CN108612075B - Method for monitoring horizontal displacement of deep foundation pit - Google Patents
Method for monitoring horizontal displacement of deep foundation pit Download PDFInfo
- Publication number
- CN108612075B CN108612075B CN201810489698.6A CN201810489698A CN108612075B CN 108612075 B CN108612075 B CN 108612075B CN 201810489698 A CN201810489698 A CN 201810489698A CN 108612075 B CN108612075 B CN 108612075B
- Authority
- CN
- China
- Prior art keywords
- foundation pit
- point
- line
- monitoring
- horizontal displacement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000006073 displacement reaction Methods 0.000 title claims abstract description 66
- 238000012544 monitoring process Methods 0.000 title claims abstract description 54
- 238000000034 method Methods 0.000 title claims abstract description 30
- 238000010276 construction Methods 0.000 claims description 4
- 238000005259 measurement Methods 0.000 abstract description 5
- 230000001788 irregular Effects 0.000 abstract description 2
- 230000004888 barrier function Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000002271 resection Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D1/00—Investigation of foundation soil in situ
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Analytical Chemistry (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Testing Or Calibration Of Command Recording Devices (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑测量技术领域,具体涉及一种监测深基坑水平位移的方法。The invention relates to the technical field of building measurement, in particular to a method for monitoring the horizontal displacement of a deep foundation pit.
背景技术Background technique
随着我国经济的快速发展,在城市复杂的环境中进行基坑施工,对基坑的支护结构水平位移监测精度要求一般较高。目前,基坑桩顶水平位移监测常用的方法主要有视准线法、小角法、后方交会法、极坐标法等。视准线法和小角法测量简便,计算工作量小,测量精度也较高,但是这些方法往往需要多次设站,耗费时间长,工作量大,效益低,影响精度的不确定因素多,监测人员的监测工作十分繁琐。With the rapid development of my country's economy, foundation pit construction is carried out in a complex urban environment, and the monitoring accuracy of the horizontal displacement of the supporting structure of the foundation pit is generally high. At present, the commonly used methods for monitoring the horizontal displacement of the pile top of the foundation pit mainly include the sight line method, the small angle method, the resection method, and the polar coordinate method. The line-of-sight method and the small-angle method are easy to measure, with small computational workload and high measurement accuracy, but these methods often require multiple station setups, which are time-consuming, labor-intensive, low-efficiency, and have many uncertain factors affecting accuracy. The monitoring work of the monitoring personnel is very cumbersome.
发明内容SUMMARY OF THE INVENTION
针对现有技术存在的问题,本发明提供一种监测深基坑水平位移的方法,无需多次设站,只需在不规则的基坑建立一个矩形基准线,且矩形基准线是围绕整个基坑外侧建立,在利用基准线上的坐标快速、准确地测量出建筑基坑的水平位移,减少设站次数,提高了现场监测效率,同时节约了工程成本。Aiming at the problems existing in the prior art, the present invention provides a method for monitoring the horizontal displacement of a deep foundation pit, which does not need to set up stations many times, but only needs to establish a rectangular reference line in an irregular foundation pit, and the rectangular reference line surrounds the entire foundation pit. The outside of the pit is established, and the horizontal displacement of the building foundation pit can be quickly and accurately measured by using the coordinates on the reference line, which reduces the number of stations set up, improves the efficiency of on-site monitoring, and saves engineering costs.
