CN106644206A - Method for calculating surrounding rock pressure of shallow tunnel - Google Patents
Method for calculating surrounding rock pressure of shallow tunnel Download PDFInfo
- Publication number
- CN106644206A CN106644206A CN201610958955.7A CN201610958955A CN106644206A CN 106644206 A CN106644206 A CN 106644206A CN 201610958955 A CN201610958955 A CN 201610958955A CN 106644206 A CN106644206 A CN 106644206A
- Authority
- CN
- China
- Prior art keywords
- alpha
- load
- tunnel
- surrounding rock
- pressure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011435 rock Substances 0.000 title claims abstract description 100
- 238000000034 method Methods 0.000 title claims abstract description 40
- 238000006073 displacement reaction Methods 0.000 claims abstract description 60
- 238000012544 monitoring process Methods 0.000 claims abstract description 52
- 238000004364 calculation method Methods 0.000 claims abstract description 44
- 230000014509 gene expression Effects 0.000 claims abstract description 5
- 238000005452 bending Methods 0.000 claims description 24
- 238000009412 basement excavation Methods 0.000 claims description 9
- 239000000463 material Substances 0.000 claims description 6
- 230000000694 effects Effects 0.000 claims description 4
- 238000007596 consolidation process Methods 0.000 claims description 3
- 238000005259 measurement Methods 0.000 claims description 2
- 238000000205 computational method Methods 0.000 claims 10
- 101100042630 Caenorhabditis elegans sin-3 gene Proteins 0.000 claims 3
- 238000000354 decomposition reaction Methods 0.000 claims 1
- 239000004744 fabric Substances 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 13
- 238000013461 design Methods 0.000 description 8
- 238000010586 diagram Methods 0.000 description 8
- 238000004458 analytical method Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009795 derivation Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01L—MEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
- G01L1/00—Measuring force or stress, in general
- G01L1/26—Auxiliary measures taken, or devices used, in connection with the measurement of force, e.g. for preventing influence of transverse components of force, for preventing overload
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明涉及隧道工程技术领域。本发明的一种用于浅埋隧道的围岩压力计算方法,包括步骤:选取围岩的收敛变形监测点;在监测点构造结构力学模型;推导收敛变形与围岩压力之间的计算关系式;将工程实际数据与收敛监测数据带入关系式计算监测点左、右两侧的位移量,及监测点的收敛变形;计算得出围岩计算摩擦角与围岩压力。该方法通过分析双侧壁导坑法隧道施工中侧壁围岩的收敛变形与围岩压力之间的关系,建立结构力学模型,由现场监测数据反算求得围岩压力,相较于现有依赖经验参数的计算方法,更准确、更能代表隧道的实际围岩压力,且隧道的收敛变形数据更易获得、计算方便精确。
The invention relates to the technical field of tunnel engineering. A method for calculating surrounding rock pressure for shallow buried tunnels of the present invention comprises the steps of: selecting a monitoring point for convergent deformation of surrounding rock; constructing a structural mechanics model at the monitoring point; deriving a calculation relational expression between the convergent deformation and surrounding rock pressure ; Bring the actual engineering data and convergence monitoring data into the relationship formula to calculate the displacement on the left and right sides of the monitoring point, and the convergence deformation of the monitoring point; calculate the friction angle and pressure of the surrounding rock. This method establishes a structural mechanics model by analyzing the relationship between the convergence deformation of the surrounding rock of the side wall and the pressure of the surrounding rock in the tunnel construction of the double-side-wall pilot tunnel method, and then calculates the surrounding rock pressure from the on-site monitoring data. There is a calculation method that relies on empirical parameters, which is more accurate and can better represent the actual surrounding rock pressure of the tunnel, and the convergence deformation data of the tunnel is easier to obtain and the calculation is convenient and accurate.
Description
技术领域technical field
本发明涉及隧道工程技术领域,特别涉及一种用于浅埋隧道的围岩压力计算方法。The invention relates to the technical field of tunnel engineering, in particular to a method for calculating surrounding rock pressure for shallow buried tunnels.
背景技术Background technique
围岩压力是岩体受扰动产生应力重分配过程中的围岩变形受到支护结构的阻挡而在支护与围岩的接触面上所产生的压力,它直接影响到隧道的结构设计与施工方法的选择。浅埋隧道由于埋深较浅,开挖所造成的影响将更为直接的影响到地表及周边建筑。Surrounding rock pressure is the pressure generated on the contact surface between the support and the surrounding rock when the deformation of the surrounding rock is blocked by the support structure during the stress redistribution process caused by the disturbance of the rock mass. It directly affects the structural design and construction of the tunnel. Choice of method. Due to the shallow buried depth of shallow tunnels, the impact caused by excavation will more directly affect the surface and surrounding buildings.
隧道开挖引起的围岩压力受多种因素的影响,不仅与岩体结构、地质构造、岩石物理力学性质、地下水、初始地应力等地质因素有关,还与洞室形状、尺寸大小、开挖施工方法、支护形式等工程活动造成的人为因素有关。在隧道工程实践中,准确预测隧道开挖引起的围岩压力对于隧道施工的顺利推进有重要意义。The surrounding rock pressure caused by tunnel excavation is affected by many factors, not only related to geological factors such as rock mass structure, geological structure, rock physical and mechanical properties, groundwater, initial in-situ stress, but also related to the shape, size, and excavation pressure of the cavern. It is related to human factors caused by engineering activities such as construction methods and support forms. In tunnel engineering practice, accurate prediction of surrounding rock pressure caused by tunnel excavation is of great significance for the smooth progress of tunnel construction.
经验公式法是目前应用广泛和发展较为成熟的确定围岩压力方法,它是以大量实际工程资料为基础,按不同围岩级别提出的经验总结,它便于工程技术人员方便快捷地求得围岩压力的大小和分布模式。如目前国内应用最广的《公路隧道设计规范》、《铁路隧道设计规范》中的围岩压力计算公式就是依据大量以往工程实例分析得到经验参数进行计算求得围岩压力。但是经验公式法还是存在一些局限性:经验公式法中的计算参数取值所参考的工程实例只能代表有限的工程地质情况,且随着设计与施工技术水平的发展进步,隧道施工地质条件越来越复杂,工程实际中的工程地质条件有其特殊性,在这种情况下采用传统经验公式法无法得到较为准确的围岩压力值。The empirical formula method is a widely used and relatively mature method for determining the surrounding rock pressure. It is based on a large number of actual engineering data and is based on experience summed up according to different surrounding rock levels. It is convenient for engineering and technical personnel to obtain the surrounding rock pressure quickly and conveniently. The magnitude and distribution pattern of the pressure. For example, the calculation formulas of surrounding rock pressure in "Code for Design of Highway Tunnel" and "Code for Design of Railway Tunnel" which are widely used in China at present are calculated based on the empirical parameters obtained from the analysis of a large number of previous engineering examples to obtain the surrounding rock pressure. However, the empirical formula method still has some limitations: the engineering examples referred to in the empirical formula method can only represent limited engineering geological conditions, and with the development and progress of design and construction technology, the geological conditions of tunnel construction are getting worse. The engineering geological conditions in engineering practice are more and more complex, and the engineering geological conditions in engineering practice have their own particularities. In this case, it is impossible to obtain more accurate surrounding rock pressure values by using the traditional empirical formula method.
发明内容Contents of the invention
本发明的目的在于克服采用经验公式法确定隧道围岩压力时,所依据的经验参数并不能很好的代表隧道的力学性质,因此采用传统经验公式法无法得到准确的围岩压力值的技术问题,提供一种用于浅埋隧道的围岩压力计算方法,该方法通过分析双侧壁导坑法隧道施工中侧壁围岩的收敛变形与围岩压力之间的关系,建立结构力学模型,由现场监测数据反算求得围岩压力,相较于现有依赖经验参数的计算方法,更准确、更能代表隧道的实际围岩压力,且隧道的收敛变形数据更易获得、计算方便精确。The purpose of the present invention is to overcome the technical problem that when the empirical formula method is used to determine the surrounding rock pressure of the tunnel, the empirical parameters based on it cannot well represent the mechanical properties of the tunnel, so the traditional empirical formula method cannot obtain accurate surrounding rock pressure values. , providing a calculation method for surrounding rock pressure in shallow tunnels, the method establishes a structural mechanics model by analyzing the relationship between the convergence deformation of the side wall surrounding rock and the pressure of the surrounding rock in the tunnel construction of the double side wall pilot tunnel method, Compared with the existing calculation methods that rely on empirical parameters, the surrounding rock pressure obtained by inverse calculation from on-site monitoring data is more accurate and can better represent the actual surrounding rock pressure of the tunnel, and the convergence deformation data of the tunnel is easier to obtain and the calculation is convenient and accurate.
为了实现上述发明目的,本发明提供了以下技术方案:In order to realize the above-mentioned purpose of the invention, the present invention provides the following technical solutions:
一种用于浅埋隧道的围岩压力计算方法,包括以下步骤:A method for calculating surrounding rock pressure for shallow buried tunnels, comprising the following steps:
(1)选取围岩的收敛变形监测点:对采用双侧壁导坑法施工的隧道进行研究分析,选取按开挖顺序最先开挖的导洞上的点为收敛变形监测点;(1) Select the convergence deformation monitoring point of the surrounding rock: conduct research and analysis on the tunnel constructed by the double-side-wall pilot tunnel method, and select the point on the pilot tunnel excavated first according to the excavation sequence as the convergence deformation monitoring point;
(2)在监测点构造结构力学模型;按实际先行开挖导洞处构造结构力学模型;(2) Construct a structural mechanics model at the monitoring point; construct a structural mechanics model at the pilot tunnel according to the actual situation;
(3)推导收敛变形与围岩压力之间的计算关系式;(3) Deduce the calculation relationship between the convergence deformation and the surrounding rock pressure;
(4)将工程实际数据与收敛监测数据带入步骤(3)的关系式中,分别计算监测点左、右两侧的位移量,及监测点的收敛变形;(4) Bring the actual engineering data and the convergence monitoring data into the relational formula in step (3), and calculate the displacement on the left and right sides of the monitoring point and the convergence deformation of the monitoring point respectively;
(5)计算得出围岩计算摩擦角与围岩压力;(5) Calculate the calculated friction angle and surrounding rock pressure of surrounding rock;
该方法通过分析双侧壁导坑法隧道施工中侧壁围岩的收敛变形与围岩压力之间的关系,建立结构力学模型,由现场监测数据反算求得水平围岩压力与垂直围岩压力,相较于现有依赖经验参数的计算方法,更准确、更能代表隧道的实际围岩压力,且隧道的收敛变形数据更易获得、计算方便精确。This method analyzes the relationship between the convergence deformation of the side wall surrounding rock and the pressure of the surrounding rock in the tunnel construction of the double side wall pilot pit method, establishes a structural mechanics model, and obtains the horizontal surrounding rock pressure and the vertical surrounding rock pressure from the on-site monitoring data. Compared with the existing calculation methods that rely on empirical parameters, the pressure is more accurate and can better represent the actual surrounding rock pressure of the tunnel, and the convergence deformation data of the tunnel is easier to obtain and the calculation is convenient and accurate.
作为优选,步骤(2)中选取左导坑上台阶或右导坑上台阶进行分析,构造力学模型。根据实际施工经验,最先开挖的左导坑或右导坑上台阶施工后,其收敛变形一周内稳步增加,一周后收敛速度放缓,两周之后基本稳定,因此可以取左导坑与右导坑掌子面中间的一个监测点,一到两周内监测数据基本稳定之后的其收敛变形能代表围岩压力作用产生的变形收敛。As a preference, in step (2), the upper step of the left pilot pit or the upper step of the right pilot pit is selected for analysis and a mechanical model is constructed. According to actual construction experience, after the construction of the first left pilot pit or right pilot pit, the convergence deformation increases steadily within a week, the convergence speed slows down after one week, and basically stabilizes after two weeks. Therefore, the left pilot pit and the right pilot pit can be taken as At a monitoring point in the middle of the face of the right pilot pit, the convergence deformation after the monitoring data is basically stable within one to two weeks can represent the deformation convergence caused by the surrounding rock pressure.
作为优选,建立模型时做以下假设:将左导坑上台阶或右导坑上台阶视为扇形;上台阶右壁及圆拱部分简化为刚性材料;简化模型各节点视为刚性连接。As a preference, the following assumptions are made when building the model: the upper step of the left pilot pit or the upper step of the right pilot pit is regarded as a sector; the right wall and round arch of the upper step are simplified as rigid materials; each node of the simplified model is regarded as a rigid connection.
作为优选,将监测点两侧分别视为超静定梁和超静定拱进行分析,分别计算超静定梁和超静定拱的位移量来得到监测点的收敛变形。Preferably, both sides of the monitoring point are regarded as statically indeterminate beams and statically indeterminate arches for analysis, and the displacements of the statically indeterminate beams and statically indeterminate arches are calculated respectively to obtain the convergent deformation of the monitoring points.
作为优选,监测点的超静定梁的位移计算包括以下步骤:Preferably, the displacement calculation of the statically indeterminate beam at the monitoring point includes the following steps:
(1)首先分析超静定梁所受荷载:超静定梁所受荷载ql为水平荷载qs和垂直荷载qc在垂直于梁方向的分量之和,即ql=qs·sinα+qc·cosα,并将荷载ql分为均布荷载ql1、线性荷载ql2,其中α为扇形的两半径之间的夹角;由于梁两端为固结,不受轴向荷载影响,故只考虑水平荷载和垂直荷载在垂直于梁方向荷载的作用;(1) First analyze the load on the statically indeterminate beam: the load on the statically indeterminate beam q l is the sum of the components of the horizontal load q s and the vertical load q c in the direction perpendicular to the beam, that is, q l = q s sinα +q c ·cosα, and divide the load q l into uniform load q l1 and linear load q l2 , where α is the angle between the two radii of the sector; since both ends of the beam are consolidated, no axial load Therefore, only the effect of horizontal load and vertical load on the load perpendicular to the beam direction is considered;
(2)分别列出荷载ql1、ql2的计算式;(2) List the calculation formulas of loads q l1 and q l2 respectively;
(3)利用结构力学的力法原理计算超静定梁上的弯矩计算式;(3) Using the force method principle of structural mechanics to calculate the calculation formula of the bending moment on the statically indeterminate beam;
(4)结合荷载和弯矩计算式分别得到监测点受荷载ql1、ql2的位移计算式,将实测的隧道压力数据带入计算式,分别得到荷载的位移量;(4) Combining the load and bending moment calculation formulas to obtain the displacement calculation formulas of the monitoring point under the load q l1 and q l2 respectively, and bring the measured tunnel pressure data into the calculation formula to obtain the displacement of the load respectively;
(5)得到超静定梁的总位移量ωl。(5) Obtain the total displacement ω l of the statically indeterminate beam.
