+

CN115967120B - 220 KV power grid on-line transformer substation judging method and capacity-to-load ratio calculating method - Google Patents

220 KV power grid on-line transformer substation judging method and capacity-to-load ratio calculating method Download PDF

Info

Publication number
CN115967120B
CN115967120B CN202310034718.1A CN202310034718A CN115967120B CN 115967120 B CN115967120 B CN 115967120B CN 202310034718 A CN202310034718 A CN 202310034718A CN 115967120 B CN115967120 B CN 115967120B
Authority
CN
China
Prior art keywords
substation
load
transformer substation
power
maximum load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202310034718.1A
Other languages
Chinese (zh)
Other versions
CN115967120A (en
Inventor
谢宇峥
章德
严勇华
张斌
侯彦若
谢国恒
卢平江
苏筱凡
张睿琪
周雨桦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Hunan Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
State Grid Hunan Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Hunan Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Hunan Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical State Grid Hunan Electric Power Co Ltd
Priority to CN202310034718.1A priority Critical patent/CN115967120B/en
Publication of CN115967120A publication Critical patent/CN115967120A/en
Application granted granted Critical
Publication of CN115967120B publication Critical patent/CN115967120B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a 220 KV power grid on-line substation judging method, which comprises the steps of obtaining substation data information of a 220 KV regional power grid; calculating the ratio of the power on the network to the power off the network of the transformer substation, and the probability of new energy or conventional power supply power; and judging the online substation according to the data information and the selected maximum load time period. The invention also discloses a capacity-to-load ratio calculation method comprising the 220 KV power grid on-line substation judgment method. According to the invention, different factors are comprehensively considered so as to judge whether the transformer substation belongs to an internet-surfing transformer substation or not; therefore, the invention has high reliability, good accuracy and higher efficiency; meanwhile, the invention can provide accurate data reference for the calculation process of the capacity-to-load ratio, so that the calculation process of the capacity-to-load ratio is more accurate and reliable.

Description

220千伏电网上网变电站判定方法及容载比计算方法220 kV grid-connected substation determination method and capacity load ratio calculation method

技术领域Technical Field

本发明属于电气自动化技术领域,具体涉及一种220千伏电网上网变电站判定方法及容载比计算方法。The present invention belongs to the technical field of electrical automation, and in particular relates to a method for determining a 220 kV grid-connected substation and a method for calculating a capacity-load ratio.

背景技术Background Art

随着经济技术的发展和人们生活水平的提高,电能已经成为了人们生产和生活中必不可少的二次能源,给人们的生产和生活带来了无尽的便利。因此,保障电能的稳定可靠供应,就成为了电力系统最重要的任务之一。With the development of economy and technology and the improvement of people's living standards, electricity has become an indispensable secondary energy source in people's production and life, bringing endless convenience to people's production and life. Therefore, ensuring the stable and reliable supply of electricity has become one of the most important tasks of the power system.

目前,随着新能源发电系统的迅速发展,新能源发电系统开始大规模并入110千伏及以下电压等级电网,在新能源富集区域,新能源大规模并网将导致新能源通过220千伏变电站主变上送至上级电网,此时该变电站主要承担上送新能源电力的任务,而非负荷供带作用。因此在分析地区负荷供带能力时,需要计算220千伏区域电网下网容载比,也即需要合理确定该区域计算时刻下网220千伏变电容量。因此,如何准确剔除220千伏变电站中主要承担上送电力任务的变电站,即对220千伏电网上网变电站进行判定,对准确计算该区域220千伏下网容载比具有十分重要的意义。At present, with the rapid development of new energy power generation systems, new energy power generation systems have begun to be integrated into 110 kV and below voltage level power grids on a large scale. In new energy-rich areas, large-scale grid connection of new energy will lead to the transmission of new energy to the upper grid through the main transformer of the 220 kV substation. At this time, the substation mainly undertakes the task of transmitting new energy electricity, rather than the load supply function. Therefore, when analyzing the regional load supply capacity, it is necessary to calculate the 220 kV regional power grid offline capacity-load ratio, that is, it is necessary to reasonably determine the 220 kV substation capacity of the region at the time of calculation. Therefore, how to accurately eliminate the substations that mainly undertake the task of transmitting electricity in the 220 kV substation, that is, to determine the 220 kV grid-connected substations, is of great significance for accurately calculating the 220 kV offline capacity-load ratio in the region.

但是,现在在进行220千伏区域电网下网容载比的计算过程中,并没有考虑到上述的特殊情况,即剔除220千伏变电站中主要承担上送电力任务的变电站,或者对220千伏电网上网变电站进行判定。因此,现有技术并未对220千伏电网上网变电站进行判定;这使得现有的容载比计算方案,将导致计算出的下网容载比过大或过小,无法真实、准确地反映电网在电力供应方面存在的问题。However, in the current calculation process of the offline capacity-load ratio of the 220 kV regional power grid, the above-mentioned special situation is not taken into account, that is, the substations that are mainly responsible for the task of sending power in the 220 kV substations are excluded, or the 220 kV grid-connected substations are not judged. Therefore, the existing technology does not judge the 220 kV grid-connected substations; this makes the existing capacity-load ratio calculation scheme lead to the calculated offline capacity-load ratio being too large or too small, and cannot truly and accurately reflect the problems existing in the power supply of the grid.

发明内容Summary of the invention

本发明的目的之一在于提供一种可靠性高、精确性好且效率较高的220千伏电网上网变电站判定方法。One of the purposes of the present invention is to provide a method for determining a 220 kV grid-connected substation with high reliability, good accuracy and high efficiency.

本发明的目的之二在于提供一种包括了所述220千伏电网上网变电站判定方法的容载比计算方法。A second object of the present invention is to provide a method for calculating the capacity-load ratio that includes the method for determining a 220 kV grid-connected substation.

本发明提供的这种220千伏电网上网变电站判定方法,包括如下步骤:The 220 kV power grid on-grid substation determination method provided by the present invention comprises the following steps:

S1.获取220千伏区域电网的变电站数据信息;S1. Obtain substation data information of 220 kV regional power grid;

S2.根据步骤S1获取的数据信息,计算变电站的上网电量与下网电量的比值以及出现上送新能源或常规电源电力的概率;S2. According to the data information obtained in step S1, the ratio of the on-grid power of the substation to the off-grid power and the probability of sending new energy or conventional power are calculated;

S3.根据步骤S2计算得到的数据信息和选定的最大负荷时段,对上网变电站进行判定。S3. According to the data information calculated in step S2 and the selected maximum load period, the grid-connected substation is determined.

步骤S2所述的根据步骤S1获取的数据信息,计算变电站的上网电量与下网电量的比值以及出现上送新能源或常规电源电力的概率,具体包括如下步骤:Step S2, according to the data information obtained in step S1, calculates the ratio of the on-grid power to the off-grid power of the substation and the probability of sending up new energy or conventional power, which specifically includes the following steps:

基于当前变电站上一年的8760运行小时数据,统计当前变电站上一年的全年上网电量Pi≤0和下网电量Pi>0,其中Wup为上网电量,ΔT为时间段的长度,Pi为变电站在第i小时的功率,且Pi≤0表示变电站上送电力,Pi>0表示变电站正常供带负荷;Based on the 8760 operating hours data of the current substation last year, the annual online power consumption of the current substation last year is counted P i ≤ 0 and off-grid power P i > 0, where W up is the amount of electricity online, ΔT is the length of the time period, P i is the power of the substation at the i-th hour, and P i ≤ 0 means that the substation is sending electricity, and P i > 0 means that the substation is supplying load normally;

计算当前变电站的上网电量与下网电量的比值η为 The ratio of the current on-grid power to the off-grid power of the substation is calculated as

计算当前变电站上送新能源或常规电源电力的概率p为Pi≤0且i∈(1,35040),其中Nup,year为全年当前变电站运行数据中负荷小于0的个数,Nyear为全年当前变电站运行数据点的总个数。Calculate the probability p of the current substation sending new energy or conventional power supply power as follows: P i ≤ 0 and i∈(1,35040), where N up,year is the number of loads less than 0 in the current substation operation data throughout the year, and N year is the total number of current substation operation data points throughout the year.

步骤S3所述的根据步骤S2计算得到的数据信息和选定的最大负荷时段,对上网变电站进行判定,具体包括如下步骤:Step S3, according to the data information calculated in step S2 and the selected maximum load period, determines the grid-connected substation, specifically including the following steps:

根据步骤S2得到的变电站的上网电量与下网电量的比值η和变电站上送新能源或常规电源电力的概率p,对上网变电站进行判定;According to the ratio η of the grid-connected power to the grid-connected power of the substation obtained in step S2 and the probability p of the substation transmitting renewable energy or conventional power, the grid-connected substation is determined;

选定最大负荷时段,计算最大负荷时段内当前变电站的净上网电量、最大负荷时段内变电站上送电力的概率和最大负荷时段内最大上送功率与最大下送功率的比值,从而对上网变电站进行判定;Select the maximum load period, calculate the net grid-connected power of the current substation during the maximum load period, the probability of the substation sending power during the maximum load period, and the ratio of the maximum up-sending power to the maximum down-sending power during the maximum load period, so as to determine the grid-connected substation;

当当前变电站接入的电源装机容量大于或等于当前变电站最大负荷时,根据负荷与变电站最大负荷之间的关系以及最大负荷时段内地区负荷与地区最大负荷之间的关系,对上网变电站进行判定。When the installed capacity of the power source connected to the current substation is greater than or equal to the current maximum load of the substation, the grid-connected substation is judged based on the relationship between the load and the maximum load of the substation and the relationship between the regional load and the regional maximum load during the maximum load period.

所述的根据步骤S2得到的变电站的上网电量与下网电量的比值η和变电站上送新能源或常规电源电力的概率p,对上网变电站进行判定,具体包括如下步骤:The determination of the grid-connected substation based on the ratio η of the grid-connected power to the grid-connected power obtained in step S2 and the probability p of the substation transmitting renewable energy or conventional power is specifically performed including the following steps:

采用如下规则进行判断:The following rules are used for judgment:

若η≥1且p>0.5,则表示当前变电站全年上网电量大于下网电量,且全年上网运行概率大于下网运行概率,则判定当前变电站为上网变电站;If η≥1 and p>0.5, it means that the current substation’s annual online power generation is greater than the offline power generation, and the annual online operation probability is greater than the offline operation probability, then the current substation is determined to be an online substation;

若η<1或η>1,且p<0.5,则判定当前变电站为下网变电站。If η<1 or η>1, and p<0.5, the current substation is determined to be a grid-connected substation.

所述的选定最大负荷时段,计算最大负荷时段内当前变电站的净上网电量、最大负荷时段内变电站上送电力的概率和最大负荷时段内最大上送功率与最大下送功率的比值,从而对上网变电站进行判定,具体包括如下步骤:The selected maximum load period, calculating the net grid-connected power of the current substation during the maximum load period, the probability of the substation sending power during the maximum load period, and the ratio of the maximum sending power to the maximum sending power during the maximum load period, so as to determine the grid-connected substation, specifically includes the following steps:

选取最大负荷,并以最大为分界点,前后各取X天的时间,总计2X天的时间作为最大负荷段;X为设定的实数;Select the maximum load and take the maximum as the dividing point, take X days before and after, and a total of 2X days as the maximum load segment; X is a set real number;

计算在最大负荷时段内当前变电站净上网电量WN,up其中Pi为变电站在第i小时的功率;Calculate the net on-grid power of the current substation during the maximum load period W N,up Where Pi is the power of the substation at the i-th hour;

计算最大负荷时段内变电站上送电力的概率p为Pi≤0;其中Nup为数据小于0时的个数,此时表示变电站上送电力;N为最大负荷时段内变电站采集的数据点个数;The probability p of the substation transmitting power during the maximum load period is calculated as P i ≤0; N up is the number of data points less than 0, which indicates that the substation is transmitting power; N is the number of data points collected by the substation during the maximum load period;

计算最大负荷时段内最大上送功率与最大下送功率的比值α为其中Pi,up,max为最大负荷时段内变电站最大上送功率;Pi,down,max为最大负荷时段内变电站最大下送功率;The ratio α of the maximum uplink power to the maximum downlink power during the maximum load period is calculated as Where P i,up,max is the maximum up-transmission power of the substation during the maximum load period; P i,down,max is the maximum down-transmission power of the substation during the maximum load period;

采用如下规则进行判断:The following rules are used for judgment:

若p>0.5且WN,up<0,则判定当前变电站为上网变电站;If p>0.5 and W N,up <0, the current substation is determined to be an on-grid substation;

若p>0.5且α>1,则判定当前变电站为上网变电站。If p>0.5 and α>1, the current substation is determined to be an on-grid substation.

所述的当当前变电站接入的电源装机容量大于或等于当前变电站最大负荷时,根据负荷与变电站最大负荷之间的关系以及最大负荷时段内地区负荷与地区最大负荷之间的关系,对上网变电站进行判定,具体包括如下步骤:When the installed capacity of the power source connected to the current substation is greater than or equal to the maximum load of the current substation, the on-grid substation is determined according to the relationship between the load and the maximum load of the substation and the relationship between the regional load and the regional maximum load during the maximum load period, specifically including the following steps:

基于历史运行数据,在最大负荷时段内获取当前地区负荷Pload,j大于地区最大负荷Pload,max的Y%的时刻,Pload,j≥0.85Pload,max,j∈(1,N1);然后,得到当前变电站在对应第j个时刻的负荷Pj,并获取负荷Pj与变电站最大负荷的10%之间的关系,Pj≤0或者Pj≤0.1Pload,station,max,j∈(1,N2);其中,Pload,station,max为当前变电站可供带的最大负荷;N1为在最大负荷时段内获取当前地区负荷Pload,j大于地区最大负荷Pload,max的Y%的时刻的数据个数;N2为满足Pj≤0或者Pj≤0.1Pload,station,max的数据个数;Based on the historical operation data, obtain the moment when the current regional load P load,j is greater than Y% of the regional maximum load P load,max during the maximum load period, P load,j ≥0.85P load,max ,j∈(1,N 1 ); then, obtain the load P j of the current substation at the corresponding j-th moment, and obtain the relationship between the load P j and 10% of the maximum load of the substation, P j ≤0 or P j ≤0.1P load,station,max ,j∈(1,N 2 ); where P load,station,max is the maximum load that the current substation can carry; N 1 is the number of data at which the current regional load P load,j is greater than Y% of the regional maximum load P load,max during the maximum load period; N 2 is the number of data satisfying P j ≤0 or P j ≤0.1P load,station,max ;

计算概率p为Pj≤0或者Pj≤0.1Pload,station,maxCalculate the probability p as P j ≤0 or P j ≤0.1P load,station,max ;

采用如下规则进行判断:The following rules are used for judgment:

若p>0.5,则判定当前变电站为上网变电站。If p>0.5, the current substation is determined to be an on-grid substation.

本发明还提供了一种包括了所述220千伏电网上网变电站判定方法的容载比计算方法,具体包括如下步骤:The present invention also provides a method for calculating the capacity-load ratio including the method for determining a 220 kV grid-connected substation, which specifically includes the following steps:

A.采用所述的220千伏电网上网变电站判定方法,对区域内的上网变电站进行排定;A. Using the above-mentioned 220 kV grid-connected substation determination method, the grid-connected substations in the area are scheduled;

B.在计算区域220千伏下网容载比时,剔除步骤A得到的上网变电站的容量;B. When calculating the regional 220 kV grid capacity-load ratio, exclude the capacity of the grid-connected substation obtained in step A;

C.根据步骤B得到的数据信息,计算220千伏区域电网的下网容载比。C. Based on the data information obtained in step B, calculate the off-grid capacity load ratio of the 220 kV regional power grid.

步骤B所述的在计算区域220千伏下网容载比时,剔除步骤A得到的上网变电站的容量,具体包括如下步骤:When calculating the regional 220 kV grid-connected capacity-load ratio in step B, the capacity of the grid-connected substation obtained in step A is eliminated, which specifically includes the following steps:

剔除步骤A得到的上网变电站的容量;Eliminate the capacity of the grid-connected substation obtained in step A;

在计算区域220千伏下网容载比时,剔除以高耗能用户为主的变电站;所述的以高耗能用户为主的变电站,包括以炼铁行业和电解铝行业为用户的变电站。When calculating the regional 220 kV grid capacity load ratio, substations that are mainly used by high-energy-consuming users are eliminated; the substations that are mainly used by high-energy-consuming users include substations that serve the iron and steelmaking industries and the electrolytic aluminum industry.

本发明提供的这种220千伏电网上网变电站判定方法及容载比计算方法,考虑变电站全年的上网电量、下网电量、上网电量与下网电量的比值、出现变电站上送新能源或常规电源电力的概率、变电站在该地区最大负荷时段出现上送电力的情况及概率、变电站接入的电源装机容量大于等于该变电站最大负荷时该变电站在地区负荷大于地区最大负荷85%时电力上送情况以及高耗能用户为主的变电站负荷特性约束等方面,综合考虑不同因素进而判断出该变电站是否属于上网变电站;因此本发明的可靠性高、精确性好且效率较高;同时本发明能够为容载比计算过程提供准确的数据参考,使得容载比的计算过程更加准确可靠。The 220 kV grid-connected substation determination method and load-to-capacity ratio calculation method provided by the present invention take into account the grid-connected power, grid-offline power, the ratio of grid-connected power to grid-offline power of the substation throughout the year, the probability of the substation sending new energy or conventional power, the situation and probability of the substation sending power during the maximum load period in the region, the power sending situation of the substation when the regional load is greater than 85% of the regional maximum load when the installed capacity of the power source connected to the substation is greater than or equal to the maximum load of the substation, and the load characteristic constraints of the substation dominated by high-energy-consuming users, etc., comprehensively consider different factors to determine whether the substation belongs to the grid-connected substation; therefore, the present invention has high reliability, good accuracy and high efficiency; at the same time, the present invention can provide accurate data reference for the load-to-capacity ratio calculation process, so that the load-to-capacity ratio calculation process is more accurate and reliable.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为本发明判定方法的方法流程示意图。FIG. 1 is a schematic diagram of a flow chart of a determination method of the present invention.

图2为本发明容载比计算方法的方法流程示意图。FIG. 2 is a schematic diagram of a method flow chart of a method for calculating a capacity-load ratio according to the present invention.

具体实施方式DETAILED DESCRIPTION

如图1所示为本发明判定方法的方法流程示意图:本发明提供的这种220千伏电网上网变电站判定方法,包括如下步骤:FIG1 is a schematic diagram of a method flow chart of the determination method of the present invention: The 220 kV grid-connected substation determination method provided by the present invention comprises the following steps:

S1.获取220千伏区域电网的变电站数据信息;S1. Obtain substation data information of 220 kV regional power grid;

S2.根据步骤S1获取的数据信息,计算变电站的上网电量与下网电量的比值以及出现上送新能源或常规电源电力的概率;具体包括如下步骤:S2. According to the data information obtained in step S1, the ratio of the on-grid power to the off-grid power of the substation and the probability of sending new energy or conventional power are calculated; specifically, the steps include:

基于当前变电站上一年的8760运行小时数据,统计当前变电站上一年的全年上网电量Pi≤0和下网电量Pi>0,其中Wup为上网电量,ΔT为时间段的长度,Pi为变电站在第i小时的功率,且Pi≤0表示变电站上送电力,Pi>0表示变电站正常供带负荷;Based on the 8760 operating hours data of the current substation last year, the annual online power consumption of the current substation last year is counted P i ≤ 0 and off-grid power P i > 0, where W up is the amount of electricity online, ΔT is the length of the time period, P i is the power of the substation at the i-th hour, and P i ≤ 0 means that the substation is sending electricity, and P i > 0 means that the substation is supplying load normally;

计算当前变电站的上网电量与下网电量的比值η为 The ratio of the current on-grid power to the off-grid power of the substation is calculated as

计算当前变电站上送新能源或常规电源电力的概率p为Pi≤0且i∈(1,35040),其中Nup,year为全年当前变电站运行数据中负荷小于0的个数,Nyear为全年当前变电站运行数据点的总个数;Calculate the probability p of the current substation sending new energy or conventional power supply power as follows: P i ≤ 0 and i∈(1,35040), where N up,year is the number of loads less than 0 in the current substation operation data throughout the year, and N year is the total number of current substation operation data points throughout the year;

S3.根据步骤S2计算得到的数据信息和选定的最大负荷时段,对上网变电站进行判定;具体包括如下步骤:S3. According to the data information calculated in step S2 and the selected maximum load period, the grid-connected substation is determined; specifically comprising the following steps:

根据步骤S2得到的变电站的上网电量与下网电量的比值η和变电站上送新能源或常规电源电力的概率p,对上网变电站进行判定;具体包括如下步骤:According to the ratio η of the grid-connected power of the substation to the grid-connected power obtained in step S2 and the probability p of the substation transmitting renewable energy or conventional power, the grid-connected substation is determined; specifically, the following steps are included:

采用如下规则进行判断:The following rules are used for judgment:

若η≥1且p>0.5,则表示当前变电站全年上网电量大于下网电量,且全年上网运行概率大于下网运行概率,则判定当前变电站为上网变电站;If η≥1 and p>0.5, it means that the current substation’s annual online power generation is greater than the offline power generation, and the annual online operation probability is greater than the offline operation probability, then the current substation is determined to be an online substation;

若η<1或η>1,且p<0.5,则判定当前变电站为下网变电站;If η<1 or η>1, and p<0.5, the current substation is determined to be an off-grid substation;

选定最大负荷时段,计算最大负荷时段内当前变电站的净上网电量、最大负荷时段内变电站上送电力的概率和最大负荷时段内最大上送功率与最大下送功率的比值,从而对上网变电站进行判定;具体包括如下步骤:The maximum load period is selected, and the net grid-connected power of the current substation during the maximum load period, the probability of the substation sending power during the maximum load period, and the ratio of the maximum sending power to the maximum sending power during the maximum load period are calculated, so as to determine the grid-connected substation; specifically, the following steps are included:

分析当前变电站在地区最大负荷时段出现上送电力的情况及概率,通常日最大负荷时段出现在晚上6点~11点之间,而受地区气候和用电习惯影响,年最大负荷通常出现在夏季或冬季,不同的地区年最大负荷出现季节存在差异;夏季通常取7~8月,冬季通常取1月~次年12月。由于出现最大负荷时必然会有一个稳定的负荷增长过程;因此,选取最大负荷,并以最大为分界点,前后各取X天(优选为7天)的时间,总计2X天(优选为14天)的时间作为最大负荷段;X为设定的实数;Analyze the current situation and probability of the substation sending electricity during the period of regional maximum load. Usually, the daily maximum load period occurs between 6 pm and 11 pm. Affected by the regional climate and electricity consumption habits, the annual maximum load usually occurs in summer or winter. The annual maximum load occurs in different regions in different seasons. Summer is usually from July to August, and winter is usually from January to December of the following year. Since there must be a stable load growth process when the maximum load occurs, therefore, the maximum load is selected, and the maximum is used as the dividing point. X days (preferably 7 days) are taken before and after, and a total of 2X days (preferably 14 days) are taken as the maximum load period; X is a set real number;

计算在最大负荷时段内当前变电站净上网电量WN,up其中Pi为变电站在第i小时的功率;Calculate the net on-grid power of the current substation during the maximum load period W N,up Where Pi is the power of the substation at the i-th hour;

计算最大负荷时段内变电站上送电力的概率p为Pi≤0;其中Nup为数据小于0时的个数,此时表示变电站上送电力;N为最大负荷时段内变电站采集的数据点个数;The probability p of the substation transmitting power during the maximum load period is calculated as P i ≤0; N up is the number of data points less than 0, which indicates that the substation is transmitting power; N is the number of data points collected by the substation during the maximum load period;

计算最大负荷时段内最大上送功率与最大下送功率的比值α为其中Pi,up,max为最大负荷时段内变电站最大上送功率;Pi,down,max为最大负荷时段内变电站最大下送功率;The ratio α of the maximum uplink power to the maximum downlink power during the maximum load period is calculated as Where P i,up,max is the maximum up-transmission power of the substation during the maximum load period; P i,down,max is the maximum down-transmission power of the substation during the maximum load period;

采用如下规则进行判断:The following rules are used for judgment:

若p>0.5且WN,up<0,则判定当前变电站为上网变电站;If p>0.5 and W N,up <0, the current substation is determined to be an on-grid substation;

若p>0.5且α>1,则判定当前变电站为上网变电站;If p>0.5 and α>1, the current substation is determined to be an on-grid substation;

当当前变电站接入的电源装机容量大于或等于当前变电站最大负荷时,根据负荷与变电站最大负荷之间的关系以及最大负荷时段内地区负荷与地区最大负荷之间的关系,对上网变电站进行判定;具体包括如下步骤:When the installed capacity of the power source connected to the current substation is greater than or equal to the current maximum load of the substation, the online substation is determined based on the relationship between the load and the maximum load of the substation and the relationship between the regional load during the maximum load period and the regional maximum load. The specific steps include:

基于历史运行数据,在最大负荷时段内获取当前地区负荷Pload,j大于地区最大负荷Pload,max的Y%的时刻(优选为85%),Pload,j≥0.85Pload,max,j∈(1,N1);然后,得到当前变电站在对应第j个时刻的负荷Pj,并获取负荷Pj与变电站最大负荷的10%之间的关系,Pj≤0或者Pj≤0.1Pload,station,max,j∈(1,N2);其中,Pload,station,max为当前变电站可供带的最大负荷;N1为在最大负荷时段内获取当前地区负荷Pload,j大于地区最大负荷Pload,max的Y%的时刻的数据个数;N2为满足Pj≤0或者Pj≤0.1Pload,station,max的数据个数;Based on the historical operation data, obtain the moment when the current regional load P load,j is greater than Y% (preferably 85%) of the regional maximum load P load,max during the maximum load period, P load,j ≥0.85P load,max ,j∈(1,N 1 ); then, obtain the load P j of the current substation at the corresponding j-th moment, and obtain the relationship between the load P j and 10% of the maximum load of the substation, P j ≤0 or P j ≤0.1P load,station,max ,j∈(1,N 2 ); wherein P load,station,max is the maximum load that the current substation can carry; N 1 is the number of data at which the current regional load P load,j is greater than Y% of the regional maximum load P load,max during the maximum load period; N 2 is the number of data satisfying P j ≤0 or P j ≤0.1P load,station,max ;

计算概率p为Pj≤0或者Pj≤0.1Pload,station,maxCalculate the probability p as P j ≤0 or P j ≤0.1P load,station,max ;

采用如下规则进行判断:The following rules are used for judgment:

若p>0.5,则判定当前变电站为上网变电站。If p>0.5, the current substation is determined to be an on-grid substation.

以下结合一个实施例,对本发明的判定方法进行说明:The determination method of the present invention is described below in conjunction with an embodiment:

以某省级电网中,某新能源富集地区地级市为例,该市共拥有15座220千伏变电站。截至2021年底,该地区220千伏变电站主变压器容量为420万千伏安,该地区2021年最大负荷出现在冬季,地区最大负荷为221.72万千瓦,220千伏下网最大负荷为133.89万千瓦。此时15座变电站负荷均为正数,这些变电站在最大负荷时刻均向下级电网输送电力。但是这些变电站中,有部分变电站供带负荷不大,且一年365天运行中,大部分时间处于上送电力至上级电网。若在分析该地区220千伏下网容载比时不剔除220千伏上网变电站,则计算出的下网容载比为3.14。该容载比值偏大且无法准确反应出电网存在的问题,所以需要合理剔除上网站,然后依据变电容量和下网负荷得到220千伏下网最小容载比。Take a prefecture-level city in a new energy-rich area in a provincial power grid as an example. The city has a total of 15 220 kV substations. As of the end of 2021, the main transformer capacity of the 220 kV substation in the region was 4.2 million kVA. The maximum load in the region in 2021 occurred in winter, with a regional maximum load of 2.2172 million kW and a 220 kV grid-connected maximum load of 1.3389 million kW. At this time, the loads of the 15 substations are all positive numbers, and these substations all transmit electricity to the lower-level power grid at the moment of maximum load. However, some of these substations have a small supply load, and they are in operation 365 days a year, and most of the time they are transmitting electricity to the upper-level power grid. If the 220 kV grid-connected substations are not excluded when analyzing the 220 kV grid-connected capacity-load ratio in the region, the calculated grid-connected capacity-load ratio is 3.14. This capacity-load ratio is too large and cannot accurately reflect the problems existing in the power grid, so it is necessary to reasonably eliminate the upstream network and then obtain the minimum capacity-load ratio of the 220 kV downstream network based on the substation capacity and downstream load.

根据上述分析,对该地市15座220千伏变电站2021年运行数据进行分析,确定该地区上网站座数及主变压器容量。Based on the above analysis, the operating data of 15 220 kV substations in the city in 2021 were analyzed to determine the number of online stations and the capacity of main transformers in the area.

15座变电站分别命名为Station 1,Station 2,Station 3,……,Station 15,首先以Station 1为例进行分析:The 15 substations are named Station 1, Station 2, Station 3, ..., Station 15. First, Station 1 is taken as an example for analysis:

分析Station 1全年运行数据,通过分析数据可知:Analyzing the full-year operation data of Station 1, we can see that:

Wup,station1=-313887.337万千瓦时W up,station1 = -313887337 kWh

Wdown,station1=25150.478万千瓦时W down,station1 =251,504,780 kWh

根据上送电量与下送电量,可以计算得到两者的比值,即:According to the power transmission up and power transmission down, the ratio between the two can be calculated, that is:

根据η值的大小和p(Pi≤0)的概率可以判定,Station 1变电站全年的上网电量大于下网电量;According to the value of η and the probability of p(P i ≤0), it can be determined that the on-grid power of Station 1 substation is greater than the off-grid power throughout the year;

大负荷出现时段共5小时,以15分钟为间隔取点,一天可得到21个数据点,以地区最大负荷出现的当天为节点,前后各取7天并分析其实际运行数据,共取得315组数据,即N=315。该变电站最大上网负荷为19.378万千瓦,最大下网负荷为8.358万千瓦,由此可计算得到:The period of high load is 5 hours in total. The data points are collected at intervals of 15 minutes, and 21 data points can be obtained in one day. The day when the regional maximum load occurs is taken as the node. The actual operation data is analyzed for 7 days before and after, and a total of 315 sets of data are obtained, that is, N = 315. The maximum on-grid load of the substation is 193,780 kilowatts, and the maximum off-grid load is 83,580 kilowatts. It can be calculated as follows:

因此根据判断依据,判断Station 1变电站为上网变电站;Therefore, according to the judgment basis, Station 1 substation is judged to be an on-grid substation;

2021年底,Station 1变电站下接入电源装机容量45万千瓦,该变电站共有2台18万千伏安的主变压器,2021年最大负荷为9.5万千瓦,因此变电站接入的新能源装机容量大于该变电站最大负荷。At the end of 2021, the installed capacity of power connected to Station 1 substation was 450,000 kilowatts. The substation has two 180,000 kilowatt-ampere main transformers. The maximum load in 2021 was 95,000 kilowatts. Therefore, the installed capacity of new energy connected to the substation is greater than the maximum load of the substation.

此时该地区最大负荷的85%为188.46万千瓦,因此根据实际运行数据分析可知,全年该地区负荷大于188.46万千瓦的数据点共285个,即N1=285,由此可以得到该变电站在对应时刻的负荷情况,通过分析可知,对应时刻该变电站负荷小于0的数据点共有93个,小于该变电站最大负荷的10%的数据点共有50个;At this time, 85% of the maximum load in the region is 1.8846 million kilowatts. Therefore, according to the analysis of actual operation data, there are 285 data points with a load greater than 1.8846 million kilowatts in the region throughout the year, that is, N 1 = 285. From this, the load situation of the substation at the corresponding time can be obtained. Through analysis, it can be seen that there are 93 data points with a load less than 0 at the corresponding time, and 50 data points with a load less than 10% of the maximum load of the substation.

根据判断条件,即p(Pj≤0or0.1Pload,station,max)>0.5,此时该变电站认为是上网变电站;According to the judgment condition, that is, p(P j ≤0or0.1P load,station,max )>0.5, the substation is considered to be an on-grid substation;

由于该变电站下没有高耗能用户,若仅以该作为判断依据的话,在计算该地区220千伏下网容载比时,不需要剔除220千伏Station 1变电站的容量。Since there are no high-energy-consuming users under this substation, if this is used as the only basis for judgment, there is no need to exclude the capacity of the 220 kV Station 1 substation when calculating the 220 kV grid load ratio in the area.

综合上述分析可知,在计算该地区下网容载比时,需要剔除220千伏Station1变电站的容量,即认为该变电站为新能源上送电力的上网变电站。Based on the above analysis, it can be seen that when calculating the grid-connected capacity-load ratio in the area, the capacity of the 220 kV Station 1 substation needs to be excluded, that is, the substation is considered to be an online substation for transmitting electricity from renewable energy.

然后以Station 2为例进行分析:Then take Station 2 as an example for analysis:

分析Station 2全年运行数据,通过分析数据可知:Analyzing the full-year operation data of Station 2, we can see that:

Wup,station2=-82427.833万千瓦时W up,station2 = -824,278,330 kWh

Wdown,station2=55768.48万千瓦时W down,station2 =557,684,800 kWh

根据上送电量与下送电量,可以计算得到两者的比值,即:According to the power transmission up and power transmission down, the ratio between the two can be calculated, that is:

根据η值的大小和p(Pi≤0)的概率可以判定,Station2变电站为下网变电站。According to the value of η and the probability of p(P i ≤0), it can be determined that Station 2 is a grid-connected substation.

大负荷出现时段共5小时,以15分钟为间隔取点,一天可得到21个数据点,以地区最大负荷出现的当天为节点,前后各取7天并分析其实际运行数据,共取得315组数据,即N=315。由此可计算得到:The period of high load is 5 hours in total. We take data points at intervals of 15 minutes, and get 21 data points in one day. The day when the regional maximum load occurs is taken as the node. We take 7 days before and after and analyze the actual operation data, and get a total of 315 sets of data, that is, N = 315. From this, we can calculate:

因此根据判断依据,判断Station2变电站为下网变电站;Therefore, according to the judgment basis, Station 2 substation is judged to be a grid-connected substation;

2021年底,Station2变电站下接入电源装机容量23万千瓦,该变电站共有1台18万千伏安的主变压器,2021年最大负荷为9.7万千瓦,因此变电站接入的电源装机容量大于该变电站最大负荷。At the end of 2021, the installed capacity of power connected to the Station 2 substation was 230,000 kilowatts. The substation has a total of 180,000 kilowatt-ampere main transformer. The maximum load in 2021 was 97,000 kilowatts. Therefore, the installed capacity of power connected to the substation is greater than the maximum load of the substation.

此时该地区最大负荷的85%为188.46万千瓦,因此根据实际运行数据分析可知,全年该地区负荷大于188.46万千瓦的数据点共285个,即N1=285,由此可以得到该变电站在对应时刻的负荷情况,通过分析可知,对应时刻该变电站负荷小于0的数据点共有2个,小于该变电站最大负荷的10%的数据点共有50个;At this time, 85% of the maximum load in the region is 1.8846 million kilowatts. Therefore, according to the analysis of actual operation data, there are 285 data points with a load greater than 1.8846 million kilowatts in the region throughout the year, that is, N 1 = 285. From this, the load situation of the substation at the corresponding time can be obtained. Through analysis, it can be seen that there are 2 data points with a load less than 0 at the corresponding time, and 50 data points with a load less than 10% of the maximum load of the substation.

根据判断条件,即该变电站不满足p(Pj≤0or 0.1Pload,station,max)>0.5,此时该变电站认为是下网变电站;According to the judgment condition, the substation does not satisfy p(P j ≤0or 0.1P load,station,max )>0.5, and the substation is considered to be an off-grid substation;

由于该变电站下没有高耗能用户,若仅以该作为判断依据的话,在计算该地区220千伏下网容载比时,不需要剔除220千伏Station2变电站的容量。Since there are no high-energy-consuming users under this substation, if this is used as the only basis for judgment, there is no need to exclude the capacity of the 220 kV Station 2 substation when calculating the 220 kV grid load ratio in the area.

综合上述分析可知,在计算该地区下网容载比时,需要剔除220千伏Station2变电站的容量,即认为该变电站为上网变电站。Based on the above analysis, it can be seen that when calculating the grid-connected capacity-load ratio in the area, the capacity of the 220 kV Station 2 substation needs to be excluded, that is, the substation is considered to be an online substation.

根据上述方法对该地市15座220千伏变电站进行分析后,可以得出该地区上网站情况,如下表所示:After analyzing the 15 220 kV substations in the city according to the above method, the network connection situation in the area can be obtained, as shown in the following table:

表1某地市220千伏上网变电站情况示意表Table 1 Schematic diagram of 220 kV grid-connected substation in a certain city

变电站名Substation name 变电站容量(万千伏安)Substation capacity (10,000 kVA) 是否为上网变电站Is it an on-grid substation? Station1Station1 3636 yes Station 2Station 2 1818 no Station3Station3 3636 yes Station4Station4 1818 no Station5Station5 3030 yes Station6Station6 3636 yes Station7Station7 3636 no Station8Station8 24twenty four no Station9Station9 24twenty four no Station10Station10 24twenty four no Station11Station11 24twenty four no Station12Station12 3636 no Station13Station13 3636 no Station14Station14 1818 yes Station15Station15 24twenty four no

截至2021年底该地区15座220千伏变电站一共420万千伏安,其中10座220千伏变电站为下网变电站,变电容量为264万千伏安;5座220千伏变电站为上网变电站,变电容量为156万千伏安。根据上述方法求得该地区冬季最大负荷时段最小容载比为1.77,满足相关导则要求(220千伏地区容载比控制在1.7~2.0范围内)。此时该地区220千伏下网负荷为111.53万千瓦,此时剔除上网容量后的220千伏下网变电容量为198万千伏安。As of the end of 2021, the 15 220 kV substations in the region have a total capacity of 4.2 million kVA, of which 10 220 kV substations are off-grid substations with a substation capacity of 2.64 million kVA; 5 220 kV substations are on-grid substations with a substation capacity of 1.56 million kVA. According to the above method, the minimum load-to-capacity ratio during the maximum load period in winter in the region is 1.77, which meets the requirements of relevant guidelines (the load-to-capacity ratio in the 220 kV area is controlled within the range of 1.7 to 2.0). At this time, the 220 kV off-grid load in the region is 1.1153 million kW, and the 220 kV off-grid substation capacity after excluding the on-grid capacity is 1.98 million kVA.

通过上述方法所得到的上网站和目前实际运行中考虑的220千伏上网变电站一致,验证了所提方法的有效性,同时所得到的结果也能准确的反映出该地区220千伏电网保障负荷供电的情况。The grid-connected site obtained by the above method is consistent with the 220 kV grid-connected substation currently considered in actual operation, which verifies the effectiveness of the proposed method. At the same time, the results obtained can also accurately reflect the situation of the 220 kV power grid in the region to ensure load power supply.

如图2所示为本发明容载比计算方法的方法流程示意图:本发明提供的这种包括了所述220千伏电网上网变电站判定方法的容载比计算方法,具体包括如下步骤:FIG2 is a flow chart of the method for calculating the capacity-load ratio of the present invention: The method for calculating the capacity-load ratio provided by the present invention, which includes the method for determining the 220 kV grid-connected substation, specifically includes the following steps:

A.采用所述的220千伏电网上网变电站判定方法,对区域内的上网变电站进行排定;A. Using the above-mentioned 220 kV grid-connected substation determination method, the grid-connected substations in the area are scheduled;

B.在计算区域220千伏下网容载比时,剔除步骤A得到的上网变电站的容量;具体包括如下步骤:B. When calculating the regional 220 kV grid-connected capacity-load ratio, the capacity of the grid-connected substation obtained in step A is eliminated; specifically, the following steps are included:

剔除步骤A得到的上网变电站的容量;Eliminate the capacity of the grid-connected substation obtained in step A;

在计算区域220千伏下网容载比时,剔除以高耗能用户为主的变电站;所述的以高耗能用户为主的变电站,定义高耗能用户为炼铁行业、电解铝行业等工业;When calculating the regional 220 kV grid capacity load ratio, substations with high energy consumption users are excluded; the substations with high energy consumption users are defined as industries such as iron smelting and electrolytic aluminum industries;

本步骤的核心在于,对于部分以高耗能用户为主的变电站,用户的用电负荷特性主要由电价决定,这类用户最大负荷时刻通常出现在晚上12点以后,在电网高峰负荷时段,由于电价等因素影响该变电站负荷水平较低;因此在分析下网容载比时,需将这类变电站容量剔除,但此类变电站并不属于上网变电站;The core of this step is that for some substations that are mainly high-energy-consuming users, the user's power load characteristics are mainly determined by the electricity price. The maximum load time of such users usually occurs after 12 o'clock in the evening. During the peak load period of the power grid, the load level of the substation is relatively low due to factors such as electricity prices. Therefore, when analyzing the offline capacity-load ratio, the capacity of such substations needs to be eliminated, but such substations do not belong to online substations.

C.根据步骤B得到的数据信息,计算220千伏区域电网的下网容载比。C. Based on the data information obtained in step B, calculate the off-grid capacity load ratio of the 220 kV regional power grid.

Claims (3)

1. A220 KV power grid on-line transformer substation judging method comprises the following steps:
s1, acquiring substation data information of a 220 kilovolt regional power grid;
S2, calculating the ratio of the power on the network to the power off the network of the transformer substation according to the data information obtained in the step S1, and the probability of the occurrence of new energy or conventional power supply power; the method specifically comprises the following steps:
based on 8760 operation hours data of the current transformer substation in the last year, the annual internet power of the current transformer substation in the last year is counted P i is less than or equal to 0 and the power of the power supply under the netP i is more than 0, wherein W up is the power on line, deltaT is the length of a time period, P i is the power of the transformer substation in the ith hour, P i is less than or equal to 0 and represents the power transmitted by the transformer substation, and P i is more than 0 and represents the normal load supply of the transformer substation;
Calculating the ratio eta of the on-line electric quantity and the off-line electric quantity of the current transformer substation as
Calculating the probability p of new energy or conventional power supply power sent by the current transformer substation asP i is less than or equal to 0 and i epsilon (1,35040), wherein N up,year is the number of loads less than 0 in the current transformer substation operation data of the whole year, and N year is the total number of the current transformer substation operation data points of the whole year;
S3, judging the online substation according to the data information obtained by calculation in the step S2 and the selected maximum load period; the method specifically comprises the following steps:
judging the online substation according to the ratio eta of the online electric quantity and the offline electric quantity of the substation and the probability p of new energy or conventional power supply power sent by the substation, which are obtained in the step S2; the method specifically comprises the following steps:
The following rules are adopted for judgment:
if eta is more than or equal to 1 and p is more than 0.5, the annual online electric quantity of the current transformer substation is larger than the offline electric quantity, the annual online operation probability is larger than the offline operation probability, and the current transformer substation is judged to be the online transformer substation;
if eta is less than 1 or eta is more than 1 and p is less than 0.5, judging that the current transformer substation is an off-grid transformer substation;
selecting a maximum load period, and calculating net surfing electric quantity of a current transformer substation in the maximum load period, probability of power transmission of the transformer substation in the maximum load period and ratio of maximum power transmission to maximum power transmission in the maximum load period, so as to judge the surfing transformer substation; the method specifically comprises the following steps:
selecting the maximum load, taking the maximum as a demarcation point, taking the time of X days before and after, and taking the total time of 2X days as a maximum load section; x is a set real number;
Calculating the net surfing electric quantity W N,up of the current transformer substation in the maximum load period as Wherein P i is the power of the transformer station at the ith hour;
calculating the probability p of power transmission of the transformer substation in the maximum load period as P i is less than or equal to 0; n up is the number when the data is smaller than 0, and represents the power sent by the transformer substation at the moment; n is the number of data points collected by the transformer substation in the maximum load period;
Calculating the ratio alpha of the maximum upward power to the maximum downward power in the maximum load period as Wherein P i,up,max is the maximum upward power of the transformer substation in the maximum load period; p i,down,max is the maximum downward power of the transformer substation in the maximum load period;
The following rules are adopted for judgment:
If p is more than 0.5 and W N,up is less than 0, judging that the current transformer substation is an online transformer substation;
if p is more than 0.5 and alpha is more than 1, judging that the current transformer substation is an online transformer substation;
when the installed capacity of the power supply accessed by the current transformer substation is larger than or equal to the maximum load of the current transformer substation, judging the online transformer substation according to the relation between the load and the maximum load of the transformer substation and the relation between the regional load and the regional maximum load in the maximum load period; the method specifically comprises the following steps:
Acquiring a moment when the current regional load P load,j is greater than Y% of the regional maximum load P load,max in the maximum load period based on the historical operation data, P load,j≥0.85Pload,max,j∈(1,N1); then, obtaining the load P j of the current transformer substation at the corresponding j-th moment, and obtaining the relation between the load P j and 10% of the maximum load of the transformer substation, wherein P j is less than or equal to 0 or P j≤0.1Pload,station,max,j∈(1,N2); wherein P load,station,max is the maximum load available for the current transformer substation; n 1 is the number of data obtained at the moment when the current regional load P load,j is greater than Y% of the regional maximum load P load,max in the maximum load period; n 2 is the number of data meeting the requirement that P j is less than or equal to 0 or P j≤0.1Pload,station,max;
Calculating the probability p as P j is less than or equal to 0 or P j≤0.1Pload,station,max;
The following rules are adopted for judgment:
if p is more than 0.5, the current transformer substation is judged to be the internet transformer substation.
2. A method for calculating a capacity ratio comprising the 220 kv power grid-on-line substation determination method of claim 1, comprising the steps of:
A. Scheduling the network substation in the area by adopting the 220 KV power grid network substation judging method;
B. C, eliminating the capacity of the network substation obtained in the step A when the network capacity-to-load ratio of 220 kilovolts in the area is calculated;
C. And C, calculating the lower network capacity-to-load ratio of the 220 KV regional power grid according to the data information obtained in the step B.
3. The method for calculating the capacity/load ratio according to claim 2, wherein in the step B, when calculating the network capacity/load ratio under 220 kv in the area, the capacity of the network substation obtained in the step a is removed, and the method specifically comprises the following steps:
Removing the capacity of the online substation obtained in the step A;
When the network capacity-load ratio is calculated under 220 kilovolts in the area, eliminating the transformer substation mainly with high-energy-consumption users; the transformer substation mainly comprises transformer substations mainly comprising iron-making industry and electrolytic aluminum industry.
CN202310034718.1A 2023-01-10 2023-01-10 220 KV power grid on-line transformer substation judging method and capacity-to-load ratio calculating method Active CN115967120B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310034718.1A CN115967120B (en) 2023-01-10 2023-01-10 220 KV power grid on-line transformer substation judging method and capacity-to-load ratio calculating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310034718.1A CN115967120B (en) 2023-01-10 2023-01-10 220 KV power grid on-line transformer substation judging method and capacity-to-load ratio calculating method

Publications (2)

Publication Number Publication Date
CN115967120A CN115967120A (en) 2023-04-14
CN115967120B true CN115967120B (en) 2024-10-29

Family

ID=87361479

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310034718.1A Active CN115967120B (en) 2023-01-10 2023-01-10 220 KV power grid on-line transformer substation judging method and capacity-to-load ratio calculating method

Country Status (1)

Country Link
CN (1) CN115967120B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116523403A (en) * 2023-05-05 2023-08-01 国网湖南省电力有限公司 Regional power grid 220KV capacity-load ratio calculation method and system
CN116436020B (en) * 2023-05-05 2024-05-07 国网湖南省电力有限公司 Demand determination method and system for new energy grid-connected aggregation station

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105929225A (en) * 2016-07-13 2016-09-07 广东电网有限责任公司 Method for acquiring on-grid and off-grid electric quantities
CN110414759A (en) * 2018-04-27 2019-11-05 广西电网有限责任公司 A Differential Calculation Method of Capacity-load Ratio

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5394217B2 (en) * 2009-12-14 2014-01-22 株式会社日立パワーソリューションズ Natural energy power plant with power storage
CN104348256B (en) * 2013-07-30 2016-09-21 国家电网公司 Consider the polymorphic type battery energy storage power station energy management method of charge-discharge magnification
CN105894394A (en) * 2016-03-30 2016-08-24 中国南方电网有限责任公司 Method for calculating power loss of power grid in multi-dimension real time cutting power grid model generated statistical scope
CN112529377B (en) * 2020-11-27 2022-08-26 贵州电网有限责任公司 Medium-voltage distribution network capacity-to-load ratio calculation method
CN113034205B (en) * 2021-04-20 2022-03-11 上海交通大学 Energy storage station and transformer substation combined planning method considering capacity-to-load ratio dynamic adjustment
CN114386703A (en) * 2022-01-14 2022-04-22 国网上海市电力公司 New energy power station power generation internet access auxiliary decision method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105929225A (en) * 2016-07-13 2016-09-07 广东电网有限责任公司 Method for acquiring on-grid and off-grid electric quantities
CN110414759A (en) * 2018-04-27 2019-11-05 广西电网有限责任公司 A Differential Calculation Method of Capacity-load Ratio

Also Published As

Publication number Publication date
CN115967120A (en) 2023-04-14

Similar Documents

Publication Publication Date Title
Begovic et al. Impact of renewable distributed generation on power systems
CN115967120B (en) 220 KV power grid on-line transformer substation judging method and capacity-to-load ratio calculating method
CN114069700B (en) Regional comprehensive energy scheduling control system based on energy Internet
CN112241923B (en) Distribution network power balance method based on comprehensive energy system source load equivalent external characteristics
CN117595517B (en) Intelligent cluster control method and system based on distributed photovoltaic
CN114386703A (en) New energy power station power generation internet access auxiliary decision method
CN114285034A (en) A day-ahead control optimization method and system considering fluctuations in electricity and new energy
CN119543131A (en) A method for evaluating grid access capability with multi-energy synergy and complementarity
CN119051040A (en) Photovoltaic absorption optimization method and system for power distribution network
CN106203742B (en) An energy-saving evaluation and selection method for power grid equipment based on energy-saving rate of return
CN111835003A (en) Real-time calculation method and system for theoretical line loss of medium-voltage distribution network under multi-source power supply
Ding et al. A dynamic period partition method for time-of-use pricing with high-penetration renewable energy
CN106981030A (en) A kind of grid-connected characteristics of DG to the power distribution network containing DG, the method for receiving ability to carry out quantitative evaluation
CN118982287A (en) Evaluation method and computer program product for grid-connected power quality of new energy power stations
CN118589503A (en) Source-load dynamic scheduling method based on photovoltaic access capability
CN118195709A (en) Method and system for calculating return of power distribution network engineering project
CN116937562A (en) Power quality prediction method and device for distributed photovoltaic access and power system
Gerald et al. A large-scale study of the impact of future unregulated EV charging on low voltage grids
CN116436020A (en) Demand judging method and system for new energy Internet surfing aggregation station
CN113919885B (en) Method for evaluating influence of user electricity price design on new energy consumption of power system
CN114386849A (en) Power balance risk early warning method for high proportion of new energy systems
Han et al. Reserve demand assessment based on dynamic percentage of renewable generation and load forecasts
Li et al. Improvement of Renewable Power Forecasting Indicators Based on System Flexibility
Zhou et al. Optimization of 10kV distribution network planning based on modified genetic anneal
Guo et al. Assessment of voltage fluctuations based on wind power fluctuation characteristics

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
点击 这是indexloc提供的php浏览器服务,不要输入任何密码和下载