为了实现上述目的,一种监测深基坑水平位移的方法,包括以下步骤:In order to achieve the above purpose, a method for monitoring the horizontal displacement of a deep foundation pit, comprising the following steps:
步骤1:根据基坑监测规范,在欲施工地点设立两个监测点a和b,通过a、b两点利用全站仪确定平面直角坐标系c;Step 1: According to the foundation pit monitoring specification, set up two monitoring points a and b at the construction site, and use the total station to determine the plane rectangular coordinate system c through the two points a and b;
步骤2:在坐标系c下以基坑为中心,围绕基坑建立矩形基准线o,矩形基准线o上每一点的位置由直角坐标系c确定,在基坑周边已经标注的监测点中任意选择一点k进行监测;Step 2: Take the foundation pit as the center under the coordinate system c, and establish a rectangular reference line o around the foundation pit. The position of each point on the rectangular reference line o is determined by the rectangular coordinate system c, and any monitoring points that have been marked around the foundation pit are determined. Select a point k for monitoring;
步骤3:在建立的矩形基准线o的一条边上选取基准点m,在基准点m通过全站仪进行测量,找到与基准点m所在基准线平行的另一条基准线上的基准点n,基准点m和n的连线与m、n所在基准线垂直;Step 3: Select a reference point m on one side of the established rectangular reference line o, measure at the reference point m with a total station, and find a reference point n on another reference line parallel to the reference line where the reference point m is located, The line connecting the reference points m and n is perpendicular to the reference line where m and n are located;
步骤4:通过全站仪测量计算基坑监测点水平位移所需的参数,包括基准点m与任意点k之间的直线距离L1、基准点n与任意点k之间的直线距离L2、两基准点m与n之间连线和基准点m与任意点k之间连线的夹角α、两基准点m与n之间连线和基准点n与任意点k之间连线的夹角β、基准点m与任意点k位移变化后的点k'之间的直线距离L1'、基准点n与任意点k位移变化后的点k'之间的直线距离L2'、两基准点m与n之间连线和基准点m与任意点k位移变化后的点k'之间连线的夹角α',两基准点m与n之间连线和基准点n与任意点k位移变化后的点k'之间连线的夹角β';Step 4: Measure and calculate the parameters required for the horizontal displacement of the foundation pit monitoring point by the total station measurement, including the straight-line distance L 1 between the reference point m and any point k, and the straight-line distance L 2 between the reference point n and any point k , the included angle α of the line between the two reference points m and n and the line between the reference point m and any point k, the line between the two reference points m and n, and the line between the reference point n and any point k The included angle β, the straight-line distance L 1 ' between the reference point m and the point k' after the displacement of any point k is changed, and the straight-line distance L 2 ' between the reference point n and the point k' after the displacement of the arbitrary point k is changed L 2 ' , the included angle α' of the line between the two reference points m and n and the line between the reference point m and the point k' after the displacement of any point k changes, the line between the two reference points m and n and the reference point n The included angle β' of the line connecting with the point k' after the displacement of any point k is changed;
步骤5:根据步骤4中测量得到的参数,计算基坑监测点水平位移,即基坑的水平位移;Step 5: Calculate the horizontal displacement of the foundation pit monitoring point, that is, the horizontal displacement of the foundation pit according to the parameters measured in step 4;
所述计算基坑监测点水平位移的公式如下:The formula for calculating the horizontal displacement of the foundation pit monitoring point is as follows:
D=(D1+D2)/2;D=(D 1 +D 2 )/2;
S=(S1+S2)/2;S=(S 1 +S 2 )/2;
其中,D1为基坑基准点m垂直基坑边变化的水平位移,D2为基坑基准点n垂直基坑边变化的水平位移,D为基坑基准点垂直基坑边变化的平均水平位移,S1为基坑基准点m平行基坑边变化的水平位移,S2为基坑基准点n平行基坑边变化的水平位移,S为基坑基准点平行基坑边变化的平均水平位移;所述基坑基准点m、n垂直基坑边变化的水平位移和平行基坑边变化的水平位移的计算公式如下:Among them, D 1 is the horizontal displacement of the foundation pit reference point m of the vertical foundation pit side change, D 2 is the foundation pit reference point n The horizontal displacement of the vertical foundation pit side change, D is the average level of the vertical foundation pit side change of the foundation pit reference point Displacement, S1 is the horizontal displacement of the foundation pit reference point m parallel to the side of the foundation pit, S2 is the horizontal displacement of the foundation pit reference point n parallel to the side of the foundation pit, S is the average level of the change of the foundation pit reference point parallel to the side of the foundation pit Displacement; the calculation formulas of the horizontal displacement of the vertical foundation pit side change and the horizontal displacement of the parallel foundation pit side change of the foundation pit reference points m, n are as follows:
D1=(L1cosα-L1'cosα′);D 1 =(L 1 cosα-L 1 'cosα');
D2=(L2cosβ-L2'cosβ′);D 2 =(L 2 cosβ-L 2 'cosβ');
S1=(L1sinα-L1'sinα′);S 1 =(L 1 sinα-L 1 'sinα');
S2=(L2sinβ-L2'sinβ′)。S 2 =(L 2 sinβ-L 2 'sinβ').
本发明的有益效果:Beneficial effects of the present invention:
本发明提出一种监测深基坑水平位移的方法,通过基准点建立坐标系,通过坐标系,以基坑为中心,围绕基坑建立矩形基准线,通过矩形基准线上的基准点和监测点连线与两个基准点连线的角度关系,计算监测点的水平位移,简单、快速、易行,本方法可以在矩形基准线上任意设立监测点,并且可以随意切换监测点,不受障碍物限制,对于大多数基坑均适用,大大提高了不规则形状基坑的监测效率,相对小角度法的多次设站、角度限制,本方法更具有优越性,另外,本方法通过测量计算取均值的方式,大大提高准确度。The invention proposes a method for monitoring the horizontal displacement of a deep foundation pit. A coordinate system is established through a reference point, a rectangular reference line is established around the foundation pit with the foundation pit as the center through the coordinate system, and a reference point and a monitoring point on the rectangular reference line are passed. The angle relationship between the connection line and the line connecting the two reference points is simple, fast and easy to calculate the horizontal displacement of the monitoring point. This method can arbitrarily set up monitoring points on the rectangular reference line, and can switch the monitoring points at will without obstacles. It is applicable to most foundation pits, which greatly improves the monitoring efficiency of irregular-shaped foundation pits. Compared with the multiple station setting and angle limitation of the small-angle method, this method is more advantageous. In addition, this method is calculated by measuring and calculating The method of taking the mean value greatly improves the accuracy.
附图说明Description of drawings
图1为本发明实施例中监测深基坑水平位移的方法流程图;Fig. 1 is the method flow chart of monitoring the horizontal displacement of deep foundation pit in the embodiment of the present invention;
图2为本发明实施例中监测深基坑水平位移的现场监测示意图。FIG. 2 is a schematic diagram of on-site monitoring for monitoring the horizontal displacement of a deep foundation pit in an embodiment of the present invention.
具体实施方式Detailed ways
为了使本发明的目的、技术方案及优势更加清晰,下面结合附图和具体实施例对本发明做进一步详细说明。此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. The specific embodiments described herein are only used to explain the present invention, and are not intended to limit the present invention.
一种监测深基坑水平位移的方法,流程如图1所示,现场监测示意图如图2所示,具体方法如下所述:A method for monitoring the horizontal displacement of a deep foundation pit, the process is shown in Figure 1, and the schematic diagram of on-site monitoring is shown in Figure 2. The specific method is as follows:
步骤1:根据基坑监测规范,在欲施工地点设立两个监测点a和b,通过a、b两点利用全站仪确定平面直角坐标系c。Step 1: According to the foundation pit monitoring specification, set up two monitoring points a and b at the construction site, and use the total station to determine the plane rectangular coordinate system c through the two points a and b.
步骤2:在坐标系c下以基坑为中心,围绕基坑建立矩形基准线o,矩形基准线o上每一点的位置由直角坐标系c确定,在基坑周边已经标注的监测点中任意选择一点k进行监测;Step 2: Take the foundation pit as the center under the coordinate system c, and establish a rectangular reference line o around the foundation pit. The position of each point on the rectangular reference line o is determined by the rectangular coordinate system c, and any monitoring points that have been marked around the foundation pit are determined. Select a point k for monitoring;
步骤3:在建立的矩形基准线o的一条边上选取基准点m,在基准点m通过全站仪进行测量,找到与基准点m所在基准线平行的另一条基准线上的基准点n,基准点m和n的连线与m、n所在基准线垂直。Step 3: Select a reference point m on one side of the established rectangular reference line o, measure at the reference point m with a total station, and find a reference point n on another reference line parallel to the reference line where the reference point m is located, The line connecting the reference points m and n is perpendicular to the reference line where m and n are located.
步骤4:通过全站仪测量计算基坑监测点水平位移所需的参数,包括基准点m与任意点k之间的直线距离L1、基准点n与任意点k之间的直线距离L2、两基准点m与n之间连线和基准点m与任意点k之间连线的夹角α、两基准点m与n之间连线和基准点n与任意点k之间连线的夹角β、基准点m与任意点k位移变化后的点k'之间的直线距离L1'、基准点n与任意点k位移变化后的点k'之间的直线距离L2'、两基准点m与n之间连线和基准点m与任意点k位移变化后的点k'之间连线的夹角α',两基准点m与n之间连线和基准点n与任意点k位移变化后的点k'之间连线的夹角β'。Step 4: Measure and calculate the parameters required for the horizontal displacement of the foundation pit monitoring point by the total station measurement, including the straight-line distance L 1 between the reference point m and any point k, and the straight-line distance L 2 between the reference point n and any point k , the included angle α of the line between the two reference points m and n and the line between the reference point m and any point k, the line between the two reference points m and n, and the line between the reference point n and any point k The included angle β, the straight-line distance L 1 ' between the reference point m and the point k' after the displacement of any point k is changed, and the straight-line distance L 2 ' between the reference point n and the point k' after the displacement of the arbitrary point k is changed L 2 ' , the included angle α' of the line between the two reference points m and n and the line between the reference point m and the point k' after the displacement of any point k changes, the line between the two reference points m and n and the reference point n The included angle β' of the line connecting with the point k' after the displacement of any point k is changed.
步骤5:根据步骤4中测量得到的参数,计算基坑监测点水平位移,即基坑的水平位移。Step 5: According to the parameters measured in Step 4, calculate the horizontal displacement of the monitoring point of the foundation pit, that is, the horizontal displacement of the foundation pit.
所述计算基坑监测点水平位移的公式如公式(1)和公式(2)所示:The formula for calculating the horizontal displacement of the monitoring point of the foundation pit is shown in formula (1) and formula (2):
D=(D1+D2)/2 (1)D=(D 1 +D 2 )/2 (1)
S=(S1+S2)/2 (2)S=(S 1 +S 2 )/2 (2)
其中,D1为基坑基准点m垂直基坑边变化的水平位移,D2为基坑基准点n垂直基坑边变化的水平位移,D为基坑基准点垂直基坑边变化的平均水平位移,S1为基坑基准点m平行基坑边变化的水平位移,S2为基坑基准点n平行基坑边变化的水平位移,S为基坑基准点平行基坑边变化的平均水平位移;所述基坑基准点m、n垂直基坑边变化的水平位移和平行基坑边变化的水平位移的计算公式如公式(3)-公式(6)所示:Among them, D 1 is the horizontal displacement of the foundation pit reference point m of the vertical foundation pit side change, D 2 is the foundation pit reference point n The horizontal displacement of the vertical foundation pit side change, D is the average level of the vertical foundation pit side change of the foundation pit reference point Displacement, S1 is the horizontal displacement of the foundation pit reference point m parallel to the side of the foundation pit, S2 is the horizontal displacement of the foundation pit reference point n parallel to the side of the foundation pit, S is the average level of the change of the foundation pit reference point parallel to the side of the foundation pit Displacement; the calculation formulas of the horizontal displacement of the vertical foundation pit side change and the horizontal displacement of the parallel foundation pit side change of the foundation pit reference points m and n are shown in formula (3)-formula (6):
D1=(L1cosα-L1'cosα′) (3)D 1 =(L 1 cosα-L 1 'cosα′) (3)
D2=(L2cosβ-L2'cosβ′) (4)D 2 =(L 2 cosβ-L 2 'cosβ') (4)
S1=(L1sinα-L1'sinα′) (5)S 1 =(L 1 sinα-L 1 'sinα') (5)
S2=(L2sinβ-L2'sinβ′) (6)S 2 =(L 2 sinβ-L 2 'sinβ') (6)
由步骤4可知,本实施例只需测量4条边长及4个夹角的度数,带入公式(3)-公式(6)即可根据公式(1)和公式(2)得到基坑的水平位移,简单、快速、易行,大大提高了不规则形状基坑的监测效率,相对小角度法的多次设站、角度限制,本方法更具有优越性。As can be seen from step 4, the present embodiment only needs to measure the degree of 4 side lengths and 4 included angles, and brings into formula (3)-formula (6) to obtain the foundation pit according to formula (1) and formula (2). The horizontal displacement is simple, fast and easy to implement, which greatly improves the monitoring efficiency of irregular-shaped foundation pits. Compared with the multiple station setting and angle limitation of the small-angle method, this method is more advantageous.
最后应说明的是:以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解;其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;因而这些修改或者替换,并不使相应技术方案的本质脱离本发明权利要求所限定的范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand; The technical solutions described in the foregoing embodiments are modified, or some or all of the technical features thereof are equivalently replaced; therefore, these modifications or replacements do not make the essence of the corresponding technical solutions depart from the scope defined by the claims of the present invention.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810489698.6A CN108612075B (en) | 2018-05-21 | 2018-05-21 | Method for monitoring horizontal displacement of deep foundation pit |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810489698.6A CN108612075B (en) | 2018-05-21 | 2018-05-21 | Method for monitoring horizontal displacement of deep foundation pit |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN108612075A CN108612075A (en) | 2018-10-02 |
| CN108612075B true CN108612075B (en) | 2020-07-07 |
Family
ID=63663977
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810489698.6A Expired - Fee Related CN108612075B (en) | 2018-05-21 | 2018-05-21 | Method for monitoring horizontal displacement of deep foundation pit |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108612075B (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111457848B (en) * | 2020-05-19 | 2022-02-01 | 四川合众精准科技有限公司 | Method and system for measuring displacement through coordinate change between adjacent monitoring points |
| CN111664793B (en) * | 2020-06-15 | 2021-11-09 | 衡橡科技股份有限公司 | Building movement track monitoring method |
| CN112325856B (en) * | 2020-11-13 | 2024-07-23 | 湖南联智科技股份有限公司 | Method and device for continuously monitoring change of verticality of structure |
| CN113804148B (en) * | 2021-08-04 | 2024-04-19 | 吉林建筑科技学院 | Dynamic reference-based measurement adjustment method |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001289956A (en) * | 2000-04-04 | 2001-10-19 | Taisei Corp | Ground displacement measuring method |
| CN102628281A (en) * | 2012-04-10 | 2012-08-08 | 长沙理工大学 | Horizontal displacement monitoring method for measuring point in foundation pit engineering |
| CN103526783B (en) * | 2013-10-21 | 2015-11-04 | 中航勘察设计研究院有限公司 | A kind of method measuring building foundation pit horizontal movement |
| CN104988928B (en) * | 2015-05-25 | 2017-01-25 | 浙江省围海建设集团股份有限公司 | Method of Real-time Monitoring Horizontal Displacement of Foundation Pit Excavation Based on Digital Image |
| CN105606066A (en) * | 2016-03-12 | 2016-05-25 | 中国水利水电第七工程局有限公司 | Foundation pit supporting structure deep level displacement monitoring system and method |
| CN105806226A (en) * | 2016-03-24 | 2016-07-27 | 中国科学院半导体研究所 | Method for remotely measuring horizontal displacement of roadbed through lasers |
-
2018
- 2018-05-21 CN CN201810489698.6A patent/CN108612075B/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| CN108612075A (en) | 2018-10-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108612075B (en) | Method for monitoring horizontal displacement of deep foundation pit | |
| CN108827230B (en) | Ultra-wide water area precise river crossing leveling device and method | |
| CN113124782B (en) | Construction perpendicularity detection method based on point cloud tolerance self-adaption | |
| CN113267156B (en) | Method and system for measuring flatness of cement floor by using inertial navigation | |
| WO2017201812A1 (en) | Method for acquiring canal flow rate | |
| CN109443476B (en) | A non-contact measuring device and method for water level fluctuation process | |
| CN105091838B (en) | A kind of long distance water transfer channel roughness prototype measurement assay method | |
| CN106895819A (en) | A kind of total powerstation high accuracy Trigonometric Leveling | |
| CN109765592B (en) | A kind of Deformation Control Net method for analyzing stability based on variance-covariance matrix | |
| CN111521148B (en) | Method for rapidly measuring plane coordinates of reference points on tower column | |
| CN112902934B (en) | A GPS-EJA-based Geometrical Attitude Test Method for Caisson | |
| CN104048605A (en) | Laser scanning measurement target adjustment equation establishing method | |
| CN104897059A (en) | Portable irregular accumulation body volume measurement method | |
| CN109282817A (en) | A multi-robot cooperative positioning and control method | |
| CN101216546A (en) | A Position Estimation Method for Target Location in Wireless Sensor Networks | |
| CN110631564A (en) | A method for measuring the inclination of a cylinder with a circular section | |
| CN205748193U (en) | A kind of portable deck-siding survey tool | |
| CN109883327B (en) | Track frame system monitoring method | |
| CN110424201B (en) | Calculation method for measuring unknown points of high-speed railway track in uneven state | |
| CN204753558U (en) | Foundation ditch horizontal displacement monitoring devices | |
| CN208968545U (en) | Auxiliary measuring device for camber nodes and camber vertices of circular tube structures | |
| CN111721272A (en) | An Engineering Surface Measurement Method Based on Ellipsoid Calculation | |
| CN106949886B (en) | Rapid positioning device and positioning method for subway tunnel engineering line measuring point positions | |
| CN216523637U (en) | Flatness detection device for building engineering | |
| CN113503865B (en) | Three-dimensional control network establishment method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200707 Termination date: 20210521 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |