+

CN108677638A - Express highway roadbed dam filling construction based on building waste - Google Patents

Express highway roadbed dam filling construction based on building waste Download PDF

Info

Publication number
CN108677638A
CN108677638A CN201810533967.4A CN201810533967A CN108677638A CN 108677638 A CN108677638 A CN 108677638A CN 201810533967 A CN201810533967 A CN 201810533967A CN 108677638 A CN108677638 A CN 108677638A
Authority
CN
China
Prior art keywords
construction waste
rolling
construction
water
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810533967.4A
Other languages
Chinese (zh)
Inventor
徐永福
徐宁
张攀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiao Tong University
Original Assignee
Shanghai Jiao Tong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiao Tong University filed Critical Shanghai Jiao Tong University
Priority to CN201810533967.4A priority Critical patent/CN108677638A/en
Publication of CN108677638A publication Critical patent/CN108677638A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of express highway roadbed dam filling construction based on building waste, including step:Construction site pre-processes;Surveying and locating;Basal layer processing;Building waste pre-processes;The processing of bound edge soil water proof;Building waste is laid with and leveling;Building waste rolls;Quality testing.Present invention realization is filled to express highway roadbed in high quality using building waste; largely alleviate the problem of building waste surplus; and material for roadbed filling and method provide a reliable selection; accomplish to economize on resources more to a certain extent, environmental protection, has met the theory of sustainable development.

Description

基于建筑垃圾的高速公路路基填筑方法Construction Waste Based Expressway Roadbed Filling Method

技术领域technical field

本发明涉及土木建筑的高速公路路基施工领域,具体的是一种基于建筑垃圾的高速公路路基填筑方法。The invention relates to the field of expressway subgrade construction of civil engineering, in particular to a filling method for expressway subgrade based on construction waste.

背景技术Background technique

近年来,随着我国经济发展和城市化进程的加快,城市基础设施建设、维修、拆除中产生的混凝土块、废砖及渣土等建筑垃圾的总量与日俱增。据相关资料反映:目前,我国的建筑垃圾数量已经占到城市垃圾总量的30~40%,我国目前建筑垃圾堆放总量已达70亿吨,每年新产生的建筑垃圾超过4亿吨,但是综合处理利用率不到5%。全国600多座城市,有400多城市面临垃圾围城的现象。据推测到2020年,我国将新增建筑面积约300亿平米,若以500~600吨/万平方米的垃圾产量标准推算,新产生的建筑垃圾将是一个令人震惊的数字。日益增加的建筑垃圾不进行回收利用,不仅浪费了大量自然资源,占据了大量生产用地,更加重了生态污染。因此,寻求一种将建筑垃圾资源化利用的方法已经成为我国迫切需要解决的问题。In recent years, with the acceleration of my country's economic development and urbanization process, the total amount of construction waste such as concrete blocks, waste bricks and muck generated in the construction, maintenance and demolition of urban infrastructure is increasing day by day. According to relevant information: at present, the amount of construction waste in my country has accounted for 30-40% of the total amount of urban waste, and the total amount of construction waste piled up in my country has reached 7 billion tons, and the annual new generation of construction waste exceeds 400 million tons. Comprehensive processing utilization is less than 5%. There are more than 600 cities in the country, and more than 400 cities are facing the phenomenon of garbage siege. It is estimated that by 2020, my country will add about 30 billion square meters of construction area. If calculated based on the waste production standard of 500-600 tons/10,000 square meters, the newly generated construction waste will be an astonishing figure. The ever-increasing construction waste is not recycled, which not only wastes a lot of natural resources, occupies a lot of production land, but also aggravates ecological pollution. Therefore, seeking a method for resource utilization of construction waste has become an urgent problem to be solved in our country.

建筑垃圾是指在新建、改建、扩建、拆除、加固各类建筑物、构筑物、管网等以及居民装饰装修房屋过程中产生的废物料。建筑垃圾的组成因地区经济发展水平、建筑结构、拆除和回收方式不同而变化,通常含有土、水泥基材料、烧结材料、天然石材、木材、金属、玻璃、塑料及其他材料。其性能优于黏土和粉性土,具有较好的硬度、强度、韧性和稳定性。Construction waste refers to the waste materials generated in the process of new construction, reconstruction, expansion, demolition, reinforcement of various buildings, structures, pipe networks, etc., as well as the process of residential decoration. The composition of construction waste varies with regional economic development levels, building structures, demolition and recycling methods, and usually contains soil, cement-based materials, sintered materials, natural stone, wood, metal, glass, plastic and other materials. Its performance is better than that of clay and silty soil, and it has better hardness, strength, toughness and stability.

发明内容Contents of the invention

针对当下建筑垃圾严重过剩的问题,结合建筑垃圾优良的力学及工程性能,本发明提出了一种基于建筑垃圾的高速公路路基填方法,使建筑垃圾得到了回收再利用Aiming at the serious excess of construction waste at present, combined with the excellent mechanical and engineering properties of construction waste, the present invention proposes a method of filling highway subgrade based on construction waste, so that construction waste can be recycled and reused

为实现上述目的,本发明的技术解决方案如下:To achieve the above object, the technical solution of the present invention is as follows:

S1:施工现场预处理;S1: Construction site pretreatment;

S2:测量放样;S2: measurement stakeout;

S3:基底层处理;S3: Base layer processing;

S4:建筑垃圾预处理;S4: Construction waste pretreatment;

S5:包边土隔水处理:在左右幅两边用成品石灰土进行包边隔水;S5: water-proof treatment of edge-wrapping soil: use finished lime soil on both sides of the left and right panels for edge-wrapping and water-proofing;

S6:建筑垃圾铺设与整平;S6: Laying and leveling of construction waste;

S7:对建筑垃圾进行碾压处理,具体步骤如下:S7: Rolling and compacting construction waste, the specific steps are as follows:

碾压前,计算建筑垃圾需补充的水量M,公式如下:Before rolling, calculate the amount of water M water that needs to be supplemented by construction waste, the formula is as follows:

M=(W00)×M/(1+ω0)M water = (W 00 )×M/(1+ω 0 )

式中,W0为实测建筑垃圾含水量、ω0为压实的最佳含水(一般为13%±2%)、 M为需要补充水分的建筑垃圾质量;In the formula, W 0 is the measured water content of construction waste, ω 0 is the optimal water content for compaction (generally 13% ± 2%), and M is the quality of construction waste that needs to be supplemented with water;

碾压时,对建筑垃圾补充水量后,首先用羊足碾碾压,在颗粒直径碾到3cm以下后,采用振动压路机碾压8~12遍,最后用光轮压路机以1.0~1.4km/h的速度碾压至少10遍。When rolling, after adding water to the construction waste, firstly roll it with sheep feet, and when the diameter of the particles is less than 3cm, use a vibratory roller to roll it 8 to 12 times, and finally use a bare wheel roller at a speed of 1.0 to 1.4km/h. Speed rolling at least 10 times.

所述步骤S1施工现场预处理,包括三个部分:一是清理杂物;二是地表排水;三是场地整平。The step S1 of construction site pretreatment includes three parts: one is cleaning debris; the other is surface drainage; the third is site leveling.

所述步骤S2测量放样,具体是:在原地面进行放样,标识出石灰土铺筑宽度,并设层位杆以控制摊铺厚度。The step S2 measures stakeout, specifically: stake out on the original ground, mark the width of the lime soil paving, and set layer level bars to control the paving thickness.

所述步骤S3基底层处理,具体是:首先对施工作业面的土堆采用推土机摊铺,然后用平地机精平,并用振动压路机进行碾压,保证层厚均匀一致。The treatment of the base layer in the step S3 specifically includes: firstly, bulldozers are used to pave the mound of the construction work surface, and then it is finely leveled with a grader, and rolled with a vibratory roller to ensure that the layer thickness is uniform.

所述碾压的方式如下:由两边向中间进行,横向衔接处碾压轮迹重叠40-50cm,纵向前后相邻施工段轮迹重叠宽度100-150cm。The rolling method is as follows: from both sides to the middle, the rolling wheel tracks overlap 40-50cm at the transverse joints, and the overlapping width of the wheel tracks in the longitudinal front and rear adjacent construction sections is 100-150cm.

所述步骤S4建筑垃圾预处理,包括两点:一是挑选不适合填筑的杂物;二是将建筑垃圾进行机械破碎,使破碎后粒径小于25cm。The step S4 of construction waste pretreatment includes two points: one is to select debris that is not suitable for filling; the other is to mechanically crush the construction waste so that the particle size after crushing is less than 25 cm.

所述步骤S5包边土松铺系数大于建筑垃圾铺系数的10%-20%,并高出同层建筑垃圾5-8cm。In the step S5, the coefficient of loose paving of edge-wrapping soil is greater than 10%-20% of that of construction waste, and is 5-8cm higher than that of construction waste on the same layer.

所述步骤S6建筑垃圾铺设与整平,具体是,将施工面划分为若干等大方格,并按照填筑高度和面积的乘积推算所需建筑垃圾的方量,确保摊铺时层厚均匀一致;然后,采用挖机粗平后用推土机精平,达到松铺30cm。The step S6 of laying and leveling the construction waste, specifically, divides the construction surface into a number of equal large squares, and calculates the required amount of construction waste according to the product of the filling height and area, so as to ensure that the layer thickness is even when paving Consistent; then, use an excavator for rough leveling and then use a bulldozer for fine leveling to achieve a loose pavement of 30cm.

所述步骤S7中羊足碾是指由两边向中间碾压,碾压速度控制在2.8~3.2km/h,轮迹重叠0.4~0.5m。In the step S7, the sheep foot rolling refers to rolling from both sides to the middle, the rolling speed is controlled at 2.8-3.2km/h, and the wheel tracks overlap by 0.4-0.5m.

所述步骤S7中,碾压方式:由两边向中间进行,形成2-3%的路拱横坡;横向衔接处碾压轮迹重叠40-50cm;纵向前后相邻施工段轮迹重叠宽度100-150cm。In the step S7, the rolling method is carried out from both sides to the middle to form a 2-3% road arch cross slope; the rolling wheel tracks at the horizontal joints overlap by 40-50cm; the overlapping width of the wheel tracks in the longitudinal front and rear adjacent construction sections is 100 cm -150cm.

所述步骤S7中先安装沉降板,然后将水准仪架在路基外的堆料区旁,分别测量三种压路机对建筑垃圾碾压前和碾压后的高程值的读数,当前后两次读数差小于5 mm,则说明路基填料满足要求,填筑结束,否则用光轮压路机继续碾压,直至符合小于5毫米的标准。In the step S7, the settling plate is first installed, and then the level is placed beside the stockpiling area outside the subgrade, and the readings of the elevation values of the three types of road rollers before and after the construction waste are measured respectively. If it is less than 5 mm, it means that the subgrade filling meets the requirements, and the filling is completed. Otherwise, continue rolling with a smooth wheel roller until it meets the standard of less than 5 mm.

所述安装沉降板的方法如下:施工场地纵向平分为若干个断面,每个断面安装两块,从底基层开始安装,以上每两层安装一次;安装好沉降板后,即可在之后的碾压中进行沉降测量。The method for installing the settlement plate is as follows: the construction site is divided into several sections vertically, and two pieces are installed in each section, starting from the base layer, and installed once every two layers above; Settlement measurements were carried out under pressure.

与现有技术相比,本发明的技术效果如下:Compared with prior art, technical effect of the present invention is as follows:

1)将建筑垃圾进行资源化利用不仅能在极大程度上解决建筑垃圾堆积的问题,更节约了大量自然资源,节省了大量生产用地,此外还具备一定的经济性。1) The resource utilization of construction waste can not only solve the problem of construction waste accumulation to a great extent, but also save a lot of natural resources and a lot of production land. In addition, it also has a certain degree of economy.

2)利用新建、改建、扩建、拆除中产生的建筑垃圾,同时对传统的填筑方法进行了一定的改进,提高了高速公路路基的质量,同时也降低了高速公路的造价。2) Utilize the construction waste generated during new construction, reconstruction, expansion, and demolition, and at the same time make some improvements to the traditional filling methods, which improves the quality of the expressway roadbed and reduces the cost of the expressway.

3)能够节约大量自然资源,空出大量生产用地,减缓了生态污染,符合可持续发展的理念。3) It can save a lot of natural resources, free up a lot of production land, slow down the ecological pollution, and conform to the concept of sustainable development.

附图说明Description of drawings

图1为包边土大样图Figure 1 is a large sample of edge-wrapped soil

图2为建筑垃圾填筑层数示意图Figure 2 is a schematic diagram of the number of layers of construction waste filling

具体实施方式Detailed ways

下面结合具体实例对本发明进行详细说明,以下实施例将有助于本领域的技术人员进一步理解本发明,但不以任何形式限制本发明。应当指出的是,对本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。根据下面说明和权利要求书,本发明的优点和特征将更清楚。需要说明的是附图均采用简化形式和非精准比例,仅用于方便明晰地辅助说明本发明实施例的目的。The present invention will be described in detail below in conjunction with specific examples. The following examples will help those skilled in the art to further understand the present invention, but do not limit the present invention in any form. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Advantages and features of the present invention will be apparent from the following description and claims. It should be noted that the drawings are all in simplified form and inaccurate proportions, and are only used for the purpose of conveniently and clearly assisting in describing the embodiments of the present invention.

本发明提出的一种将建筑垃圾用于高速公路路基填筑的方法,包括下列步骤:A kind of method that the present invention proposes is used for highway subgrade filling with construction waste, comprises the following steps:

S1:施工现场预处理:包括以下三个部分:一是清理现场塑料袋、电线、杂草、生活垃圾等不适合路基填筑的废弃物;二是在路基两侧修筑临时排水沟,排除原地面地表水,并防止周边水进入路基施工范围;三是场地整平,翻松25cm掺灰处理后进行压实,保证原地面压实度不小于90%。S1: Construction site pretreatment: including the following three parts: one is to clean up plastic bags, wires, weeds, household garbage and other wastes that are not suitable for roadbed filling; the other is to build temporary drainage ditches on both sides of the roadbed to remove Surface water on the ground, and prevent the surrounding water from entering the subgrade construction area; the third is to level the site, loosen 25cm and mix it with ash, and then compact it to ensure that the original ground compaction degree is not less than 90%.

S2:测量放样;在已验收合格的路基原地面上进行红外全站仪准确地放出施工路段的中、边桩(保证不少于50cm的加宽),用石灰线明显标识出石灰土铺筑宽度,并在左右幅边桩位置处各设置一根层位杆,以控制摊铺厚度。S2: Measurement and stakeout; on the original ground of the subgrade that has passed the inspection, the infrared total station is used to accurately release the middle and side piles of the construction section (to ensure that the width is not less than 50cm), and the lime soil paving is clearly marked with lime lines Width, and a layer bar is set at the position of the left and right side piles to control the paving thickness.

S3:基底层处理:原地面以上40cm为基底防水层,分两层填筑,每层20cm。施工作业面的土堆采用推土机摊铺、平地机精平,保证层厚均匀一致。首先采用振动压路机碾压,先静压一遍再弱振一遍,强振三遍,振动静压速度拟采用1.2km/h。经压实度自检合格后由胶轮压路机收光。碾压由两边向中间进行,横向衔接处碾压轮迹重叠40-50cm,纵向前后相邻施工段轮迹重叠宽度100-150cm。碾压应保证无漏压、无死角、全面均匀压实,保证第一层压实度不小于92%,第二层压实度不小于93%。S3: Treatment of the base layer: 40cm above the original ground is the base waterproof layer, filled in two layers, each layer 20cm. The soil mound on the construction work surface shall be paved by bulldozers and finely leveled by a grader to ensure uniform layer thickness. Firstly, the vibratory roller is used for rolling, first static pressure once, then weak vibration once, and strong vibration three times, the vibratory static pressure speed is planned to be 1.2km/h. After passing the compaction self-test, it will be collected by a rubber-tyred road roller. Rolling is carried out from both sides to the middle, the rolling wheel tracks overlap by 40-50cm at the horizontal joints, and the overlapping width of the wheel tracks in the front and rear adjacent construction sections in the longitudinal direction is 100-150cm. Rolling should ensure no pressure leakage, no dead angle, comprehensive and uniform compaction, and ensure that the compaction degree of the first layer is not less than 92%, and the compaction degree of the second layer is not less than 93%.

S4:建筑垃圾预处理:挑拣出有机垃圾及不适合用于作为路基填料的废弃物。利用挖机对超大块材料进行预破碎,针对楼板等空洞密集垃圾充分破碎处理,破碎最大粒径不超过25cm。人工剪除钢筋以避免大量钢筋缠绕,影响填筑质量。破碎过程中注意洒水除尘。S4: Construction waste pretreatment: Sorting out organic waste and waste not suitable for use as roadbed filler. Use the excavator to pre-shred super-large pieces of materials, and fully shred the hollow and dense garbage such as floors. The maximum particle size of the shreds does not exceed 25cm. Manually cut off the steel bars to avoid a large number of steel bars being entangled and affecting the filling quality. Pay attention to watering and dust removal during the crushing process.

S5:包边土隔水处理:在左右幅两边先用5%成品石灰土回填2.5m宽(包括50 cm加宽值)进行包边隔水。为避免包边土和建筑垃圾碾压后高程出现差异,包边土松铺系数一般大于建筑垃圾松铺系数的10%-20%。对包边土先进行预压,使其较同层建筑垃圾高出5-8cm,然后再与该层建筑废弃砖渣填料同步压实,增加结构整体性。S5: Edge-wrapping soil water-proof treatment: backfill 2.5m wide (including 50 cm widening value) with 5% finished lime soil on both sides of the left and right sides to carry out edge-wrapping and water-proofing. In order to avoid the difference in elevation between the edge-wrapped soil and construction waste after rolling, the loose-spread coefficient of the edge-wrapped soil is generally 10%-20% greater than that of the construction waste. The edge-wrapping soil is pre-pressed to make it 5-8cm higher than the construction waste of the same layer, and then it is compacted synchronously with the waste brick slag filler of this layer to increase the structural integrity.

S6:建筑垃圾铺设与整平;本实施例长度为50m,宽度随标高增高而变窄,填筑土压实厚度为20cm,松铺厚度约30cm。上土布料前,用石灰线画出10m(纵向) ×(实际标高推算宽度+1m-2.5m)/3(横向平均分3份)的方格子,共计15个方格。每层建筑垃圾压实方量为:10m×(实际标高推算宽度+1m-2.5m)m×0.2m,同时推算出每个方格需砖渣量,采用运输车将所需量运每个方格中。上料把好上料关,装车时,注意控制每车的运土数量大致相等;卸料时,专人负责指挥卸料,保证每个方格子都卸相同车数的料,且卸料间距均匀一致,以确保摊铺时层厚能够均匀一致。运料完成后,采用挖机将填料粗平后用推土机精平,若还有个别较高的堆体,采用人工整平使其表面平整,达到松铺30cm。S6: Laying and leveling of construction waste; the length of this embodiment is 50m, and the width becomes narrower as the elevation increases. The compacted thickness of the filling soil is 20cm, and the loose laying thickness is about 30cm. Before laying the soil, draw a square grid of 10m (longitudinal) × (calculated width of actual elevation + 1m-2.5m)/3 (horizontal average 3 parts) with lime lines, a total of 15 squares. The compaction volume of construction waste on each floor is: 10m×(calculated width from actual elevation + 1m-2.5m)m×0.2m, and at the same time calculate the amount of brick slag required for each square, and use the transport vehicle to transport the required amount to each in the grid. When loading, make sure that the loading is closed. When loading, pay attention to controlling the amount of soil transported by each vehicle to be roughly equal; Uniform and consistent to ensure that the layer thickness can be uniform when paving. After the materials are transported, use the excavator to roughly level the filler, and then use the bulldozer to level it finely. If there are individual high piles, use manual leveling to make the surface smooth, reaching a loose layer of 30cm.

S7:建筑垃圾碾压:根据路基对压实度的要求,采用21t铁三轮压路机(铁轮内提前灌注黄砂)及21t羊足碾联合对建筑垃圾进行碾压,以保证压实功效和建筑垃圾表面的平整。表1为羊足碾参数表。S7: Construction waste rolling: According to the compaction requirements of the subgrade, a 21t iron three-wheel road roller (the iron wheel is filled with yellow sand in advance) and a 21t sheep foot roller are combined to roll the construction waste to ensure the compaction effect and construction The leveling of the garbage surface. Table 1 is the parameter list of sheep foot mill.

表1:羊足碾参数表Table 1: Parameter table of sheep foot mill

碾压前先对建筑垃圾的含水率进行检测,使含水率控制在最佳含水率±2%,若当含水率偏高时,采用晾晒直至含水量达到要求。当含水量满足要求时,应尽量缩短施工时间,减少含水量的损失,确保碾压效果。当含水量偏低时,用洒水车洒水进行补充,根据实测含水量W0、压实的最佳含水量ω0、需要补充水分的建筑垃圾质量M等,计算其应补充的水量M=(W00)×M/(1+ω0)。洒水车补水时,专人负责,保证水分在建筑垃圾内均匀。Before rolling, the moisture content of the construction waste is tested to control the moisture content at the optimum moisture content ± 2%. If the moisture content is too high, dry it until the moisture content meets the requirements. When the water content meets the requirements, the construction time should be shortened as much as possible to reduce the loss of water content and ensure the rolling effect. When the water content is low, use a sprinkler to add water. According to the measured water content W 0 , the optimal water content ω 0 for compaction, and the quality M of construction waste that needs to be supplemented with water, calculate the amount of water that should be supplemented Mwater = (W 0 −ω 0 )×M/(1+ω 0 ). When the sprinkler replenishes water, a special person is responsible to ensure that the water is evenly distributed in the construction waste.

碾压时,首先用羊足碾碾压,第6遍和第10遍后,采用平地机粗平,第14遍后,采用平地机精平。羊足碾由两边向中间碾压,碾压速度控制在3km/h左右,轮迹重叠0.4-0.5m。在碾压的过程中,时刻关注建筑垃圾颗粒直径的大小,若碾压到 14遍后发现颗粒直径在3cm以下,则可以采光轮压路机碾压;若14遍后,发现颗粒直径在3cm以上,则需用羊足碾继续碾压,直到颗粒直径在3cm以下后,才能用光轮压路机碾压。羊足碾碾压完成后,挑拣出少量的未压碎的钢筋混凝土块,按照路面横坡平地机精平。其后采用振动压路机碾压10遍。最后用光轮压路机碾压 10遍,采用1.2km/h碾压;碾压行进速度由慢到快,最大速度不超过4km/h;碾压由两边向中间进行,形成2-3%的路拱横坡,利于排水;横向衔接处碾压轮迹重叠 40-50cm,纵向前后相邻施工段轮迹重叠宽度100-150cm。碾压应保证无漏压、无死角、全面均匀压实。采用沉降量观测进行质量检测。本试验段纵向平均分为5个断面,每个断面安装两块,从底基层5%石灰土顶开始安装,以上每两层安装一次,共需安装6次,需沉降板60块。测量时将水准仪架在路基外的堆料区旁,测量碾压前的读数,同时在碾压工程中时刻观测读数,当前后两次读数差小于5mm,则说明路基填料的刚度较大,稳定性较好,满足路基填料要求。压前各点读数及最后一次各点读数差值为沉降量。When rolling, first use a sheep foot roller to roll, after the 6th and 10th times, use a grader for rough leveling, and after the 14th time, use a grader for fine leveling. The sheep foot mill is rolled from both sides to the middle, the rolling speed is controlled at about 3km/h, and the wheel tracks overlap by 0.4-0.5m. During the rolling process, always pay attention to the size of the particle diameter of the construction waste. If the particle diameter is found to be less than 3cm after 14 times of rolling, it can be rolled with a light wheel roller; if the particle diameter is found to be more than 3cm after 14 times, You need to continue rolling with a sheep foot roller until the diameter of the particles is below 3cm before rolling with a smooth wheel roller. After the sheep foot roller is rolled, a small amount of uncrushed reinforced concrete blocks are picked out, and they are finely leveled according to the road surface grader. Then use a vibratory roller to roll 10 times. Finally, use a slick wheel roller to roll 10 times, using 1.2km/h for rolling; the rolling speed changes from slow to fast, and the maximum speed does not exceed 4km/h; the rolling is carried out from both sides to the middle, forming a 2-3% road The arched transverse slope is good for drainage; the overlapping width of rolling wheel tracks at the horizontal joints is 40-50cm, and the overlapping width of wheel tracks in the front and rear adjacent construction sections in the longitudinal direction is 100-150cm. Rolling should ensure that there is no pressure leakage, no dead angle, and comprehensive and uniform compaction. Quality inspection is performed by sedimentation observation. The test section is divided into 5 sections on average in the longitudinal direction, and two sections are installed on each section. The installation starts from the top of the 5% lime soil of the subbase, and is installed once every two layers above. A total of 6 installations are required, and 60 settlement plates are required. When measuring, set the level meter next to the stockpiling area outside the roadbed, measure the reading before rolling, and observe the reading at all times during the rolling project. If the difference between the two readings before and after the two readings is less than 5mm, it means that the stiffness of the roadbed filler is large and stable. It has good performance and meets the requirements of roadbed filling. The difference between the readings of each point before pressure and the last reading of each point is the settlement amount.

应当指出的是,以上是本发明的较优实施例,本发明还有其他的实现方式,比如在本发明所述范围内变化其中的工艺参数等。这对于本领域的施工人员来说是很容易实现的。It should be noted that the above are preferred embodiments of the present invention, and the present invention also has other implementation modes, such as changing process parameters within the scope of the present invention. This is easy to implement for construction personnel in the field.

尽管本发明的内容已经通过上述实施例作了详细介绍,但应当认识到上述的描述不应被认为是对本发明的限制。在本领域的施工人员阅读了上述内容后,对于本发明的多种修改和替代都将是显而易见的。因此,本发明的保护范围应由所附的权利要求来限定。Although the content of the present invention has been described in detail through the above embodiments, it should be understood that the above description should not be considered as limiting the present invention. Various modifications and alternatives to the present invention will be apparent to those skilled in the art after reading the foregoing. Therefore, the protection scope of the present invention should be defined by the appended claims.

Claims (12)

1.一种基于建筑垃圾的高速公路路基填筑方法,其特征在于,该方法包括如下步骤:1. A method for filling highway subgrade based on construction waste, characterized in that, the method may further comprise the steps: S1:施工现场预处理;S1: Construction site pretreatment; S2:测量放样;S2: measurement stakeout; S3:基底层处理;S3: Base layer processing; S4:建筑垃圾预处理;S4: Construction waste pretreatment; S5:包边土隔水处理:在左右幅两边用成品石灰土进行包边隔水;S5: water-proof treatment of edge-wrapping soil: use finished lime soil on both sides of the left and right panels for edge-wrapping and water-proofing; S6:建筑垃圾铺设与整平;S6: Laying and leveling of construction waste; S7:对建筑垃圾进行碾压处理,具体步骤如下:S7: Rolling and compacting construction waste, the specific steps are as follows: 碾压前,计算建筑垃圾需补充的水量M,公式如下:Before rolling, calculate the amount of water M water that needs to be supplemented by construction waste, the formula is as follows: M=(W00)×M/(1+ω0)M water = (W 00 )×M/(1+ω 0 ) 式中,W0为实测建筑垃圾含水量、ω0为压实的最佳含水、M为需要补充水分的建筑垃圾质量;In the formula, W 0 is the measured water content of construction waste, ω 0 is the optimal water content for compaction, and M is the quality of construction waste that needs to be supplemented with water; 碾压时,对建筑垃圾补充水量后,首先用羊足碾碾压,在颗粒直径碾到3cm以下后,采用振动压路机碾压8~12遍,最后用光轮压路机以1.0~1.4km/h的速度碾压至少10遍。When rolling, after adding water to the construction waste, firstly roll it with sheep feet, and when the diameter of the particles is less than 3cm, use a vibratory roller to roll it 8 to 12 times, and finally use a bare wheel roller at a speed of 1.0 to 1.4km/h. Speed rolling at least 10 times. 2.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S1施工现场预处理,包括三个部分:一是清理杂物;二是地表排水;三是场地整平。2. The expressway subgrade filling method based on construction waste according to claim 1, characterized in that, said step S1 construction site pretreatment includes three parts: the one is to clean up debris; the other is surface drainage; It's leveling the ground. 3.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S2测量放样,具体是:在原地面进行放样,标识出石灰土铺筑宽度,并设层位杆以控制摊铺厚度。3. The highway subgrade filling method based on construction waste according to claim 1, characterized in that, said step S2 measures stakeout, specifically: stake out on the original ground, mark the lime soil paving width, and set layers Position bar to control pave thickness. 4.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S3基底层处理,具体是:首先对施工作业面的土堆采用推土机摊铺,然后用平地机精平,并用振动压路机进行碾压。4. The expressway subgrade filling method based on construction waste according to claim 1, characterized in that, said step S3 base layer processing, specifically: first adopt bulldozers to pave the mound of the construction work surface, and then use The grader is fine-leveled and the vibratory roller is used for rolling. 5.根据权利要求4所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述碾压的方式如下:由两边向中间进行,横向衔接处碾压轮迹重叠40-50cm,纵向前后相邻施工段轮迹重叠宽度100-150cm。5. The construction waste-based expressway embankment filling method according to claim 4, characterized in that, the rolling method is as follows: from both sides to the middle, and the rolling wheel tracks overlap by 40-50cm at the transverse junction, The overlapping width of the wheel tracks in the front and rear adjacent construction sections in the longitudinal direction is 100-150cm. 6.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S4建筑垃圾预处理,包括两点:一是挑选不适合填筑的杂物;二是将建筑垃圾进行机械破碎,使破碎后粒径小于25cm。6. The highway subgrade filling method based on construction waste according to claim 1, characterized in that, said step S4 construction waste pretreatment includes two points: one is to select sundries that are not suitable for filling; the other is to The construction waste is mechanically crushed so that the particle size after crushing is less than 25cm. 7.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S5包边土松铺系数大于建筑垃圾铺系数的10%-20%,并高出同层建筑垃圾5-8cm。7. The highway subgrade filling method based on construction waste according to claim 1, characterized in that, the step S5 edge-wrapping soil loose paving coefficient is greater than 10%-20% of the construction waste paving coefficient, and higher than the same Layer construction waste 5-8cm. 8.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S6建筑垃圾铺设与整平,具体是,将施工面划分为若干等大方格,并按照填筑高度和面积的乘积推算所需建筑垃圾的方量,确保摊铺时层厚均匀一致;然后,采用挖机粗平后用推土机精平,达到松铺30cm。8. The expressway subgrade filling method based on construction waste according to claim 1, characterized in that, said step S6 construction waste is laid and leveled, specifically, the construction surface is divided into several equal large squares, and According to the product of filling height and area, calculate the amount of construction waste required to ensure that the layer thickness is uniform during paving; then, use an excavator for rough leveling and then use a bulldozer for fine leveling to achieve a loose paving of 30cm. 9.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S7中羊足碾是指由两边向中间碾压,碾压速度控制在2.8~3.2km/h,轮迹重叠0.4~0.5m。9. The construction waste-based expressway embankment filling method according to claim 1, characterized in that, in the step S7, the sheep foot roller refers to rolling from both sides to the middle, and the rolling speed is controlled at 2.8-3.2km /h, wheel tracks overlapping 0.4 ~ 0.5m. 10.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S7中,碾压方式:由两边向中间进行,形成2-3%的路拱横坡;横向衔接处碾压轮迹重叠40-50cm;纵向前后相邻施工段轮迹重叠宽度100-150cm。10. The construction waste-based expressway subgrade filling method according to claim 1, characterized in that, in the step S7, the rolling method is carried out from both sides to the middle to form a 2-3% road crown slope ; The overlap of rolling wheel tracks at the horizontal joint is 40-50cm; the overlapping width of wheel tracks in the longitudinal front and rear adjacent construction sections is 100-150cm. 11.根据权利要求1所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述步骤S7中先安装沉降板,然后将水准仪架在路基外的堆料区旁,分别测量三种压路机对建筑垃圾碾压前和碾压后的高程值的读数,当前后两次读数差小于5mm,则说明路基填料满足要求,填筑结束,否则用光轮压路机继续碾压,直至符合小于5毫米的标准。11. The highway subgrade filling method based on construction waste according to claim 1, characterized in that, in the step S7, a settling plate is first installed, and then the level is placed beside the stockpiling area outside the subgrade to measure three If the difference between the two readings before and after the construction waste is less than 5mm, it means that the subgrade filling meets the requirements and the filling is completed. Otherwise, continue rolling with the smooth roller until it meets the requirements 5 mm standard. 12.根据权利要求10所述的基于建筑垃圾的高速公路路基填筑方法,其特征在于,所述安装沉降板的方法如下:施工场地纵向平分为若干个断面,每个断面安装两块,从底基层开始安装,以上每两层安装一次;安装好沉降板后,即可在之后的碾压中进行沉降测量。12. The expressway subgrade filling method based on construction waste according to claim 10, characterized in that, the method for installing the settling plate is as follows: the construction site is longitudinally divided into several sections, and each section is installed with two pieces, from The base layer is installed first, and the above two layers are installed once; after the settlement plate is installed, the settlement measurement can be carried out in the subsequent rolling.
CN201810533967.4A 2018-05-29 2018-05-29 Express highway roadbed dam filling construction based on building waste Pending CN108677638A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810533967.4A CN108677638A (en) 2018-05-29 2018-05-29 Express highway roadbed dam filling construction based on building waste

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810533967.4A CN108677638A (en) 2018-05-29 2018-05-29 Express highway roadbed dam filling construction based on building waste

Publications (1)

Publication Number Publication Date
CN108677638A true CN108677638A (en) 2018-10-19

Family

ID=63807156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810533967.4A Pending CN108677638A (en) 2018-05-29 2018-05-29 Express highway roadbed dam filling construction based on building waste

Country Status (1)

Country Link
CN (1) CN108677638A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109594442A (en) * 2018-12-14 2019-04-09 北京绿视点园林景观工程有限公司 Garden path construction technology
CN109722968A (en) * 2019-01-10 2019-05-07 江苏工程职业技术学院 A kind of high-performance permeable concrete system and preparation method thereof of building waste preparation
CN109736155A (en) * 2018-11-28 2019-05-10 中交一公局桥隧工程有限公司 Construction method of filling highway roadbed with construction waste
CN110273428A (en) * 2019-07-03 2019-09-24 中电建十一局工程有限公司 It is a kind of using building waste as the construction method for filling materials
CN114717884A (en) * 2022-04-27 2022-07-08 湖南建工交通建设有限公司 Completely weathered granite sedimentary soil subgrade and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101624277A (en) * 2009-08-20 2010-01-13 三门峡豫鑫路桥工程有限责任公司 Roadbed material adopting regenerative raw materials including construction wastes and discarded glass to replace sand and stone
JP2013194403A (en) * 2012-03-19 2013-09-30 Marushima Sangyo Kk Floating tide gate for embankment
CN106758709A (en) * 2016-11-28 2017-05-31 北京市政建设集团有限责任公司 A kind of method for express highway roadbed building castoff breaking, regenerating
CN106988179A (en) * 2017-03-21 2017-07-28 中冶天工集团有限公司 A kind of road structure for preventing salinized soil from corroding and its construction method
CN206666953U (en) * 2016-12-30 2017-11-24 安徽省交通规划设计研究总院股份有限公司 A kind of construction refuse regenerated road structure to gather materials
CN206800094U (en) * 2017-06-20 2017-12-26 河北工业大学 A kind of big particle diameter building waste roadbed

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101624277A (en) * 2009-08-20 2010-01-13 三门峡豫鑫路桥工程有限责任公司 Roadbed material adopting regenerative raw materials including construction wastes and discarded glass to replace sand and stone
JP2013194403A (en) * 2012-03-19 2013-09-30 Marushima Sangyo Kk Floating tide gate for embankment
CN106758709A (en) * 2016-11-28 2017-05-31 北京市政建设集团有限责任公司 A kind of method for express highway roadbed building castoff breaking, regenerating
CN206666953U (en) * 2016-12-30 2017-11-24 安徽省交通规划设计研究总院股份有限公司 A kind of construction refuse regenerated road structure to gather materials
CN106988179A (en) * 2017-03-21 2017-07-28 中冶天工集团有限公司 A kind of road structure for preventing salinized soil from corroding and its construction method
CN206800094U (en) * 2017-06-20 2017-12-26 河北工业大学 A kind of big particle diameter building waste roadbed

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736155A (en) * 2018-11-28 2019-05-10 中交一公局桥隧工程有限公司 Construction method of filling highway roadbed with construction waste
CN109594442A (en) * 2018-12-14 2019-04-09 北京绿视点园林景观工程有限公司 Garden path construction technology
CN109594442B (en) * 2018-12-14 2020-12-11 北京绿视点园林景观工程有限公司 Garden road construction process
CN109722968A (en) * 2019-01-10 2019-05-07 江苏工程职业技术学院 A kind of high-performance permeable concrete system and preparation method thereof of building waste preparation
CN110273428A (en) * 2019-07-03 2019-09-24 中电建十一局工程有限公司 It is a kind of using building waste as the construction method for filling materials
CN114717884A (en) * 2022-04-27 2022-07-08 湖南建工交通建设有限公司 Completely weathered granite sedimentary soil subgrade and construction method
CN114717884B (en) * 2022-04-27 2023-11-24 湖南建工交通建设有限公司 A fully weathered granite sedimentary soil roadbed and construction method

Similar Documents

Publication Publication Date Title
CN108677638A (en) Express highway roadbed dam filling construction based on building waste
CN103774616B (en) From the Ecological Retaining Wall construction method that embedded block is built by laying bricks or stones
CN102587243B (en) Urban road water permeability cement concrete pavement structure and construction process thereof
CN106192907B (en) Add the construction method of 150m~300m grade high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN104264680B (en) The method for processing foundation of Tian Wa joint portion, a kind of collapsible loess slope
CN104878678A (en) Construction method for water-permeable and water-retaining water-permeable pavement structure
CN103352407A (en) Construction process of roadbed structure with sand-based water-permeable bricks
CN107338686A (en) A kind of Subgrade Filled Soil in High Speed Railway construction method
CN104652238B (en) A kind of urban road accessible base layer construction method
CN107761495A (en) A kind of pre-buried expanding bag compensation subgrade settlement construction method
CN114318990A (en) A method of recycling construction waste for road widening
CN106567410A (en) New construction method of municipal road inspection well
CN111778796A (en) A roadbed construction process
CN116377780A (en) Construction Method of High Fill Subgrade in Mountainous Highway
CN103276649A (en) Method for constructing multi-thickness rockfill embankment with lateral confinement and layering functions
CN110080051A (en) A kind of soil engineering bag bridge-type embankment structure and its construction method
CN106592608A (en) Differential settlement control method for new foundation and old roadbed of utility tunnel
CN111021174A (en) Construction method of urban road
CN114908630A (en) Factory road structure and secondary permanent-temporary combined layered construction method
CN118600793A (en) A roadbed fill improvement and construction method in carbonaceous mudstone geological areas
CN109082961B (en) Road construction method with steep slope
CN210529400U (en) A solidified construction waste road structure
CN110273428A (en) It is a kind of using building waste as the construction method for filling materials
CN203096758U (en) Hard concrete smooth foundation pit for installing drainage pipeline
CN112854841B (en) Civil construction structure construction method of bottom mud treatment plant

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181019

WD01 Invention patent application deemed withdrawn after publication
点击 这是indexloc提供的php浏览器服务,不要输入任何密码和下载