作为优选,上述步骤(2)中计算时:将沿超静定梁的方向定义为x方向,与其垂直方向为y方向;As preferably, when calculating in the above-mentioned step (2): the direction along the statically indeterminate beam is defined as the x direction, and the direction perpendicular to it is the y direction;
(1)计算ql1时:(1) When calculating q l1 :
按结构力学的力法原理计算超静定梁在x方向上任意位置的弯矩:According to the force method principle of structural mechanics, calculate the bending moment of the statically indeterminate beam at any position in the x direction:
式中r为扇形的半径,M(x)为x方向的弯矩; In the formula, r is the radius of the sector, and M(x) is the bending moment in the x direction;
根据材料力学中弯矩与挠度的关系式:其中EI为常数,ω为变形量;According to the relationship between bending moment and deflection in material mechanics: Where EI is a constant, ω is the amount of deformation;
对弯矩求二重积分得到:Double integrating the bending moment yields:
ωl1(x)·EI=∫∫[M(x)dx]dx+C1x+D1,式中ωl1(x)为监测点受ql1荷载在y方向上的位移量,由于梁与拱为固结,所以ω(0)=0、ω(r)=0,代入上式计算可得:ω l1 (x)·EI=∫∫[M(x)dx]dx+C 1 x+D 1 , where ω l1 (x) is the displacement of the monitoring point in the y direction under the q l1 load, because the beam It is consolidated with the arch, so ω(0)=0, ω(r)=0, which can be calculated by substituting into the above formula:
而ql1=qc·cosα+e1sinα,其中e1为隧道顶水平侧压力/kPa,得出ql1的值,进而得出在荷载ql1作用下超静定梁的位移量ωl1; And q l1 = q c ·cosα+e 1 sinα, where e 1 is the horizontal lateral pressure of the tunnel top/kPa, the value of q l1 is obtained, and then the displacement of the statically indeterminate beam under the load q l1 is obtained ω l1 ;
(2)计算ql2的值:(2) Calculate the value of q l2 :
按结构力学的力法原理计算超静定梁上任意位置x处的弯矩:Calculate the bending moment at any position x on the statically indeterminate beam according to the force method principle of structural mechanics:
对弯矩求二重积分可得: Taking the double integral over the bending moment gives:
式中ωl2(x)为监测点受ql2荷载在y方向上的位移量;而ql2=(e2-e1)·sinα,式中e2为隧道底水平侧压力/kPa,得出在荷载ql2作用下超静定梁的位移量; In the formula, ω l2 (x) is the displacement of the monitoring point in the y direction under the q l2 load; and q l2 = (e 2 -e 1 ) sinα, where e 2 is the horizontal side pressure of the tunnel bottom/kPa, Get the displacement of the statically indeterminate beam under the action of load q l2 ;
该计算过程中,ql1、ql2的位移量均由实测隧道数据反算得出,即将实测的e1隧道顶水平侧压力、e2隧道底水平侧压力带入推导公式中,得到荷载ql1和ql2值,进而分别得到超静定梁受荷载ql1、ql2的位移量,得到超静定梁的位移量,为计算监测点的位移量打下基础,实测的数据来计算的超静定梁的位移量较传统依靠经验公式法计算的方式更为准确可靠,适应性更广。In this calculation process, the displacements of q l1 and q l2 are obtained by inverse calculation from the measured tunnel data, that is, the measured horizontal lateral pressure at the top of the tunnel at e1 and the horizontal lateral pressure at the bottom of the tunnel at e2 are brought into the derivation formula to obtain the load q l1 and q l2 values, and then obtain the displacement of the super statically indeterminate beam under the load q l1 and q l2 respectively, and obtain the displacement of the super statically indeterminate beam, which lays the foundation for calculating the displacement of the monitoring point. The measured data is used to calculate the super static The displacement of the fixed beam is more accurate and reliable than the traditional calculation method relying on empirical formulas, and has wider adaptability.
作为优选,监测点的超静定拱的位移计算包括以下步骤:Preferably, the displacement calculation of the hyperstatically indeterminate arch at the monitoring point includes the following steps:
(1)将超静定拱所受水平方向荷载分解为均布荷载q1、线性荷载q2,还包括竖直方向的荷载q3;将超静定拱与水平面的交点受到的水平方向的约束荷载记为x3,竖直方向荷载记为x2,该交点收到的扭矩记为x1;(1) decompose the horizontal load on the statically indeterminate arch into uniform load q 1 , linear load q 2 , and also include the vertical load q 3 ; The restraint load is recorded as x 3 , the vertical load is recorded as x 2 , and the torque received at the intersection point is recorded as x 1 ;
(2)根据超静定拱与水平面的交点为刚性连接节点,得出该交点在三个方向上的单位荷载作用下的位移关系;(2) According to the intersection of the statically indeterminate arch and the horizontal plane as a rigid connection node, the displacement relationship of the intersection point under the action of unit load in three directions is obtained;
(3)列出超静定拱与水平面的交点在三个方向荷载作用下的位移关系式;(3) List the displacement relational expressions of the intersection of the statically indeterminate arch and the horizontal plane under loads in three directions;
(4)列出超静定拱上任意点的弯矩计算式;(4) List the calculation formula of bending moment at any point on the statically indeterminate arch;
(5)由于梁与拱为固结,将坐标点的数据带入上式得到超静定拱的位移量ωg。(5) Since the beam and the arch are consolidated, bring the data of the coordinate points into the above formula to obtain the displacement ω g of the statically indeterminate arch.
作为优选,上述步骤(2)中根据模型的刚性连接点可得出:As preferably, in the above-mentioned step (2), it can be drawn according to the rigid connection point of the model:
式中Δiq为由荷载q产生的沿xi方向的位移,δij为由单位力xj=1产生的沿xi方向的位移,其中i=1、2或3,j=1、2或3,且根据该刚性连接点的特性,δ12=δ21、δ13=δ31、δ23=δ32; In the formula, Δiq is the displacement along the direction of x i produced by the load q, and δ ij is the displacement along the direction of x i produced by the unit force x j =1, where i=1, 2 or 3, j=1, 2 or 3, and according to the characteristics of the rigid connection point, δ 12 =δ 21 , δ 13 =δ 31 , δ 23 =δ 32 ;
而计算超静定拱任意点的位移δij时:And when calculating the displacement δ ij of any point of the statically indeterminate arch:
式中r为扇形半径,α为扇形的两半径之间的夹角; In the formula, r is the radius of the sector, and α is the angle between the two radii of the sector;
而分别计算在荷载q1、q2、q3作用下的位移Δiq:And calculate the displacement Δiq under the action of loads q 1 , q 2 , q 3 respectively:
利用上式可求得荷载q1、q2、q3作用下的约束x1、x2、x3,然后可求得拱上任意点的弯矩:The constraints x 1 , x 2 , x 3 under the loads q 1 , q 2 , q 3 can be obtained by using the above formula, and then the bending moment at any point on the arch can be obtained:
, ,
对弯矩M(x)求二重积分可得:The double integral of the bending moment M(x) can be obtained:
式中(即为0到α之间的一个值),C2为、D2为对弯矩求二重积分过程中产生的常系数; In the formula ( which is is a value between 0 and α), C 2 and D 2 are constant coefficients generated during the double integral process of bending moment;
将ω(0)=0、ω(α)=0代入上式,可求得C2、D2,得出超静定拱的位移量ωg。By substituting ω(0)=0 and ω(α)=0 into the above formula, C 2 and D 2 can be obtained, and the displacement ω g of the hyperstatic definite arch can be obtained.
作为优选,监测点的收敛变形为超静定梁与超静定拱的位移变形之和:ω=ωl·sinα+ωg。Preferably, the convergent deformation of the monitoring point is the sum of the displacement deformations of the statically indeterminate beam and the statically indeterminate arch: ω=ω l ·sinα+ω g .
作为优选,计算摩擦角时:As a preference, when calculating the friction angle:
(1)首先判断隧道是否为浅埋隧道,根据收敛变形ω及现场数据确定围岩级别;(1) First judge whether the tunnel is a shallow buried tunnel, and determine the surrounding rock level according to the convergence deformation ω and field data;
(2)为浅埋隧道时,计算其垂直围岩压力q:式中q为垂直均布荷载/kN·m-2,γ为隧道上覆围岩重度/kN·m-3;H为隧道埋深/m;Bt为坑道宽度/m,λ为侧压力系数,θ为围岩摩擦角/°;(2) For shallow tunnels, calculate the vertical surrounding rock pressure q: In the formula, q is the vertical uniform load/kN m -2 , γ is the weight of surrounding rock over the tunnel/kN m -3 ; H is the buried depth of the tunnel/m; B t is the tunnel width/m, and λ is the lateral pressure Coefficient, θ is the friction angle of surrounding rock/°;
(3)其中,侧压力系数λ:(3) Among them, the lateral pressure coefficient λ:
式中:β为破裂面与水平面的夹角/°,为围岩计算摩擦角/°,进而得出: In the formula: β is the angle/° between the rupture surface and the horizontal plane, Calculating the friction angle/° for the surrounding rock yields:
水平侧压力为: The horizontal lateral pressure is:
式中H为隧道埋深/m,h为隧道高度/m; In the formula, H is the buried depth of the tunnel/m, and h is the tunnel height/m;
(4)根据围岩级别按规范推荐取值得到γ、和λ值,根据设计图纸计算得到θ度数,最终求得水平围岩压力与垂直围岩压力。(4) γ, and λ value, the θ degree is calculated according to the design drawings, and finally the horizontal surrounding rock pressure and vertical surrounding rock pressure are obtained.
根据隧道实测的数据得到的监测点的收敛变形量来确定围岩级别,并由围岩级别根据规范推荐取值得到相关系数及围岩计算摩擦角数值,带入水平围岩压力和垂直围岩压力的计算式得到压力值。The grade of the surrounding rock is determined according to the convergent deformation of the monitoring point obtained from the actual measurement data of the tunnel, and the correlation coefficient and the calculated friction angle value of the surrounding rock are obtained from the grade of the surrounding rock according to the value recommended by the code, and the horizontal surrounding rock pressure and the vertical surrounding rock pressure are taken into account. The calculation formula of pressure obtains the pressure value.
与现有技术相比,本发明的有益效果:Compared with prior art, the beneficial effect of the present invention:
该计算方法通过分析双侧壁导坑法隧道施工中侧壁围岩的收敛变形与围岩压力之间的关系,建立结构力学模型,由现场监测数据反算求得水平围岩压力与垂直围岩压力,相较于现有依赖经验参数的计算方法,更准确、更能代表隧道的实际围岩压力,且隧道的收敛变形数据更易获得、计算方便精确。This calculation method analyzes the relationship between the convergence deformation of the surrounding rock of the side wall and the pressure of the surrounding rock in the tunnel construction of the double-side-wall pilot pit method, establishes a structural mechanics model, and calculates the horizontal surrounding rock pressure and the vertical surrounding rock pressure from the on-site monitoring data. Compared with the existing calculation method that relies on empirical parameters, the rock pressure is more accurate and can better represent the actual surrounding rock pressure of the tunnel, and the convergence deformation data of the tunnel is easier to obtain and the calculation is convenient and accurate.
附图说明:Description of drawings:
图1为现有双侧壁导坑法施工示意图。Figure 1 is a schematic diagram of the construction of the existing double-side-wall pilot pit method.
图2为本发明左导坑上台阶简化模型图。Fig. 2 is a simplified model diagram of the steps on the left pilot pit of the present invention.
图3超静定梁受到的水平方向荷载的模型图。Figure 3 is a model diagram of a statically indeterminate beam subjected to horizontal loads.
图4超静定梁受到的垂直荷载的模型图。Fig. 4 Model diagram of statically indeterminate beam subjected to vertical load.
图5超静定拱受到的水平方向荷载模型图。Figure 5 is a model diagram of the statically indeterminate arch subjected to horizontal loads.
图6超静定拱受到的垂直荷载模型图。Fig. 6 The vertical load model diagram of the statically indeterminate arch.
图7超静定梁荷载计算模型图。Figure 7 is a statically indeterminate beam load calculation model diagram.
图8超静定拱荷载计算模型图。Fig. 8 Calculation model diagram of statically indeterminate arch load.
图中标记:1-左导坑上台阶,2-左导下台阶,3-右导坑上台阶,4-右导下台阶,5-中导坑上台阶,6-中导坑下台阶,7-左导坑上台阶收敛观测点,8-上下台阶分界线,9-第一层初期支护,10-第二层初期支护。Markings in the picture: 1-step up the left guide pit, 2-step down the left guide pit, 3-step up the right guide pit, 4-step down the right guide pit, 5-up the step in the middle guide pit, 6-down the step in the middle guide pit, 7- Observation point for the convergence of the upper steps of the left pilot pit, 8- the boundary line between the upper and lower steps, 9- the initial support of the first layer, 10- the initial support of the second layer.
具体实施方式detailed description
下面结合试验例及具体实施方式对本发明作进一步的详细描述。但不应将此理解为本发明上述主题的范围仅限于以下的实施例,凡基于本发明内容所实现的技术均属于本发明的范围。The present invention will be further described in detail below in conjunction with test examples and specific embodiments. However, it should not be understood that the scope of the above subject matter of the present invention is limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.
实施例Example
如图1至图8所示,本实施例以某城市公路隧道为例进行计算,隧道埋深为7.21m~13.45m,隧道宽12m,隧道洞身为Ⅴ级围岩,采用双侧壁导坑法分部开挖,该隧道的围岩压力计算方法包括以下步骤:As shown in Figures 1 to 8, this embodiment takes a certain urban highway tunnel as an example for calculation. The pit method is excavated in parts, and the calculation method of the surrounding rock pressure of the tunnel includes the following steps:
(1)选取围岩的收敛变形监测点:如图1所示,将隧道分为6个部分依次进行开挖,分别为左导坑上台阶1、左导坑下台阶2、右导坑上台阶3、右导坑下台阶4、中导坑上台阶5、中导坑下台阶6和上下台阶分界线8,本实施例选取左导坑上台阶收敛观测点7为检测位置,在施工过程中设有外层的第一层初期支护9、内层的第二层初期支护10,本实施例选取图中①部开挖导洞后,选取按开挖导洞掌子面上的点为收敛变形的监测点,该导洞的开挖宽度为5.16m,即隧道宽度Bt=5.16m,按荷载等效高度的判定该隧道为浅埋还是深埋隧道:(1) Select the monitoring points for the convergence deformation of the surrounding rock: as shown in Figure 1, the tunnel is divided into six parts for excavation in sequence, namely, the upper step 1 of the left pilot pit, the lower step 2 of the left pilot pit, and the upper step of the right pilot pit. Step 3, the lower step 4 of the right pilot pit, the upper step 5 of the middle pilot pit, the lower step 6 of the middle pilot pit, and the boundary line 8 of the upper and lower steps. In this embodiment, the convergence observation point 7 of the upper step of the left pilot pit is selected as the detection position. The first layer of primary support 9 of the outer layer and the second layer of primary support 10 of the inner layer are arranged in the middle. Point is the monitoring point for convergence deformation. The excavation width of the pilot tunnel is 5.16m, that is, the tunnel width B t =5.16m. According to the load equivalent height, the tunnel is shallow or deep:
Hp=(2~2.5)hq,式中Hp为浅埋隧道分界深度/m,hq荷载等效高度/m,且hq=0.45×2s-1ω,其中S为围岩级别、本实施例S=5,ω为宽度影响系数,ω=1+i(B-5),B为隧道宽度/m,本实施例为Bt=5.16m,i为B每增减1m时的围岩压力增减率,以B=5m的围岩垂直均布压力为准,当B<5m时,取i=0.2;B>5m时,取i=0.1;由于为Ⅴ级围岩,Hp=2.5hq,因此得到:H p =(2~2.5)h q , where H p is the shallow tunnel boundary depth/m, h q load equivalent height/m, and h q =0.45×2 s-1 ω, where S is the surrounding rock Level, this embodiment S=5, ω is the width influence coefficient, ω=1+i(B-5), B is the tunnel width/m, this embodiment is B t =5.16m, i is every increase or decrease of B by 1m The increase and decrease rate of the surrounding rock pressure is based on the vertical uniform pressure of the surrounding rock with B=5m. When B<5m, take i=0.2; when B>5m, take i=0.1; , H p =2.5h q , thus:
hq=0.45×2s-1ω=7.32m,Hp=2.5hq=18.29m,因此该隧道为浅埋隧道。h q =0.45×2 s-1 ω=7.32m, H p =2.5h q =18.29m, so the tunnel is a shallow buried tunnel.
(2)在该监测点构造结构力学模型:(2) Construct a structural mechanics model at the monitoring point:
建立模型时做以下假设:将左导坑上台阶视为扇形;上台阶右壁及圆拱部分简化为刚性材料;简化模型各节点视为刚性连接。The following assumptions are made when building the model: the upper step of the left pilot pit is regarded as a fan shape; the right wall and round arch of the upper step are simplified as rigid materials; each node of the simplified model is regarded as a rigid connection.
因此,如图2所示,将监测点两侧分别视为超静定梁和超静定拱进行分析,分别计算超静定梁和超静定拱的位移量来得到监测点的收敛变形。Therefore, as shown in Figure 2, the two sides of the monitoring point are regarded as statically indeterminate beams and statically indeterminate arches for analysis, and the displacements of the statically indeterminate beams and statically indeterminate arches are calculated to obtain the convergent deformation of the monitoring points.
监测点的超静定梁的位移计算包括以下步骤:The displacement calculation of the statically indeterminate beam at the monitoring point includes the following steps:
1)如图3和图4所示,首先分析超静定梁所受荷载:超静定梁所受荷载ql为水平荷载qs和垂直荷载qc在垂直于梁方向的分量之和,即ql=qs·sinα+qc·cosα,并将荷载ql分为均布荷载ql1、线性荷载ql2,其中α为扇形的两半径之间的夹角;由于梁两端为固结,不受轴向荷载影响,故只考虑水平荷载和垂直荷载在垂直于梁方向荷载的作用;1) As shown in Figure 3 and Figure 4, first analyze the load on the statically indeterminate beam: the load q l on the statically indeterminate beam is the sum of the components of the horizontal load q s and the vertical load q c in the direction perpendicular to the beam, That is, q l = q s ·sinα+q c ·cosα, and the load q l is divided into uniform load q l1 and linear load q l2 , where α is the angle between the two radii of the sector; since the two ends of the beam are Consolidation is not affected by axial load, so only the effect of horizontal load and vertical load on the load perpendicular to the beam direction is considered;
2)分别列出荷载ql1、ql2的计算式:2) List the calculation formulas of loads q l1 and q l2 respectively:
计算ql1时:When calculating q l1 :
如图3和图4所示,按结构力学的力法原理计算超静定梁在x方向上任意位置的弯矩:式中r为扇形的半径,M(x)为x方向的弯矩;As shown in Figure 3 and Figure 4, the bending moment of the statically indeterminate beam at any position in the x direction is calculated according to the force method principle of structural mechanics: In the formula, r is the radius of the sector, and M(x) is the bending moment in the x direction;
根据材料力学中弯矩与挠度的关系式:其中EI为常数,ω为变形量;According to the relationship between bending moment and deflection in material mechanics: Where EI is a constant, ω is the amount of deformation;
对弯矩求二重积分得到:Double integrating the bending moment yields:
ωl1(x)·EI=∫∫[M(x)dx]dx+C1x+D1,式中ωl1(x)为监测点受ql1荷载在y方向上的位移量,由于梁与拱为固结,所以ω(0)=0、ω(r)=0,代入上式计算可得:ω l1 (x)·EI=∫∫[M(x)dx]dx+C 1 x+D 1 , where ω l1 (x) is the displacement of the monitoring point in the y direction under the q l1 load, because the beam It is consolidated with the arch, so ω(0)=0, ω(r)=0, which can be calculated by substituting into the above formula:
而ql1=qc·cosα+e1 sinα,其中e1为隧道顶水平侧压力/kPa,得出ql1的值,进而得出在荷载ql1作用下超静定梁的位移量ωl1; And q l1 = q c ·cosα+e 1 sinα, where e1 is the horizontal lateral pressure of the tunnel top/kPa, the value of q l1 is obtained, and then the displacement of the statically indeterminate beam under the load q l1 is obtained ω l1 ;
计算ql2的值:Calculate the value of q l2 :
按结构力学的力法原理计算超静定梁上任意位置x处的弯矩:Calculate the bending moment at any position x on the statically indeterminate beam according to the force method principle of structural mechanics:
对弯矩求二重积分可得: Taking the double integral over the bending moment gives:
式中ωl2(x)为监测点受ql2荷载在y方向上的位移量;而ql2=(e2-e1)·sinα,式中e2为隧道底水平侧压力/kPa,得出在荷载ql2作用下超静定梁的位移量,进而得到超静定梁的总位移量ωl。 In the formula, ω l2 (x) is the displacement of the monitoring point in the y direction under the q l2 load; and q l2 = (e 2 -e 1 ) sinα, where e 2 is the horizontal side pressure of the tunnel bottom/kPa, Calculate the displacement of the statically indeterminate beam under the action of load q l2 , and then obtain the total displacement of the statically indeterminate beam ω l .
而监测点的超静定拱的位移计算包括以下步骤:The displacement calculation of the hyperstatically indeterminate arch at the monitoring point includes the following steps:
(a)如图5至图8所示,将超静定拱所受水平方向荷载分解为均布荷载q1、线性荷载q2,还包括竖直方向的荷载q3;将超静定拱与水平面的交点受到的水平方向的约束荷载记为x3,竖直方向荷载记为x2,该交点收到的扭矩记为x1;(a) As shown in Fig. 5 to Fig. 8, decompose the horizontal load on the statically indeterminate arch into uniform load q 1 , linear load q 2 , and vertical load q 3 ; The horizontal restraint load received by the intersection with the horizontal plane is recorded as x 3 , the vertical load is recorded as x 2 , and the torque received by the intersection point is recorded as x 1 ;
(b)根据超静定拱与水平面的交点为刚性连接节点的特性,得出该交点在三个方向上的单位荷载作用下的位移关系:(b) According to the characteristic that the intersection point of the statically indeterminate arch and the horizontal plane is a rigid connection node, the displacement relationship of the intersection point under the unit load in three directions is obtained:
根据刚性连接点可得出:According to the rigid connection point, it can be obtained that:
式中Δiq为由荷载q产生的沿xi方向的位移,δij为由单位力xj=1产生的沿xi方向的位移,其中i=1、2或3,j=1、2或3,且根据该刚性连接点的特性,δ12=δ21、δ13=δ31、δ23=δ32; In the formula, Δiq is the displacement along the direction of x i produced by the load q, and δ ij is the displacement along the direction of x i produced by the unit force x j =1, where i=1, 2 or 3, j=1, 2 or 3, and according to the characteristics of the rigid connection point, δ 12 =δ 21 , δ 13 =δ 31 , δ 23 =δ 32 ;
而计算超静定拱任意点的位移δij时:And when calculating the displacement δ ij of any point of the statically indeterminate arch:
式中r为扇形半径,α为扇形的两半径之间的夹角; In the formula, r is the radius of the sector, and α is the angle between the two radii of the sector;
而分别计算在荷载q1、q2、q3作用下的位移Δiq:And calculate the displacement Δiq under the action of loads q 1 , q 2 , q 3 respectively:
利用上式可求得荷载q1、q2、q3作用下的约束x1、x2、x3,然后可求得拱上任意点的弯矩:The constraints x 1 , x 2 , x 3 under the loads q 1 , q 2 , q 3 can be obtained by using the above formula, and then the bending moment at any point on the arch can be obtained:
,对弯矩M(x)求二重积分可得:, the double integral of the bending moment M(x) can be obtained:
式中 C2为、D2为对弯矩求二重积分过程中产生的常系数; In the formula C 2 and D 2 are the constant coefficients generated in the process of calculating the double integral of the bending moment;
将ω(0)=0、ω(α)=0代入上式,可求得C2、D2,得出超静定拱的位移量ωg,监测点的收敛变形为超静定梁与超静定拱的位移变形之和:ω=ωl·sinα+ωg;Substituting ω(0)=0 and ω(α)=0 into the above formula, C 2 and D 2 can be obtained, and the displacement ω g of the statically indeterminate arch can be obtained. The convergence deformation of the monitoring point is the statically indeterminate beam and The sum of displacement and deformation of statically definite arch: ω=ω l sinα+ω g ;
判断隧道为浅埋隧道时,计算其垂直围岩压力q:式中q为垂直均布荷载/kN·m-2,γ为隧道上覆围岩重度/kN·m-3;H为隧道埋深/m;Bt为坑道宽度/m,λ为侧压力系数,θ为围岩摩擦角/°;When the tunnel is judged to be shallow buried, calculate its vertical surrounding rock pressure q: In the formula, q is the vertical uniform load/kN m -2 , γ is the weight of surrounding rock over the tunnel/kN m -3 ; H is the buried depth of the tunnel/m; B t is the tunnel width/m, and λ is the lateral pressure Coefficient, θ is the friction angle of surrounding rock/°;
其中,侧压力系数λ:Among them, the lateral pressure coefficient λ:
式中:β为破裂面与水平面的夹角/°,为围岩计算摩擦角/°,进而得出: In the formula: β is the angle/° between the rupture surface and the horizontal plane, Calculating the friction angle/° for the surrounding rock yields:
水平侧压力为: The horizontal lateral pressure is:
式中H为隧道埋深/m,h为隧道高度/m; In the formula, H is the buried depth of the tunnel/m, and h is the tunnel height/m;
将本实施例的数据带入得到,开挖过程中的累计变形ω(x)=15.5mm,隧道埋深H=13.31m,EI=7.354×106N·m2,而隧道为Ⅴ级围岩,按规范推荐取值,隧道上覆围岩重度γ=19kN·m-3,参考设计图纸计算可得模型右壁与水平面夹角θ=71.68°,代入上述计算式求得:Bringing in the data of this example, the accumulated deformation during the excavation process ω(x)=15.5mm, the buried depth of the tunnel H=13.31m, EI=7.354×10 6 N·m 2 , and the tunnel is of Class V enclosure. According to the value recommended by the code, the weight of surrounding rock on the tunnel is γ=19kN·m -3 , and the angle between the right wall of the model and the horizontal plane is θ=71.68° calculated by referring to the design drawings, which can be obtained by substituting the above calculation formula:
λ=0.19,q=199.41kPa,e1=47.35kPa,e2=17.22kPa, λ = 0.19, q = 199.41kPa, e 1 = 47.35kPa, e 2 = 17.22kPa,
公路隧道设计规范中Ⅴ级围岩计算摩擦角的建议取值区间为40°~50°,下表为分别取40°、45°、50°时根据规范计算求得的垂直围岩压力和水平围岩压力值:Calculation of Friction Angle of Level Ⅴ Surrounding Rock in Code for Design of Highway Tunnel The recommended range of values is 40°~50°, the table below is The values of vertical surrounding rock pressure and horizontal surrounding rock pressure calculated according to the code when taking 40°, 45° and 50° respectively:
由该表可以看到,由本方案的计算方法求得的围岩压力在按《公路隧道设计规范》计算结果范围内,证明该方法可行,且精确度较高。It can be seen from the table that the surrounding rock pressure obtained by the calculation method of this scheme is within the range of calculation results according to the "Code for Design of Highway Tunnels", which proves that the method is feasible and has high accuracy.
本实施例的计算方法通过分析双侧壁导坑法隧道施工中侧壁围岩的收敛变形与围岩压力之间的关系,建立结构力学模型,由现场监测数据反算求得水平围岩压力与垂直围岩压力,相较于现有依赖经验参数的计算方法,更准确、更能代表隧道的实际围岩压力,且隧道的收敛变形数据更易获得、计算方便精确。The calculation method of this embodiment establishes a structural mechanics model by analyzing the relationship between the convergence deformation of the surrounding rock of the side wall and the pressure of the surrounding rock in the tunnel construction of the double-side pilot pit method, and obtains the horizontal surrounding rock pressure by back-calculating the on-site monitoring data. Compared with the existing calculation method relying on empirical parameters, it is more accurate and can better represent the actual surrounding rock pressure of the tunnel, and the convergence deformation data of the tunnel is easier to obtain and the calculation is convenient and accurate.
本说明书中公开的所有特征,或公开的所有方法或过程中的步骤,除了互相排斥的特征和/或步骤以外,均可以以任何方式组合。All features disclosed in this specification, or steps in all methods or processes disclosed, may be combined in any manner, except for mutually exclusive features and/or steps.
本说明书(包括任何附加权利要求、摘要和附图)中公开的任一特征,除非特别叙述,均可被其他等效或具有类似目的的替代特征加以替换。即,除非特别叙述,每个特征只是一系列等效或类似特征中的一个例子而已。Any feature disclosed in this specification (including any appended claims, abstract and drawings), unless expressly stated otherwise, may be replaced by alternative features which are equivalent or serve a similar purpose. That is, unless expressly stated otherwise, each feature is one example only of a series of equivalent or similar features.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610958955.7A CN106644206B (en) | 2016-11-03 | 2016-11-03 | A method for calculating surrounding rock pressure for shallow tunnels |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610958955.7A CN106644206B (en) | 2016-11-03 | 2016-11-03 | A method for calculating surrounding rock pressure for shallow tunnels |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106644206A true CN106644206A (en) | 2017-05-10 |
| CN106644206B CN106644206B (en) | 2019-07-26 |
Family
ID=58821761
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610958955.7A Expired - Fee Related CN106644206B (en) | 2016-11-03 | 2016-11-03 | A method for calculating surrounding rock pressure for shallow tunnels |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106644206B (en) |
Cited By (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107165640A (en) * | 2017-07-06 | 2017-09-15 | 王胜利 | Tunnels and underground engineering surely builds method certainly |
| CN107194136A (en) * | 2017-07-31 | 2017-09-22 | 中国水利水电第七工程局成都水电建设工程有限公司 | A kind of pressure from surrounding rock computational methods suitable for many stratum shallow tunnels |
| CN107256321A (en) * | 2017-08-10 | 2017-10-17 | 长安大学 | A kind of Tunnel Surrounding Rock Pressure based on steelframe measured stress determines method |
| CN108801505A (en) * | 2018-06-11 | 2018-11-13 | 中国科学院武汉岩土力学研究所 | The cell cube method and device that Disturbance stress measures |
| CN109543283A (en) * | 2018-11-20 | 2019-03-29 | 成都天佑智隧科技有限公司 | A kind of internal force based on structure convergent deformation and calculating of surrounding rock pressure method |
| CN109684744A (en) * | 2018-12-27 | 2019-04-26 | 石家庄铁道大学 | A kind of calculation method of soft rock tunnel pressure from surrounding rock |
| CN110096833A (en) * | 2019-05-13 | 2019-08-06 | 中铁二院工程集团有限责任公司 | A kind of country rock load calculation method suitable for concordant unsymmetrial loading tunnel |
| CN111141601A (en) * | 2019-12-24 | 2020-05-12 | 长安大学 | Shallow-buried ultra-large-span tunnel partition wall structure stress safety inspection scheme |
| CN112302664A (en) * | 2020-11-17 | 2021-02-02 | 中冶建工集团有限公司 | Excavation construction method for super-large section shallow-buried surrounding rock double-layer primary support tunnel |
| CN112632668A (en) * | 2020-12-18 | 2021-04-09 | 中国电建集团贵阳勘测设计研究院有限公司 | Shallow tunnel surrounding rock pressure calculation method under secondary failure mode |
| CN112668904A (en) * | 2020-12-31 | 2021-04-16 | 河南华能联合电力建设有限公司 | Accurate detection method and system for electric power underground construction channel |
| CN112924059A (en) * | 2021-01-26 | 2021-06-08 | 上海同岩土木工程科技股份有限公司 | Strip-type surrounding rock pressure monitoring device, monitoring method and installation method |
| CN115033950A (en) * | 2022-04-12 | 2022-09-09 | 长安大学 | Method for calculating surrounding rock pressure and increase and decrease rate of super-large-span tunnel considering partial excavation |
| CN119047031A (en) * | 2024-08-05 | 2024-11-29 | 西南交通大学 | Tunnel deformation rapid analysis method based on surrounding rock corrosion-expansion mechanical effect |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1990001139A1 (en) * | 1988-07-19 | 1990-02-08 | Gianangelo Cargnel | A self-calibrating electronic pressure transducer for lined tunnels |
| CN1912342A (en) * | 2005-08-09 | 2007-02-14 | 同济大学 | Method for determining load of multiple-arch tunnel |
| CN102982247A (en) * | 2012-12-05 | 2013-03-20 | 浙江科技学院 | Surrounding rock stress analysis method of arbitrarily excavated cross section tunnels |
| CN103075195A (en) * | 2012-12-28 | 2013-05-01 | 西北大学 | Measurement system and method for stress of surrounding rock of hipparion red soil tunnel under influence of crack water |
| CN104989456A (en) * | 2015-07-24 | 2015-10-21 | 青岛理工大学 | Large-span underground engineering surrounding rock excavation stability monitoring and early warning method |
| CN105138767A (en) * | 2015-08-23 | 2015-12-09 | 北京工业大学 | Deep-buried asymmetric closely spaced tunnel surrounding rock pressure calculation method |
-
2016
- 2016-11-03 CN CN201610958955.7A patent/CN106644206B/en not_active Expired - Fee Related
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1990001139A1 (en) * | 1988-07-19 | 1990-02-08 | Gianangelo Cargnel | A self-calibrating electronic pressure transducer for lined tunnels |
| CN1912342A (en) * | 2005-08-09 | 2007-02-14 | 同济大学 | Method for determining load of multiple-arch tunnel |
| CN102982247A (en) * | 2012-12-05 | 2013-03-20 | 浙江科技学院 | Surrounding rock stress analysis method of arbitrarily excavated cross section tunnels |
| CN103075195A (en) * | 2012-12-28 | 2013-05-01 | 西北大学 | Measurement system and method for stress of surrounding rock of hipparion red soil tunnel under influence of crack water |
| CN104989456A (en) * | 2015-07-24 | 2015-10-21 | 青岛理工大学 | Large-span underground engineering surrounding rock excavation stability monitoring and early warning method |
| CN105138767A (en) * | 2015-08-23 | 2015-12-09 | 北京工业大学 | Deep-buried asymmetric closely spaced tunnel surrounding rock pressure calculation method |
Non-Patent Citations (4)
| Title |
|---|
| 刘志宝等: "岩土工程中位移反分析方法及其进展", 《路基工程》 * |
| 周锋: "大断面浅埋暗挖隧道施工方法及其稳定性研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 * |
| 李宁: "大断面黄土隧道双侧壁导坑法的力学行为研究", 《铁道标准设计》 * |
| 龚建伍等: "浅埋小净距隧道围岩压力计算与监测分析", 《岩石力学与工程学报》 * |
Cited By (20)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107165640A (en) * | 2017-07-06 | 2017-09-15 | 王胜利 | Tunnels and underground engineering surely builds method certainly |
| CN107194136A (en) * | 2017-07-31 | 2017-09-22 | 中国水利水电第七工程局成都水电建设工程有限公司 | A kind of pressure from surrounding rock computational methods suitable for many stratum shallow tunnels |
| CN107256321B (en) * | 2017-08-10 | 2020-11-10 | 长安大学 | Tunnel surrounding rock pressure determination method based on steel frame actual measurement stress |
| CN107256321A (en) * | 2017-08-10 | 2017-10-17 | 长安大学 | A kind of Tunnel Surrounding Rock Pressure based on steelframe measured stress determines method |
| CN108801505A (en) * | 2018-06-11 | 2018-11-13 | 中国科学院武汉岩土力学研究所 | The cell cube method and device that Disturbance stress measures |
| CN108801505B (en) * | 2018-06-11 | 2019-11-29 | 中国科学院武汉岩土力学研究所 | The cell cube method and device of Disturbance stress measurement |
| CN109543283A (en) * | 2018-11-20 | 2019-03-29 | 成都天佑智隧科技有限公司 | A kind of internal force based on structure convergent deformation and calculating of surrounding rock pressure method |
| CN109543283B (en) * | 2018-11-20 | 2023-08-25 | 成都天佑智隧科技有限公司 | Internal force and confining pressure calculation method based on structural convergence deformation |
| CN109684744A (en) * | 2018-12-27 | 2019-04-26 | 石家庄铁道大学 | A kind of calculation method of soft rock tunnel pressure from surrounding rock |
| CN110096833B (en) * | 2019-05-13 | 2022-09-09 | 中铁二院工程集团有限责任公司 | Surrounding rock load calculation method suitable for bedding bias tunnel |
| CN110096833A (en) * | 2019-05-13 | 2019-08-06 | 中铁二院工程集团有限责任公司 | A kind of country rock load calculation method suitable for concordant unsymmetrial loading tunnel |
| CN111141601A (en) * | 2019-12-24 | 2020-05-12 | 长安大学 | Shallow-buried ultra-large-span tunnel partition wall structure stress safety inspection scheme |
| CN112302664A (en) * | 2020-11-17 | 2021-02-02 | 中冶建工集团有限公司 | Excavation construction method for super-large section shallow-buried surrounding rock double-layer primary support tunnel |
| CN112632668A (en) * | 2020-12-18 | 2021-04-09 | 中国电建集团贵阳勘测设计研究院有限公司 | Shallow tunnel surrounding rock pressure calculation method under secondary failure mode |
| CN112668904A (en) * | 2020-12-31 | 2021-04-16 | 河南华能联合电力建设有限公司 | Accurate detection method and system for electric power underground construction channel |
| CN112924059A (en) * | 2021-01-26 | 2021-06-08 | 上海同岩土木工程科技股份有限公司 | Strip-type surrounding rock pressure monitoring device, monitoring method and installation method |
| CN112924059B (en) * | 2021-01-26 | 2022-09-23 | 上海同岩土木工程科技股份有限公司 | Strip-type surrounding rock pressure monitoring device, monitoring method and installation method |
| CN115033950A (en) * | 2022-04-12 | 2022-09-09 | 长安大学 | Method for calculating surrounding rock pressure and increase and decrease rate of super-large-span tunnel considering partial excavation |
| CN115033950B (en) * | 2022-04-12 | 2025-04-22 | 长安大学 | Calculation method of surrounding rock pressure and increase/decrease rate of super-long span tunnel considering partial excavation |
| CN119047031A (en) * | 2024-08-05 | 2024-11-29 | 西南交通大学 | Tunnel deformation rapid analysis method based on surrounding rock corrosion-expansion mechanical effect |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106644206B (en) | 2019-07-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106644206A (en) | Method for calculating surrounding rock pressure of shallow tunnel | |
| Bao et al. | Numerical analysis of seismic response of a circular tunnel-rectangular underpass system in liquefiable soil | |
| Tang et al. | A novel approach for determining landslide pushing force based on landslide-pile interactions | |
| Ding et al. | Model tests on the bearing capacity of wide-shallow composite bucket foundations for offshore wind turbines in clay | |
| Marshall et al. | Tunneling beneath driven or jacked end-bearing piles in sand | |
| Mu et al. | Small strain based method for predicting three-dimensional soil displacements induced by braced excavation | |
| Jongpradist et al. | Development of tunneling influence zones for adjacent pile foundations by numerical analyses | |
| Xu et al. | Response of framed buildings on raft foundations to tunneling | |
| CN106638537A (en) | Method for calculating soil pressure of limited soil | |
| Unsever et al. | Behaviour of model pile foundations under dynamic loads in saturated sand | |
| Chakraborty et al. | Physical and numerical analysis of reinforced soil wall on clayey foundation under repetitive loading: effect of fineness modulus of backfill material | |
| Wotzlaw et al. | Numerical analysis of deep vibrocompaction at small and full scale | |
| CN118262814A (en) | Analysis method and system for influence of seepage on excavation deformation of deep buried layer surrounding rock tunnel | |
| Ye et al. | LSTM-based deformation forecasting for additional stress estimation of existing tunnel structure induced by adjacent shield tunneling | |
| Xu et al. | Supporting behavior evolution of ultra-deep circular diaphragm walls during excavation: Monitoring and assessment methods comparison | |
| Belhassena et al. | Estimation of bending moment and pile displacement for soil-pile-quay wall system subjected to liquefaction induced lateral spreading | |
| Zhou et al. | A lateral soil resistance model for XCC pile in soft clay considering the effect of the geometry of cross section | |
| Tang et al. | Calculation of pressure on the shallow-buried double-arch tunnel without middle drift | |
| Wang et al. | Axial response of short pile due to tunnelling-induced soil movement in soft clay | |
| Ouyang et al. | Second-order analysis of steel sheet piles by pile element considering nonlinear soil-structure interactions | |
| CN110263448A (en) | A kind of prediction technique that twin tunnel excavation influences neighbouring geographical pipeline | |
| CN107657092B (en) | Building inclination correcting method for foundation drilling and soil taking | |
| Jia et al. | Seismic behavior and failure mechanism of pile-group in mildly sloping liquefiable soils with crusts: Large-scale shaking table experiment | |
| CN119066905A (en) | A method and system for calculating surrounding rock pressure of deep buried tunnel in kaolinized alteration zone | |
| Hu et al. | Optimization-based model of tunneling-induced distributed loads acting on the shield periphery |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190726 Termination date: 20201103 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |