cover |
US9708816B2 (en) | 2014-05-30 | 2017-07-18 | Sacks Industrial Corporation | Stucco lath and method of manufacture |
US9752323B2 (en) | 2015-07-29 | 2017-09-05 | Sacks Industrial Corporation | Light-weight metal stud and method of manufacture |
USD831175S1 (en) | 2016-08-30 | 2018-10-16 | Billy J. Jackson | Rain gutter cover insert |
US9797142B1 (en) | 2016-09-09 | 2017-10-24 | Sacks Industrial Corporation | Lath device, assembly and method |
US10814372B2 (en) * | 2017-06-07 | 2020-10-27 | Kwm Gutterman Inc. | Method for strategically marking a gutter |
WO2019033197A1 (en) | 2017-08-14 | 2019-02-21 | Sacks Industrial Corporation | Varied length metal studs |
US11351593B2 (en) | 2018-09-14 | 2022-06-07 | Structa Wire Ulc | Expanded metal formed using rotary blades and rotary blades to form such |
JP7608764B2 (en) * | 2020-09-30 | 2025-01-07 | 積水ハウス株式会社 | Eaves gutter |
US12252884B2 (en) | 2021-03-30 | 2025-03-18 | Independence Materials Group, Llc | Gutter system having a gutter, bracket, and cover, and method of installing the gutter system |
US12037792B2 (en) | 2021-05-26 | 2024-07-16 | Independence Materials Group, Llc | Gutter cover, gutter system using the gutter cover, and method of installing the gutter cover |
Family Cites Families (78)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US603611A (en) | 1898-05-03 | Eaves-trough | ||
US836012A (en) | 1906-07-13 | 1906-11-13 | George Cassen | Eaves-trough. |
US891405A (en) | 1907-12-11 | 1908-06-23 | George Cassens | Eaves-trough. |
US891406A (en) | 1907-12-11 | 1908-06-23 | George Cassens | Eaves-trough. |
US2636458A (en) | 1948-03-18 | 1953-04-28 | Paul D Hoel | Drain trough cover |
US2536704A (en) | 1949-09-01 | 1951-01-02 | James B Shea | Support and hanger for eaves trough and gutters |
US2672832A (en) | 1951-01-12 | 1954-03-23 | Alfred K Goetz | Eaves trough |
US2649890A (en) * | 1952-04-02 | 1953-08-25 | Dunlap | Machine and method for producing corner beads for use in dry-built construction |
US2669950A (en) | 1952-10-08 | 1954-02-23 | George A Bartholomew | Nonclogging eaves structure |
US2873700A (en) | 1953-08-28 | 1959-02-17 | Henry C Heier | Shielded eaves troughs |
US3080682A (en) | 1960-02-09 | 1963-03-12 | Teutsch John Herman | Eaves trough construction |
US3189304A (en) | 1961-12-26 | 1965-06-15 | Louis M Vranyosovics | Gutter hanger |
US3752428A (en) | 1971-06-10 | 1973-08-14 | Aluminum Co Of America | Gutter hanger assembly |
US3840960A (en) * | 1971-09-09 | 1974-10-15 | A Toti | Apparatus for forming a structural unit |
CA955472A (en) * | 1972-02-24 | 1974-10-01 | Dan B. Davis | Registering of transversely corrugated elements |
JPS5118501B2 (en) * | 1972-06-06 | 1976-06-10 | ||
US4000587A (en) | 1975-02-05 | 1977-01-04 | Weber William H | Gutter structure |
US4059215A (en) * | 1975-09-05 | 1977-11-22 | Lamons Metal Gasket Company | Circular double-jacketed gasket with single joint |
US4435925A (en) | 1976-03-18 | 1984-03-13 | Jefferys Henry J | Shield for eaves drain gutter |
US4020666A (en) * | 1976-04-15 | 1977-05-03 | Beymer Glen E | Mobile forming machine with embossing rolls |
US4161811A (en) * | 1978-03-13 | 1979-07-24 | James Nyssen | Method and apparatus for the manufacture of reinforced smooth flow pipe |
US4195452A (en) | 1979-02-02 | 1980-04-01 | Clyde Grayum | Gutter and hanger arrangement |
US4199121A (en) | 1979-03-28 | 1980-04-22 | Le Febvre Alfred F | Invertible rain gutter mounting apparatus |
US4333208A (en) | 1979-07-09 | 1982-06-08 | Fuller Ernest H | Gutter guard clip and method of manufacture |
US4294422A (en) | 1979-09-24 | 1981-10-13 | Odekirk William H | Gutter hanger |
US4241548A (en) | 1979-11-27 | 1980-12-30 | Rowe Lacy A | Gutter hanger |
JPS56102302A (en) * | 1980-01-21 | 1981-08-15 | Hitachi Cable Ltd | Manufacture of long sized metallic shape |
US4404775A (en) | 1980-10-20 | 1983-09-20 | Demartini Robert J | Rain gutter devices |
US4493588A (en) | 1981-09-21 | 1985-01-15 | Duffy Gifford R | Non-clogging eaves trough |
US4411110A (en) | 1981-11-09 | 1983-10-25 | Carey Robert J | Rain gutter |
US4433512A (en) | 1982-03-24 | 1984-02-28 | Schoener Harry E | Reinforced gutter hanger supporting bar |
JPS6064729A (en) * | 1983-09-21 | 1985-04-13 | Hitachi Ltd | feed leveler |
US4592174A (en) | 1985-01-22 | 1986-06-03 | John Hileman | Gutter protector |
US4757649A (en) | 1987-04-27 | 1988-07-19 | Yoder Manufacturing | Leaf rejecting rain gutter |
US4776544A (en) | 1987-06-19 | 1988-10-11 | Williams Robert M | Gutter hanger |
US5285567A (en) * | 1988-10-12 | 1994-02-15 | Barracuda Technologies Ab | Machine for applying fastener devices |
US4876827A (en) | 1989-01-03 | 1989-10-31 | Williams Robert D | Gutter assembly |
US4941299A (en) | 1989-03-17 | 1990-07-17 | Sweers Ronald L | Guard screen for a rain gutter |
US4951430A (en) | 1989-09-11 | 1990-08-28 | David Gottlieb | Removable gutter and fastener system |
US5098045A (en) | 1989-10-13 | 1992-03-24 | Bemis Manufacturing Company | Concealed gutter hanger |
US5007224A (en) | 1990-04-26 | 1991-04-16 | Segneri Carl L | Tool and method for installing roof gutters on buildings |
US5040750A (en) | 1990-05-01 | 1991-08-20 | Gsw Inc. | Eavestrough hook and leaf guard |
US5072551A (en) | 1991-01-23 | 1991-12-17 | Manoogian Jr Sarkis | Gutter guard |
US5375379A (en) | 1991-12-23 | 1994-12-27 | Meckstroth; Alan F. | Leaf deflecting cover device for a rain gutter |
US5245800A (en) | 1992-01-31 | 1993-09-21 | Davenport Ralph G | Gutter end cap |
US5253456A (en) | 1992-03-16 | 1993-10-19 | Raingard Of Alabama, Inc. | Endcap for rain gutters |
US5271192A (en) | 1992-05-06 | 1993-12-21 | Nothum Sr Alfred | Gutter hanger and screen assembly |
CA2077109C (en) * | 1992-08-28 | 1995-12-12 | George A. Morandin | Eavestrough system |
US5356164A (en) | 1993-05-20 | 1994-10-18 | Miller Chase E | Seamless gutter rolling support |
US5491998A (en) * | 1993-06-09 | 1996-02-20 | Hansen; Harry | Method of making a leaf rejecting rain gutter |
US5394722A (en) | 1993-08-17 | 1995-03-07 | Meyer; Bruce E. | Apparatus for forming profiles on strip materials |
US5388377A (en) | 1993-10-18 | 1995-02-14 | Faulkner; Charles L. | Gutter assembly for roofs |
US5457916A (en) | 1993-11-19 | 1995-10-17 | Tenute; Steven J. | Rain gutter protection device |
US5570860A (en) | 1994-02-23 | 1996-11-05 | James R. Jay, Jr. | Gutter bracket |
FI964194L (en) | 1994-04-20 | 1996-10-18 | Knudson Gary Art | Device for making a semicircular gutter |
US5537785A (en) | 1994-05-05 | 1996-07-23 | Zmc, Inc. | Fascia/gutter with channel |
US5555680A (en) | 1994-12-22 | 1996-09-17 | Sweers; Ronald L. | Guard screen for a rain gutter having flanges for gripping the front lip of a gutter |
EP0817897A4 (en) | 1995-03-27 | 1999-08-04 | Knudson Gary Art | SUPPORT FASTENING FOR PROTECTED GUTTERS |
US5640809A (en) | 1995-03-29 | 1997-06-24 | Iannelli; Anthony M. | Rain gutter shield |
US5740687A (en) | 1995-04-21 | 1998-04-21 | New Tech Machinery Corporation | Forming apparatus for strip materials |
US5575118A (en) | 1995-04-24 | 1996-11-19 | Vahldieck; Wayne | Eaves trough assembly |
US5687938A (en) * | 1995-05-26 | 1997-11-18 | Bailey; Michael E. | Adjustable pipe brace |
US5638643A (en) | 1995-05-30 | 1997-06-17 | Demartini; Robert J. | New and useful improvements in rain gutter devices and methods of making same |
US5687936A (en) | 1995-06-07 | 1997-11-18 | Wilson; Dennis E. | Gutter bracket |
US5572118A (en) * | 1995-06-29 | 1996-11-05 | Mks Instruments, Inc. | Charge rate electrometer including means for substantially eliminating leakage currents |
US5619825A (en) | 1996-01-24 | 1997-04-15 | Leroney; David W. | Gutter screen |
US5893240A (en) | 1996-02-12 | 1999-04-13 | Ealer, Sr.; James Edward | Gutter screen |
US5875590A (en) | 1997-03-19 | 1999-03-02 | Udelle; Steven D. | Raingutter leaf guard and cleaning device |
US5737879A (en) | 1997-03-31 | 1998-04-14 | Sweet; Vernon L. | Debris blocking gutter and support hanger |
US6151836A (en) * | 1997-10-30 | 2000-11-28 | Mcglothlin; W. Neal | Gutter system |
US6161338A (en) | 1998-04-02 | 2000-12-19 | Kuhns; Richard L. | Rain gutter covers and roof line protectors |
US6073398A (en) | 1998-07-28 | 2000-06-13 | Williams; Paul A. | Gutter cover |
US6254039B1 (en) | 1998-12-30 | 2001-07-03 | Raymond G. Zimmerman | Gutter hanging bracket device with rigidity augmenting U-shaped cross-sectional channel construction |
US6209826B1 (en) | 1999-03-26 | 2001-04-03 | John M. Pratt, Jr. | Gutter hanger assembly |
US6568132B1 (en) * | 2001-06-12 | 2003-05-27 | A. B. Walters | Diversion system and method |
US6453622B1 (en) * | 2001-06-12 | 2002-09-24 | Senox Corporation | Diversion system and method |
SE520880C2 (en) * | 2001-06-21 | 2003-09-09 | Accra Teknik Ab | Device and method of manufacture of vehicle beams |
US6915935B2 (en) * | 2002-07-02 | 2005-07-12 | Arkady Portnoy | Sheet dispensing system for rolled materials |
-
2001
- 2001-11-15 US US10/001,005 patent/US6568132B1/en not_active Expired - Lifetime
-
2002
- 2002-03-22 US US10/105,099 patent/US6880294B2/en not_active Expired - Lifetime
-
2003
- 2003-06-18 US US10/464,114 patent/US7257933B2/en not_active Expired - Lifetime
-
2007
- 2007-02-23 US US11/678,534 patent/US7895869B2/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080041008A1 (en) * | 2002-04-03 | 2008-02-21 | Valinge Innovation Ab | Mechanical locking system for floorboards |
USD586436S1 (en) * | 2005-03-03 | 2009-02-10 | Sal Cangialosi | Gutter |
USD586437S1 (en) * | 2006-05-18 | 2009-02-10 | Sal Cangialosi | Gutter |
US20080134587A1 (en) * | 2006-12-07 | 2008-06-12 | Ealer James E | Gutter protection system having rear compound bend |
US20090139180A1 (en) * | 2007-11-30 | 2009-06-04 | Euramax International, Inc. | Water channeling system for gutters |
USD616970S1 (en) | 2009-03-13 | 2010-06-01 | Fiskars Brand, Inc. | Downspout diverter |
US20100270219A1 (en) * | 2009-04-28 | 2010-10-28 | Fiskars Brands, Inc. | Apparatus for diverting rainwater |
US8033058B2 (en) | 2009-04-28 | 2011-10-11 | Fiskars Brands, Inc. | Apparatus for diverting rainwater |
US8404110B2 (en) | 2009-04-28 | 2013-03-26 | Fiskars Brands, Inc. | Apparatus for diverting rainwater |
US20110126477A1 (en) * | 2009-11-25 | 2011-06-02 | All Clear Gutters, Llc. | Roof gutter system with removable cover |
Also Published As
Publication number | Publication date |
---|---|
US6568132B1 (en) | 2003-05-27 |
US6880294B2 (en) | 2005-04-19 |
US7895869B2 (en) | 2011-03-01 |
US20030029129A1 (en) | 2003-02-13 |
US20040025445A1 (en) | 2004-02-12 |
US7257933B2 (en) | 2007-08-21 |
US20070130842A1 (en) | 2007-06-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6880294B2 (en) | Diversion system and method | |
US6470628B1 (en) | Diversion system and method | |
US4631875A (en) | Gutter assembly and method of installation | |
US6073398A (en) | Gutter cover | |
EP2826927B1 (en) | Gutter cover system | |
US6658796B1 (en) | Gutter hood support bracket | |
US6701674B1 (en) | Snap-on installation gutter protection system, with mounting bracket, and method of use | |
US8528262B2 (en) | Gutter-locking gutter protection | |
US20090139180A1 (en) | Water channeling system for gutters | |
US20080047206A1 (en) | Gutter retaining system | |
US20120285115A1 (en) | Method of Installing a Metal Gutter Cover | |
US9404266B2 (en) | Covered gutter system | |
US5819476A (en) | Gutter cover mounting clips | |
US12129654B2 (en) | Eavestrough debris guard | |
US7246474B2 (en) | Metal shingle system | |
US20100126078A1 (en) | Removable downspout for a gutter system | |
US20140202086A1 (en) | Gutter protection system | |
US7958677B2 (en) | Gutter retaining system | |
AU2023202610B2 (en) | Gutter assembly | |
US20140069027A1 (en) | Gutter Protection System | |
AU2002314956A1 (en) | Diversion system and method | |
EP0340856A2 (en) | Roof ventilation | |
US20040211125A1 (en) | Assembly clip for a rain gutter deflector | |
AU735006B2 (en) | Rainwater products | |
US10619352B1 (en) | Rain gutter for tin roof or the like |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STCF | Information on status: patent grant |
Free format text: PATENTED CASE |
|
CC | Certificate of correction | ||
CC | Certificate of correction | ||
FEPP | Fee payment procedure |
Free format text: PAYER NUMBER DE-ASSIGNED (ORIGINAL EVENT CODE: RMPN); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY Free format text: PAYOR NUMBER ASSIGNED (ORIGINAL EVENT CODE: ASPN); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY |
|
FPAY | Fee payment |
Year of fee payment: 4 |
|
FEPP | Fee payment procedure |
Free format text: PAYER NUMBER DE-ASSIGNED (ORIGINAL EVENT CODE: RMPN); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY Free format text: PAYOR NUMBER ASSIGNED (ORIGINAL EVENT CODE: ASPN); ENTITY STATUS OF PATENT OWNER: SMALL ENTITY |
|
FPAY | Fee payment |
Year of fee payment: 8 |
|
SULP | Surcharge for late payment |
Year of fee payment: 7 |
|
FPAY | Fee payment |
Year of fee payment: 12 |